Property, Plant and Equipment, Net of Accumulated Depreciation |
PROPERTY, PLANT AND EQUIPMENT, NET OF ACCUMULATED DEPRECIATION
As of September 30, 2021 and December 31, 2020, property, plant and equipment, net of accumulated depreciation consisted of the following (in millions):
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
September 30, |
|
December 31, |
|
|
2021 |
|
2020 |
LNG terminal |
|
|
|
|
LNG terminal and interconnecting pipeline facilities |
|
$ |
30,617 |
|
|
$ |
27,475 |
|
LNG site and related costs |
|
441 |
|
|
324 |
|
LNG terminal construction-in-process |
|
2,817 |
|
|
5,378 |
|
Accumulated depreciation |
|
(3,663) |
|
|
(2,935) |
|
Total LNG terminal, net of accumulated depreciation |
|
30,212 |
|
|
30,242 |
|
Fixed assets and other |
|
|
|
|
Computer and office equipment |
|
27 |
|
|
25 |
|
Furniture and fixtures |
|
20 |
|
|
19 |
|
Computer software |
|
122 |
|
|
117 |
|
Leasehold improvements |
|
45 |
|
|
45 |
|
Land |
|
1 |
|
|
59 |
|
Other |
|
21 |
|
|
25 |
|
Accumulated depreciation |
|
(181) |
|
|
(164) |
|
Total fixed assets and other, net of accumulated depreciation |
|
55 |
|
|
126 |
|
Assets under finance lease |
|
|
|
|
Tug vessels |
|
60 |
|
|
60 |
|
Accumulated depreciation |
|
(9) |
|
|
(7) |
|
Total assets under finance lease, net of accumulated depreciation |
|
51 |
|
|
53 |
|
Property, plant and equipment, net of accumulated depreciation |
|
$ |
30,318 |
|
|
$ |
30,421 |
|
The following table shows depreciation expense and offsets to LNG terminal costs during the three and nine months ended September 30, 2021 and 2020 (in millions):
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Three Months Ended September 30, |
|
Nine Months Ended September 30, |
|
|
2021 |
|
2020 |
|
2021 |
|
2020 |
|
|
Depreciation expense |
|
$ |
257 |
|
|
$ |
231 |
|
|
$ |
749 |
|
|
$ |
694 |
|
|
|
Offsets to LNG terminal costs (1) |
|
— |
|
|
— |
|
|
227 |
|
|
— |
|
|
|
(1)We recognize offsets to LNG terminal costs related to the sale of commissioning cargoes because these amounts were earned or loaded prior to the start of commercial operations of the respective Trains of the Liquefaction Projects during the testing phase for its construction.
|