HOUSTON, Aug. 3, 2012 /PRNewswire/ -- Cheniere Energy, Inc. ("Cheniere") (NYSE MKT: LNG) reported a net loss of $73.0 million, or $0.43 per share (basic and diluted), for the three months ended June 30, 2012, compared to a net loss of $47.2 million, or $0.67 per share (basic and diluted), for the comparable 2011 period.  For the six months ended June 30, 2012, Cheniere reported a net loss of $129.5 million, or $0.86 per share (basic and diluted) compared to a net loss of $87.0 million, or $1.26 per share (basic and diluted), during the corresponding period of 2011.  Results include significant items of $35.7 million, or $0.21 per share, for the three months ended June 30, 2012 and $58.0 million, or $0.38 per share, for the six months ended June 30, 2012 related to LNG terminal and pipeline development expenses primarily for the Sabine Pass Liquefaction Project ("Liquefaction Project") currently under development and for losses due to the early extinguishment of debt incurred in both periods. 

(Logo: https://photos.prnewswire.com/prnh/20090611/AQ31545LOGO)

Results are reported on a consolidated basis and include our ownership interest in Cheniere Energy Partners, L.P. ("Cheniere Partners"), which was 89.3% as of June 30, 2012.

Overview of Recent Significant 2012 Events

  • In May 2012, we sold 31.0 million shares of our common stock for net proceeds of $468.1 million to Havelock Fund Investments Pte. Ltd. (indirectly owned by Temasek Holdings (Private) Limited) and Greenwich Asset Holding Ltd. (owned by RRJ Capital Master Fund I, L.P.).  The proceeds were used along with cash on hand to purchase $500 million of Cheniere Partners' Class B units ("Class B Units") of which $167 million were purchased in June 2012 and $333 million were purchased in July 2012.
  • In June 2012, we repaid in full $284.5 million of the outstanding principal and accrued interest under the 2008 Term Loans.
  • In July 2012, we sold 28.0 million shares of Cheniere common stock in an underwritten public offering for net cash proceeds of $380.3 million
  • In August 2012, we repaid in full the entire outstanding principal balance plus accrued interest payable totaling $206.9 million under the Convertible Senior Unsecured Notes.
  • Cheniere Partners made significant progress on the Liquefaction Project, including the following:
    • In April 2012, Sabine Pass Liquefaction, LLC ("SPL") received authorization under Section 3 of the Natural Gas Act (the "Order") from the FERC to site, construct and operate facilities for the liquefaction and export of domestically produced natural gas at the Sabine Pass LNG terminal located in Cameron Parish, Louisiana.  The Order authorizes the development of up to four modular LNG trains;
    • In May 2012, Cheniere Partners received commitments for $2.0 billion of equity financing for the Liquefaction Project.  Cheniere Partners and Blackstone CQP Holdco LP ("Blackstone") entered into a unit purchase agreement whereby Cheniere Partners agreed to sell to Blackstone in a private placement 100 million Class B Units for $1.5 billion. We also entered into a unit purchase agreement with Cheniere Partners whereby we agreed to purchase 33.3 million Class B Units for $500 million;
    • In June 2012, we purchased $167 million of Class B Units and Cheniere Partners issued a limited notice to proceed to Bechtel Oil, Gas and Chemicals, Inc. ("Bechtel") for the Liquefaction Project;
    • In July 2012, Cheniere Partners announced that its Board of Directors made a positive final investment decision on the development and construction of the first two liquefaction trains;
    • In July 2012, Cheniere Partners closed on a $3.6 billion credit facility that will be used to fund the first two trains of the Liquefaction Project.  The credit facility has a 7 year maturity and interest rate of LIBOR plus 350 basis points during construction and then steps up to LIBOR plus 375 basis points during operations; and
    • In July 2012, we purchased the remaining $333 million of our $500 million equity commitment in Class B Units from Cheniere Partners.  

Results

Cheniere reported a loss from operations of $6.1 million and $5.4 million for the three and six months ended June 30, 2012, respectively, compared to income from operations of $16.5 million and $40.0 million for the comparable periods in 2011.  The decrease in income from operations of $22.6 million and $45.4 million for the three and six months ended June 30, 2012, respectively, was primarily a result of increased LNG terminal and pipeline development expenses, increased LNG terminal and pipeline operating expenses and decreased marketing and trading revenues.  LNG terminal and pipeline development expenses primarily include costs incurred to develop the Liquefaction Project.  LNG terminal and pipeline operating expenses increased primarily due to costs incurred for maintenance dredging during the second quarter of 2012.  Marketing and trading revenues were impacted in the three and six months ended June 30, 2012 by a loss recorded on a firm purchase commitment for LNG inventory needed to restore the heating value of vaporized LNG to meet natural gas pipeline specifications and less LNG export activity.  For the three and six months ended June 30, 2012, Cheniere recorded non-cash compensation expenses of $1.9 million and $4.2 million, respectively, compared to $6.3 million  and $14.4 million for the comparable periods in 2011. 

Loss on early extinguishment of debt of $14.6 million and $15.1 million for the three and six months ended June 30, 2012, respectively was primarily due to the repayment of the entire outstanding principal balance of the 2008 Loans due in 2018.  Interest expense, net decreased $8.7 million and $14.5 million for the three and six months ended June 30, 2012, respectively, compared to the same periods in 2011 primarily due to debt principal repayments made during the second quarter of 2012. 

Liquefaction Project Update

Cheniere Partners continues to make progress on the Liquefaction Project, which is being developed for up to four liquefaction trains, each with a nominal production capability of approximately 4.5 mtpa.

In July 2012, Cheniere Partners closed on a project credit facility of $3.6 billion. Including the recently announced $2.0 billion of equity commitments, Cheniere Partners has now secured financing of approximately $5.6 billion for the construction of the first two trains of the Liquefaction Project. Cheniere Partners' Board of Directors has made a positive final investment decision on the development and construction of the first two liquefaction trains.  Cheniere Partners  has received the remaining $333 million of the $500 million of funding through the purchase of 22.2 million Class B Units by us. Cheniere Partners will issue a full notice to proceed to Bechtel upon the receipt of initial funding from Blackstone.

LNG exports from the Sabine Pass LNG terminal are anticipated to commence as early as 2015, with the second liquefaction train commencing operations approximately six to nine months thereafter.

Commencement of construction for liquefaction trains three and four is subject, but not limited to, entering into an engineering, procurement and construction agreement, reaching a positive final investment decision and obtaining financing.  Cheniere Partners has engaged Bechtel to complete front-end engineering and design work for the third and fourth liquefaction trains and has begun negotiating a lump sum turnkey contract.  Construction for liquefaction trains three and four is targeted to begin in 2013.

 

Summary Liquefaction Project Timeline



Target Date


Milestone

Trains 1 & 2


Trains 3 & 4


DOE export authorization

Received


Received


Definitive commercial agreements

Completed 7.7 mtpa


Completed 8.3 mtpa


- BG Gulf Coast LNG, LLC

4.2 mtpa


1.3 mtpa


- Gas Natural Fenosa

3.5 mtpa




- KOGAS



3.5 mtpa


- GAIL (India) Ltd.



3.5 mtpa


EPC contract

Complete


4Q12


Financing commitments



1Q13


- Equity

Received




- Debt

Received




FERC authorization

Received


Received


- Certificate to commence construction

Received


2013


Issue full notice to proceed to Bechtel

3Q12


2013


Commence operations

2015/2016


2017/2018








Cheniere is a Houston-based energy company primarily engaged in LNG related businesses, and owns and operates the Sabine Pass LNG terminal and Creole Trail Pipeline in Louisiana. Cheniere is pursuing related business opportunities both upstream and downstream of the Sabine Pass LNG terminal.  Through its subsidiary, Cheniere Partners, Cheniere has initiated a project to add liquefaction services that would transform the Sabine Pass LNG terminal into a bi-directional facility capable of liquefying natural gas and exporting LNG in addition to importing and regasifying foreign-sourced LNG. As currently contemplated, the liquefaction project would be designed and permitted for up to four LNG trains, each with a nominal production capacity of approximately 4.5 million metric tons per annum  Additional information about Cheniere Energy, Inc. may be found on its web site at www.cheniere.com.

For additional information, please refer to the Cheniere Energy, Inc. Quarterly Report on Form 10-Q for the period ended June 30, 2012, filed with the Securities and Exchange Commission.

This press release contains certain statements that may include "forward-looking statements" within the meanings of Section 27A of the Securities Act of 1933 and Section 21E of the Securities Exchange Act of 1934. All statements, other than statements of historical fact, included herein are "forward-looking statements." Included among "forward-looking statements" are, among other things, (i) statements regarding Cheniere's business strategy, plans and objectives and (ii) statements expressing beliefs and expectations regarding the development of Cheniere's LNG terminal and pipeline businesses, including liquefaction facilities. Although Cheniere believes that the expectations reflected in these forward-looking statements are reasonable, they do involve assumptions, risks and uncertainties, and these expectations may prove to be incorrect.  Cheniere's actual results could differ materially from those anticipated in these forward-looking statements as a result of a variety of factors, including those discussed in Cheniere's periodic reports that are filed with and available from the Securities and Exchange Commission. You should not place undue reliance on these forward-looking statements, which speak only as of the date of this press release. Other than as required under the securities laws, Cheniere does not assume a duty to update these forward-looking statements.

(Financial Table Follows)

Cheniere Energy, Inc.

Selected Financial Information 

(in thousands, except per share data) (1)




Three Months Ended


Six Months Ended


June 30,


June 30,


2012


2011


2012


2011

Revenues








LNG terminal revenues

$

66,071



$

67,302



$

133,331



$

137,303


Marketing and trading

(4,007)



4,606



(1,349)



13,054


Oil and gas sales

264



884



814



1,653


Other



18



5



31


Total revenues

62,328



72,810



132,801



152,041










Operating costs and expenses








General and administrative expense

20,816



19,378



40,809



40,889


Depreciation, depletion and amortization

15,478



15,625



31,768



31,011


LNG terminal and pipeline operating expense

10,993



7,853



22,550



18,048


LNG terminal and pipeline development expense

21,088



13,356



42,907



21,793


Oil and gas production and exploration costs

74



137



166



275


Total operating costs and expenses

68,449



56,349



138,200



112,016


Income from operations

(6,121)



16,461



(5,399)



40,025










Other income (expense)








Interest expense, net

(55,864)



(64,587)



(114,215)



(128,741)


Loss on early extinguishment of debt

(14,593)





(15,100)




Derivative gain (loss), net

261



(448)



(575)



(448)


Other income

458



118



583



227


Total other income (expense)

(69,738)



(64,917)



(129,307)



(128,962)


Income (loss) before income taxes and non-controlling interest

(75,859)



(48,456)



(134,706)



(88,937)


Income tax provision

(144)





(150)




Income (loss) before non-controlling interest

(76,003)



(48,456)



(134,856)



(88,937)


Non-controlling interest

2,963



1,285



5,401



1,927


Net income (loss)

$

(73,040)



$

(47,171)



$

(129,455)



$

(87,010)










Net income (loss) per share attributable to common stockholders—

basic and diluted

$

(0.43)



$

(0.67)



$

(0.86)



$

(1.26)


Weighted average number of common shares outstanding—basic and diluted

171,001



70,630



151,054



68,800



As of June 30,


As of December 31,


2011


2010

Cash and cash equivalents

$

137,885



$

459,160


Restricted cash and cash equivalents

491,299



102,165


LNG inventory

2,319



6,562


Accounts and interest receivable

4,724



3,043


Prepaid expenses and other

19,103



20,522


Non-current restricted cash and cash equivalents

82,892



82,892


Property, plant and equipment, net

2,125,693



2,107,129


Debt issuance costs, net

15,480



33,356


Goodwill

76,819



76,819


Other assets

72,116



23,677


Total assets

$

3,028,330



$

2,915,325






Current liabilities

$

298,141



$

584,960


Long-term debt (including related party debt), net of discount

2,194,765



2,474,711


Deferred revenue

23,500



25,500


Other liabilities

3,015



3,146


Non-controlling interest

190,637



208,575


Stockholders' deficit

318,272



(381,567)


Total liabilities and deficit

$

3,028,330



$

2,915,325










 


Sabine

Pass LNG


Cheniere

Partners


    Other    

Cheniere


Consolidated

Cheniere

Cash and cash equivalents

$



$



$

137,885



$

137,885


Restricted cash and cash equivalents

98,630


(2)

168,448


(3)

307,113


(4)

574,191


Total

$

98,630



$

168,448



$

444,998



$

712,076


















As of June 30, 2012, we had unrestricted cash and cash equivalents of $137.9 million  available to Cheniere, which excludes cash and cash equivalents and other working capital available to Cheniere Partners and Sabine Pass LNG. In addition, we had restricted cash and cash equivalents of $574.2 million, which were designated for the following purposes: $301.4 million to purchase Class B Units from Cheniere Partners; $96.1 million for interest payments related to the Senior Notes; $2.5 million for Sabine Pass LNG's working capital; $168.4 million for Cheniere Partners' working capital; and $5.8 million for other restricted purposes.  

As of June 30, 2012, we had $204.6 million of current debt maturities because our Convertible Senior Unsecured Notes were due August 1, 2012.  On August 1, 2012, we used a portion of the net proceeds from the public offering of common stock in July 2012 to repay the full outstanding balance of the Convertible Senior Unsecured Notes, including the outstanding principal amount and accrued interest through August 1, 2012.

(1)  Please refer to the Cheniere Energy, Inc. Quarterly Report of Form 10-Q for the period ended June 30,   
       2012, filed with the Securities and Exchange Commission.

(2)  All cash and cash equivalents presented above for Sabine Pass LNG are considered restricted to us, but  
       $2.5 million is considered unrestricted for Sabine Pass LNG.

(3)  All cash and cash equivalents presented above for Cheniere Partners are considered restricted to us, but
      $171.0 million is considered unrestricted for Cheniere Partners, including the $2.5 million considered unrestricted for Sabine Pass LNG.

(4) Cash and cash equivalents of $301.4 million are considered restricted to us to purchase Class B Units of 
      Cheniere Partners.