Quarterly report pursuant to Section 13 or 15(d)

Nature of Operations and Basis of Presentation

v3.24.2.u1
Nature of Operations and Basis of Presentation
6 Months Ended
Jun. 30, 2024
Organization, Consolidation and Presentation of Financial Statements [Abstract]  
Nature of Operations and Basis of Presentation NATURE OF OPERATIONS AND BASIS OF PRESENTATION
We operate two natural gas liquefaction and export facilities located in Cameron Parish, Louisiana at Sabine Pass and near Corpus Christi, Texas (respectively, the “Sabine Pass LNG Terminal” and “Corpus Christi LNG Terminal”).

CQP owns the Sabine Pass LNG Terminal, which has natural gas liquefaction facilities consisting of six operational Trains, for a total production capacity of approximately 30 mtpa of LNG (the “SPL Project”). The Sabine Pass LNG Terminal also has operational regasification facilities that include five LNG storage tanks, vaporizers and three marine berths. We also own and operate a 94-mile natural gas supply pipeline that interconnects the Sabine Pass LNG Terminal with several large interstate and intrastate pipelines (the “Creole Trail Pipeline”). As of June 30, 2024, we owned 100% of the general partner interest, a 48.6% limited partner interest and 100% of the incentive distribution rights of CQP.

The Corpus Christi LNG Terminal currently has three operational Trains for a total production capacity of approximately 15 mtpa of LNG, three LNG storage tanks and two marine berths. Additionally, we are constructing an expansion of the Corpus Christi LNG Terminal (the “Corpus Christi Stage 3 Project”) consisting of seven midscale Trains with an expected total production capacity of over 10 mtpa of LNG. We also own a 21.5-mile natural gas supply pipeline that interconnects the Corpus Christi LNG Terminal with several large interstate and intrastate natural gas pipelines (the “Corpus Christi Pipeline” and together with the existing assets at the Corpus Christi LNG Terminal and the Corpus Christi Stage 3 Project, the “CCL Project”).

We are pursuing expansion projects to provide additional liquefaction capacity at the SPL Project and the CCL Project (collectively, the “Liquefaction Projects”), and we have commenced commercialization to support the additional liquefaction capacity associated with these potential expansion projects. The development of these sites or other projects, including infrastructure projects in support of natural gas supply and LNG demand, will require, among other things, acceptable commercial and financing arrangements before we make a positive FID.
Basis of Presentation

The accompanying unaudited Consolidated Financial Statements of Cheniere have been prepared in accordance with GAAP for interim financial information and in accordance with Rule 10-01 of Regulation S-X and reflect all normal recurring adjustments which are, in the opinion of management, necessary for a fair statement of the financial results for the interim periods presented. Accordingly, these Consolidated Financial Statements do not include all of the information and footnotes required by GAAP for complete financial statements and should be read in conjunction with the Consolidated Financial Statements and accompanying notes included in our annual report on Form 10-K for the fiscal year ended December 31, 2023.

Results of operations for the three and six months ended June 30, 2024 are not necessarily indicative of the results of operations that will be realized for the year ending December 31, 2024.
Recent Accounting Standards

ASU 2023-07

In November 2023, the FASB issued ASU No. 2023-07, Segment Reporting (Topic 280). This guidance requires a public entity, including entities with a single reportable segment, to disclose significant segment expenses and other segment items on an annual and interim basis and provide in interim periods all disclosures about a reportable segment’s profit or loss and assets that are currently required annually. We plan to adopt this guidance and conform with the applicable disclosures retrospectively when it becomes mandatorily effective for our annual report for the year ending December 31, 2024.

ASU 2023-09

In December 2023, the FASB issued ASU No. 2023-09, Income Taxes (Topic 740). This guidance further enhances income tax disclosures, primarily through standardization and disaggregation of rate reconciliation categories and income taxes paid by jurisdiction. We plan to adopt this guidance and conform with the disclosure requirements when it becomes mandatorily effective for our annual report for the year ending December 31, 2025.