false--12-31FY20190000003570P6M0.0580.7182.130.86P19YP3MP5DP5DP3M750000000P3DP3DP3DP3YP3Y0.03P3YP2YP4YP3YP4Y0000.0030.003480000000480000000269800000270700000257000000253600000000.011250.021250.01500.02500.00750.01750.00250.01250.00250.01250.00750.01750.00750.01750194000000LIBOR or base rateLIBOR or base rateLIBOR or base rateLIBOR or base rateLIBOR or base rate0.0940.048750.04250.056250.06250.056250.0700000.05750.052500.058750.056250.056250.058750.051250.05000.0420.0450.0370.050.039250.04800P15Y12500000002800000000.01500000000.012500000001200000000.01200000000.01130000005500000000.00010.00015000000500000000P50YP30YP7YP10YP2YP1Y001280000017100000 0000003570 2019-01-01 2019-12-31 0000003570 us-gaap:InterestRateContractMember 2019-01-01 2019-12-31 0000003570 us-gaap:ForeignExchangeContractMember 2019-01-01 2019-12-31 0000003570 us-gaap:CommodityContractMember 2019-01-01 2019-12-31 0000003570 2019-06-28 0000003570 2020-02-19 0000003570 2018-12-31 0000003570 2019-12-31 0000003570 lng:CheniereEnergyPartnersLPMember 2019-12-31 0000003570 lng:RegasificationServiceMember 2019-01-01 2019-12-31 0000003570 2018-01-01 2018-12-31 0000003570 2017-01-01 2017-12-31 0000003570 lng:RegasificationServiceMember 2018-01-01 2018-12-31 0000003570 lng:RegasificationServiceMember 2017-01-01 2017-12-31 0000003570 us-gaap:ProductAndServiceOtherMember 2017-01-01 2017-12-31 0000003570 us-gaap:ProductAndServiceOtherMember 2019-01-01 2019-12-31 0000003570 lng:LiquefiedNaturalGasMember 2019-01-01 2019-12-31 0000003570 us-gaap:ProductAndServiceOtherMember 2018-01-01 2018-12-31 0000003570 lng:LiquefiedNaturalGasMember 2017-01-01 2017-12-31 0000003570 lng:LiquefiedNaturalGasMember 2018-01-01 2018-12-31 0000003570 us-gaap:CommonStockMember 2018-01-01 2018-12-31 0000003570 us-gaap:CommonStockMember 2019-01-01 2019-12-31 0000003570 us-gaap:NoncontrollingInterestMember 2019-01-01 2019-12-31 0000003570 us-gaap:TreasuryStockMember 2017-01-01 2017-12-31 0000003570 us-gaap:RetainedEarningsMember 2018-01-01 2018-12-31 0000003570 us-gaap:RetainedEarningsMember 2019-01-01 2019-12-31 0000003570 us-gaap:CommonStockMember 2017-01-01 2017-12-31 0000003570 us-gaap:TreasuryStockMember 2019-01-01 2019-12-31 0000003570 us-gaap:AdditionalPaidInCapitalMember 2018-01-01 2018-12-31 0000003570 us-gaap:TreasuryStockMember 2018-01-01 2018-12-31 0000003570 us-gaap:AdditionalPaidInCapitalMember 2016-12-31 0000003570 us-gaap:AdditionalPaidInCapitalMember 2019-12-31 0000003570 us-gaap:NoncontrollingInterestMember 2017-01-01 2017-12-31 0000003570 us-gaap:AdditionalPaidInCapitalMember 2019-01-01 2019-12-31 0000003570 us-gaap:RetainedEarningsMember 2017-01-01 2017-12-31 0000003570 us-gaap:TreasuryStockMember 2019-12-31 0000003570 us-gaap:RetainedEarningsMember 2019-12-31 0000003570 us-gaap:NoncontrollingInterestMember 2018-01-01 2018-12-31 0000003570 2017-12-31 0000003570 us-gaap:CommonStockMember 2019-12-31 0000003570 us-gaap:CommonStockMember 2017-12-31 0000003570 us-gaap:AdditionalPaidInCapitalMember 2018-12-31 0000003570 us-gaap:RetainedEarningsMember 2016-12-31 0000003570 us-gaap:AdditionalPaidInCapitalMember 2017-01-01 2017-12-31 0000003570 us-gaap:NoncontrollingInterestMember 2019-12-31 0000003570 us-gaap:NoncontrollingInterestMember 2017-12-31 0000003570 us-gaap:CommonStockMember 2016-12-31 0000003570 2016-12-31 0000003570 us-gaap:RetainedEarningsMember 2018-12-31 0000003570 us-gaap:CommonStockMember 2018-12-31 0000003570 us-gaap:NoncontrollingInterestMember 2018-12-31 0000003570 us-gaap:TreasuryStockMember 2017-12-31 0000003570 us-gaap:RetainedEarningsMember 2017-12-31 0000003570 us-gaap:TreasuryStockMember 2016-12-31 0000003570 us-gaap:TreasuryStockMember 2018-12-31 0000003570 us-gaap:NoncontrollingInterestMember 2016-12-31 0000003570 us-gaap:AdditionalPaidInCapitalMember 2017-12-31 0000003570 lng:SabinePassLNGTerminalMember 2019-01-01 2019-12-31 0000003570 lng:CorpusChristiLNGTerminalMember 2019-01-01 2019-12-31 0000003570 lng:CorpusChristiLNGTerminalExpansionMember 2019-01-01 2019-12-31 0000003570 lng:CheniereEnergyPartnersLPMember 2019-01-01 2019-12-31 0000003570 lng:CheniereEnergyPartnersLPMember lng:SabinePassLNGTerminalMember 2019-12-31 2019-12-31 0000003570 lng:CorpusChristiLNGTerminalMember 2019-12-31 2019-12-31 0000003570 srt:MaximumMember lng:CorpusChristiLNGTerminalExpansionMember 2019-01-01 2019-12-31 0000003570 lng:CheniereEnergyPartnersLPMember lng:CreoleTrailPipelineMember 2019-01-01 2019-12-31 0000003570 lng:CorpusChristiPipelineMember 2019-01-01 2019-12-31 0000003570 lng:SabinePassLiquefactionMember lng:SPACustomersMember us-gaap:CustomerConcentrationRiskMember 2019-01-01 2019-12-31 0000003570 lng:AssetsUsedInNoncoreOperationsMember 2017-01-01 2017-12-31 0000003570 srt:MaximumMember lng:SabinePassLNGTerminalMember 2019-12-31 0000003570 lng:CreoleTrailPipelineMember 2019-12-31 0000003570 lng:CorpusChristiLiquefactionMember lng:SPACustomersMember us-gaap:CustomerConcentrationRiskMember 2019-01-01 2019-12-31 0000003570 lng:SabinePassLNGLPMember lng:TUACustomersMember us-gaap:CustomerConcentrationRiskMember 2019-01-01 2019-12-31 0000003570 lng:CorpusChristiLNGTerminalMember 2017-01-01 2017-12-31 0000003570 lng:SabinePassLNGTerminalMember 2019-12-31 0000003570 us-gaap:AccountingStandardsUpdate201602Member 2019-01-01 0000003570 lng:CorpusChristiPipelineMember 2019-12-31 0000003570 lng:A2016CQPCreditFacilitiesMember 2018-12-31 0000003570 lng:CCLProjectMember 2019-12-31 0000003570 lng:CCLProjectMember 2018-12-31 0000003570 lng:CQPAndCashHeldByGuarantorSubsidiariesMember 2019-12-31 0000003570 lng:SPLProjectMember 2019-12-31 0000003570 lng:SubsidiaryCashMember 2019-12-31 0000003570 lng:CQPAndCashHeldByGuarantorSubsidiariesMember 2018-12-31 0000003570 lng:SPLProjectMember 2018-12-31 0000003570 lng:SubsidiaryCashMember 2018-12-31 0000003570 lng:SabinePassLiquefactionAndCorpusChristiLiquefactionMember 2018-12-31 0000003570 lng:CheniereMarketingLLCMember 2019-12-31 0000003570 lng:CheniereMarketingLLCMember 2018-12-31 0000003570 lng:SabinePassLiquefactionAndCorpusChristiLiquefactionMember 2019-12-31 0000003570 lng:LiquefiedNaturalGasInventoryMember 2019-12-31 0000003570 lng:LiquefiedNaturalGasInTransitInventoryMember 2019-12-31 0000003570 lng:LiquefiedNaturalGasInTransitInventoryMember 2018-12-31 0000003570 lng:LiquefiedNaturalGasInventoryMember 2018-12-31 0000003570 lng:NaturalGasInventoryMember 2019-12-31 0000003570 lng:MaterialsAndOtherInventoryMember 2018-12-31 0000003570 lng:NaturalGasInventoryMember 2018-12-31 0000003570 lng:MaterialsAndOtherInventoryMember 2019-12-31 0000003570 lng:MarineBerthElectricalFacilityAndRoadsMember 2019-01-01 2019-12-31 0000003570 lng:WaterPipelinesMember 2019-01-01 2019-12-31 0000003570 lng:RegasificationProcessingEquipmentRecondensersVaporizationAndVentsMember 2019-01-01 2019-12-31 0000003570 lng:LNGStorageTanksMember 2019-01-01 2019-12-31 0000003570 us-gaap:PipelinesMember 2019-01-01 2019-12-31 0000003570 lng:SendoutPumpsMember 2019-01-01 2019-12-31 0000003570 us-gaap:OtherCapitalizedPropertyPlantAndEquipmentMember 2018-12-31 0000003570 us-gaap:OtherCapitalizedPropertyPlantAndEquipmentMember 2019-12-31 0000003570 lng:LngTerminalCostsMember 2019-12-31 0000003570 lng:LngTerminalMember 2018-12-31 0000003570 us-gaap:LandMember 2019-12-31 0000003570 us-gaap:SoftwareAndSoftwareDevelopmentCostsMember 2018-12-31 0000003570 lng:LngSiteAndRelatedCostsNetMember 2019-12-31 0000003570 us-gaap:LandMember 2018-12-31 0000003570 us-gaap:AssetsHeldUnderCapitalLeasesMember 2019-12-31 0000003570 us-gaap:LeaseholdImprovementsMember 2019-12-31 0000003570 us-gaap:ConstructionInProgressMember 2019-12-31 0000003570 us-gaap:LeaseholdImprovementsMember 2018-12-31 0000003570 lng:FixedAssetsMember 2018-12-31 0000003570 lng:LngTerminalMember 2019-12-31 0000003570 us-gaap:SoftwareAndSoftwareDevelopmentCostsMember 2019-12-31 0000003570 lng:LngTerminalCostsMember 2018-12-31 0000003570 us-gaap:AssetsHeldUnderCapitalLeasesMember 2018-12-31 0000003570 us-gaap:ConstructionInProgressMember 2018-12-31 0000003570 lng:FixedAssetsMember 2019-12-31 0000003570 us-gaap:FurnitureAndFixturesMember 2018-12-31 0000003570 us-gaap:OfficeEquipmentMember 2019-12-31 0000003570 us-gaap:FurnitureAndFixturesMember 2019-12-31 0000003570 lng:LngSiteAndRelatedCostsNetMember 2018-12-31 0000003570 us-gaap:OfficeEquipmentMember 2018-12-31 0000003570 srt:MaximumMember lng:LngTerminalCostsMember 2019-01-01 2019-12-31 0000003570 srt:MinimumMember lng:LngTerminalCostsMember 2019-01-01 2019-12-31 0000003570 srt:MaximumMember lng:LiquefactionProcessingEquipmentMember 2019-01-01 2019-12-31 0000003570 srt:MinimumMember lng:LiquefactionProcessingEquipmentMember 2019-01-01 2019-12-31 0000003570 srt:MaximumMember us-gaap:OtherEnergyEquipmentMember 2019-01-01 2019-12-31 0000003570 srt:MinimumMember us-gaap:OtherEnergyEquipmentMember 2019-01-01 2019-12-31 0000003570 lng:CQPInterestRateDerivativesMember us-gaap:GainLossOnDerivativeInstrumentsMember 2017-01-01 2017-12-31 0000003570 lng:CQPInterestRateDerivativesMember us-gaap:GainLossOnDerivativeInstrumentsMember 2018-01-01 2018-12-31 0000003570 lng:CCHInterestRateForwardStartDerivativesMember us-gaap:GainLossOnDerivativeInstrumentsMember 2018-01-01 2018-12-31 0000003570 lng:SPLInterestRateDerivativesMember us-gaap:GainLossOnDerivativeInstrumentsMember 2019-01-01 2019-12-31 0000003570 lng:CQPInterestRateDerivativesMember us-gaap:GainLossOnDerivativeInstrumentsMember 2019-01-01 2019-12-31 0000003570 lng:CCHInterestRateDerivativesMember us-gaap:GainLossOnDerivativeInstrumentsMember 2017-01-01 2017-12-31 0000003570 lng:CCHInterestRateForwardStartDerivativesMember us-gaap:GainLossOnDerivativeInstrumentsMember 2019-01-01 2019-12-31 0000003570 lng:CCHInterestRateForwardStartDerivativesMember us-gaap:GainLossOnDerivativeInstrumentsMember 2017-01-01 2017-12-31 0000003570 lng:SPLInterestRateDerivativesMember us-gaap:GainLossOnDerivativeInstrumentsMember 2017-01-01 2017-12-31 0000003570 lng:CCHInterestRateDerivativesMember us-gaap:GainLossOnDerivativeInstrumentsMember 2019-01-01 2019-12-31 0000003570 lng:CCHInterestRateDerivativesMember us-gaap:GainLossOnDerivativeInstrumentsMember 2018-01-01 2018-12-31 0000003570 lng:SPLInterestRateDerivativesMember us-gaap:GainLossOnDerivativeInstrumentsMember 2018-01-01 2018-12-31 0000003570 us-gaap:DerivativeFinancialInstrumentsLiabilitiesMember us-gaap:ForeignExchangeContractMember 2019-12-31 0000003570 us-gaap:DerivativeFinancialInstrumentsAssetsMember us-gaap:ForeignExchangeContractMember 2019-12-31 0000003570 us-gaap:DerivativeFinancialInstrumentsLiabilitiesMember us-gaap:ForeignExchangeContractMember 2018-12-31 0000003570 us-gaap:DerivativeFinancialInstrumentsAssetsMember us-gaap:ForeignExchangeContractMember 2018-12-31 0000003570 lng:PhysicalLiquefactionSupplyDerivativesMember us-gaap:FairValueInputsLevel3Member 2019-12-31 0000003570 lng:PhysicalLiquefactionSupplyDerivativesMember 2018-12-31 0000003570 lng:PhysicalLiquefactionSupplyDerivativesMember 2017-01-01 2017-12-31 0000003570 lng:PhysicalLiquefactionSupplyDerivativesMember 2019-01-01 2019-12-31 0000003570 lng:PhysicalLiquefactionSupplyDerivativesMember 2018-01-01 2018-12-31 0000003570 lng:PhysicalLiquefactionSupplyDerivativesMember 2017-12-31 0000003570 lng:PhysicalLiquefactionSupplyDerivativesMember 2019-12-31 0000003570 lng:PhysicalLiquefactionSupplyDerivativesMember 2016-12-31 0000003570 lng:LNGTradingDerivativeMember 2019-12-31 0000003570 lng:CorpusChristiLiquefactionMember lng:NaturalGasSupplyAgreementMember 2018-01-01 2018-12-31 0000003570 lng:CorpusChristiLiquefactionMember lng:NaturalGasSupplyAgreementMember 2019-12-31 0000003570 us-gaap:PriceRiskDerivativeMember 2018-12-31 0000003570 lng:A2015CCHTermLoanFacilityMember 2019-11-01 2019-11-30 0000003570 lng:CorpusChristiLiquefactionMember lng:NaturalGasSupplyAgreementMember 2018-12-31 0000003570 lng:CorpusChristiLiquefactionMember lng:NaturalGasSupplyAgreementMember 2019-01-01 2019-12-31 0000003570 srt:MaximumMember lng:PhysicalLiquefactionSupplyDerivativesMember 2019-01-01 2019-12-31 0000003570 us-gaap:PriceRiskDerivativeMember 2019-12-31 0000003570 lng:LNGTradingDerivativeMember 2018-12-31 0000003570 us-gaap:ForeignExchangeContractMember 2019-12-31 0000003570 us-gaap:PriceRiskDerivativeMember lng:NaturalGasSupplyAgreementMember 2019-01-01 2019-12-31 0000003570 us-gaap:ForeignExchangeContractMember 2018-12-31 0000003570 us-gaap:PriceRiskDerivativeMember us-gaap:CostOfSalesMember 2018-01-01 2018-12-31 0000003570 lng:LNGTradingDerivativeMember us-gaap:SalesMember 2019-01-01 2019-12-31 0000003570 lng:LNGTradingDerivativeMember us-gaap:CostOfSalesMember 2017-01-01 2017-12-31 0000003570 us-gaap:PriceRiskDerivativeMember us-gaap:SalesMember 2017-01-01 2017-12-31 0000003570 lng:LNGTradingDerivativeMember us-gaap:SalesMember 2018-01-01 2018-12-31 0000003570 us-gaap:PriceRiskDerivativeMember us-gaap:CostOfSalesMember 2019-01-01 2019-12-31 0000003570 us-gaap:PriceRiskDerivativeMember us-gaap:SalesMember 2019-01-01 2019-12-31 0000003570 lng:LNGTradingDerivativeMember us-gaap:CostOfSalesMember 2019-01-01 2019-12-31 0000003570 us-gaap:PriceRiskDerivativeMember us-gaap:CostOfSalesMember 2017-01-01 2017-12-31 0000003570 lng:LNGTradingDerivativeMember us-gaap:SalesMember 2017-01-01 2017-12-31 0000003570 us-gaap:PriceRiskDerivativeMember us-gaap:SalesMember 2018-01-01 2018-12-31 0000003570 lng:LNGTradingDerivativeMember us-gaap:CostOfSalesMember 2018-01-01 2018-12-31 0000003570 us-gaap:DerivativeFinancialInstrumentsAssetsMember us-gaap:PriceRiskDerivativeMember 2019-12-31 0000003570 us-gaap:DerivativeFinancialInstrumentsAssetsMember us-gaap:CommodityContractMember 2018-12-31 0000003570 lng:NoncurrentDerivativeLiabilitiesMember lng:LNGTradingDerivativeMember 2018-12-31 0000003570 us-gaap:CommodityContractMember 2019-12-31 0000003570 us-gaap:CommodityContractMember 2018-12-31 0000003570 us-gaap:DerivativeFinancialInstrumentsLiabilitiesMember lng:LNGTradingDerivativeMember 2018-12-31 0000003570 us-gaap:DerivativeFinancialInstrumentsLiabilitiesMember us-gaap:PriceRiskDerivativeMember 2019-12-31 0000003570 lng:NoncurrentDerivativeAssetsMember us-gaap:CommodityContractMember 2018-12-31 0000003570 lng:NoncurrentDerivativeAssetsMember us-gaap:PriceRiskDerivativeMember 2018-12-31 0000003570 lng:NoncurrentDerivativeLiabilitiesMember us-gaap:PriceRiskDerivativeMember 2018-12-31 0000003570 lng:NoncurrentDerivativeLiabilitiesMember us-gaap:CommodityContractMember 2018-12-31 0000003570 us-gaap:DerivativeFinancialInstrumentsLiabilitiesMember us-gaap:CommodityContractMember 2018-12-31 0000003570 us-gaap:DerivativeFinancialInstrumentsAssetsMember lng:LNGTradingDerivativeMember 2018-12-31 0000003570 lng:NoncurrentDerivativeAssetsMember us-gaap:CommodityContractMember 2019-12-31 0000003570 us-gaap:DerivativeFinancialInstrumentsLiabilitiesMember lng:LNGTradingDerivativeMember 2019-12-31 0000003570 lng:NoncurrentDerivativeLiabilitiesMember us-gaap:PriceRiskDerivativeMember 2019-12-31 0000003570 us-gaap:DerivativeFinancialInstrumentsAssetsMember lng:LNGTradingDerivativeMember 2019-12-31 0000003570 lng:NoncurrentDerivativeAssetsMember us-gaap:PriceRiskDerivativeMember 2019-12-31 0000003570 lng:CheniereEnergyPartnersLPMember 2019-01-01 2019-12-31 0000003570 lng:NoncurrentDerivativeLiabilitiesMember us-gaap:CommodityContractMember 2019-12-31 0000003570 us-gaap:DerivativeFinancialInstrumentsLiabilitiesMember us-gaap:CommodityContractMember 2019-12-31 0000003570 lng:NoncurrentDerivativeLiabilitiesMember lng:LNGTradingDerivativeMember 2019-12-31 0000003570 us-gaap:DerivativeFinancialInstrumentsAssetsMember us-gaap:PriceRiskDerivativeMember 2018-12-31 0000003570 lng:NoncurrentDerivativeAssetsMember lng:LNGTradingDerivativeMember 2018-12-31 0000003570 lng:NoncurrentDerivativeAssetsMember lng:LNGTradingDerivativeMember 2019-12-31 0000003570 us-gaap:DerivativeFinancialInstrumentsAssetsMember us-gaap:CommodityContractMember 2019-12-31 0000003570 us-gaap:DerivativeFinancialInstrumentsLiabilitiesMember us-gaap:PriceRiskDerivativeMember 2018-12-31 0000003570 lng:PriceRiskDerivativeAssetMember 2018-12-31 0000003570 lng:ForeignExchangeContractAssetMember 2019-12-31 0000003570 lng:PriceRiskDerivativeLiabilityMember 2019-12-31 0000003570 lng:CCHInterestRateDerivativeLiabilityMember 2019-12-31 0000003570 lng:ForeignExchangeContractLiabilityMember 2019-12-31 0000003570 lng:ForeignExchangeContractLiabilityMember 2018-12-31 0000003570 lng:LNGTradingDerivativesLiabilityMember 2019-12-31 0000003570 lng:LNGTradingDerivativeAssetMember 2018-12-31 0000003570 lng:CCHInterestRateDerivativeAssetMember 2018-12-31 0000003570 lng:CCHInterestRateForwardStartDerivativesMember 2019-12-31 0000003570 lng:LNGTradingDerivativesLiabilityMember 2018-12-31 0000003570 lng:PriceRiskDerivativeLiabilityMember 2018-12-31 0000003570 lng:PriceRiskDerivativeAssetMember 2019-12-31 0000003570 lng:ForeignExchangeContractAssetMember 2018-12-31 0000003570 lng:LNGTradingDerivativeAssetMember 2019-12-31 0000003570 lng:CCHInterestRateDerivativesMember 2019-12-31 0000003570 lng:CCHInterestRateDerivativesMember 2019-01-01 2019-12-31 0000003570 lng:CCHInterestRateForwardStartDerivativesMember 2018-12-31 0000003570 lng:CCHInterestRateForwardStartDerivativesMember 2019-01-01 2019-12-31 0000003570 lng:CCHInterestRateDerivativesMember 2018-12-31 0000003570 us-gaap:ForeignExchangeContractMember us-gaap:SalesMember 2019-01-01 2019-12-31 0000003570 us-gaap:ForeignExchangeContractMember us-gaap:SalesMember 2017-01-01 2017-12-31 0000003570 us-gaap:ForeignExchangeContractMember us-gaap:SalesMember 2018-01-01 2018-12-31 0000003570 lng:LNGTradingDerivativeMember us-gaap:FairValueInputsLevel1Member 2018-12-31 0000003570 lng:CCHInterestRateDerivativesMember us-gaap:FairValueInputsLevel2Member 2018-12-31 0000003570 us-gaap:PriceRiskDerivativeMember us-gaap:FairValueInputsLevel3Member 2019-12-31 0000003570 lng:CCHInterestRateForwardStartDerivativesMember us-gaap:FairValueInputsLevel3Member 2018-12-31 0000003570 lng:LNGTradingDerivativeMember us-gaap:FairValueInputsLevel3Member 2019-12-31 0000003570 us-gaap:PriceRiskDerivativeMember us-gaap:FairValueInputsLevel1Member 2019-12-31 0000003570 lng:CCHInterestRateDerivativesMember us-gaap:FairValueInputsLevel1Member 2019-12-31 0000003570 lng:CCHInterestRateDerivativesMember us-gaap:FairValueInputsLevel3Member 2019-12-31 0000003570 lng:CCHInterestRateForwardStartDerivativesMember us-gaap:FairValueInputsLevel1Member 2019-12-31 0000003570 lng:CCHInterestRateDerivativesMember us-gaap:FairValueInputsLevel1Member 2018-12-31 0000003570 us-gaap:ForeignExchangeContractMember us-gaap:FairValueInputsLevel3Member 2019-12-31 0000003570 lng:CCHInterestRateForwardStartDerivativesMember us-gaap:FairValueInputsLevel3Member 2019-12-31 0000003570 us-gaap:ForeignExchangeContractMember us-gaap:FairValueInputsLevel2Member 2019-12-31 0000003570 lng:CCHInterestRateDerivativesMember us-gaap:FairValueInputsLevel3Member 2018-12-31 0000003570 lng:LNGTradingDerivativeMember us-gaap:FairValueInputsLevel2Member 2019-12-31 0000003570 us-gaap:ForeignExchangeContractMember us-gaap:FairValueInputsLevel1Member 2018-12-31 0000003570 us-gaap:PriceRiskDerivativeMember us-gaap:FairValueInputsLevel2Member 2019-12-31 0000003570 lng:CCHInterestRateForwardStartDerivativesMember us-gaap:FairValueInputsLevel2Member 2018-12-31 0000003570 us-gaap:ForeignExchangeContractMember us-gaap:FairValueInputsLevel1Member 2019-12-31 0000003570 us-gaap:PriceRiskDerivativeMember us-gaap:FairValueInputsLevel3Member 2018-12-31 0000003570 lng:CCHInterestRateForwardStartDerivativesMember us-gaap:FairValueInputsLevel2Member 2019-12-31 0000003570 lng:LNGTradingDerivativeMember us-gaap:FairValueInputsLevel2Member 2018-12-31 0000003570 lng:CCHInterestRateDerivativesMember us-gaap:FairValueInputsLevel2Member 2019-12-31 0000003570 us-gaap:PriceRiskDerivativeMember us-gaap:FairValueInputsLevel1Member 2018-12-31 0000003570 lng:LNGTradingDerivativeMember us-gaap:FairValueInputsLevel1Member 2019-12-31 0000003570 lng:LNGTradingDerivativeMember us-gaap:FairValueInputsLevel3Member 2018-12-31 0000003570 us-gaap:PriceRiskDerivativeMember us-gaap:FairValueInputsLevel2Member 2018-12-31 0000003570 us-gaap:ForeignExchangeContractMember us-gaap:FairValueInputsLevel2Member 2018-12-31 0000003570 lng:CCHInterestRateForwardStartDerivativesMember us-gaap:FairValueInputsLevel1Member 2018-12-31 0000003570 us-gaap:ForeignExchangeContractMember us-gaap:FairValueInputsLevel3Member 2018-12-31 0000003570 us-gaap:DerivativeFinancialInstrumentsLiabilitiesMember lng:CCHInterestRateForwardStartDerivativesMember 2019-12-31 0000003570 us-gaap:DerivativeFinancialInstrumentsAssetsMember lng:CCHInterestRateDerivativesMember 2018-12-31 0000003570 lng:NoncurrentDerivativeAssetsMember lng:CCHInterestRateDerivativesMember 2018-12-31 0000003570 us-gaap:DerivativeFinancialInstrumentsLiabilitiesMember lng:CCHInterestRateDerivativesMember 2019-12-31 0000003570 us-gaap:DerivativeFinancialInstrumentsAssetsMember us-gaap:InterestRateContractMember 2018-12-31 0000003570 lng:NoncurrentDerivativeAssetsMember lng:CCHInterestRateDerivativesMember 2019-12-31 0000003570 us-gaap:DerivativeFinancialInstrumentsLiabilitiesMember us-gaap:InterestRateContractMember 2018-12-31 0000003570 lng:NoncurrentDerivativeLiabilitiesMember lng:CCHInterestRateDerivativesMember 2018-12-31 0000003570 us-gaap:DerivativeFinancialInstrumentsLiabilitiesMember lng:CCHInterestRateForwardStartDerivativesMember 2018-12-31 0000003570 lng:NoncurrentDerivativeLiabilitiesMember us-gaap:InterestRateContractMember 2019-12-31 0000003570 lng:NoncurrentDerivativeAssetsMember lng:CCHInterestRateForwardStartDerivativesMember 2019-12-31 0000003570 us-gaap:DerivativeFinancialInstrumentsAssetsMember lng:CCHInterestRateForwardStartDerivativesMember 2019-12-31 0000003570 us-gaap:InterestRateContractMember 2019-12-31 0000003570 us-gaap:DerivativeFinancialInstrumentsLiabilitiesMember lng:CCHInterestRateDerivativesMember 2018-12-31 0000003570 lng:NoncurrentDerivativeLiabilitiesMember lng:CCHInterestRateForwardStartDerivativesMember 2018-12-31 0000003570 us-gaap:InterestRateContractMember 2018-12-31 0000003570 lng:NoncurrentDerivativeAssetsMember us-gaap:InterestRateContractMember 2019-12-31 0000003570 us-gaap:DerivativeFinancialInstrumentsAssetsMember lng:CCHInterestRateDerivativesMember 2019-12-31 0000003570 us-gaap:DerivativeFinancialInstrumentsAssetsMember us-gaap:InterestRateContractMember 2019-12-31 0000003570 lng:NoncurrentDerivativeLiabilitiesMember lng:CCHInterestRateForwardStartDerivativesMember 2019-12-31 0000003570 lng:NoncurrentDerivativeAssetsMember lng:CCHInterestRateForwardStartDerivativesMember 2018-12-31 0000003570 us-gaap:DerivativeFinancialInstrumentsAssetsMember lng:CCHInterestRateForwardStartDerivativesMember 2018-12-31 0000003570 us-gaap:DerivativeFinancialInstrumentsLiabilitiesMember us-gaap:InterestRateContractMember 2019-12-31 0000003570 lng:NoncurrentDerivativeLiabilitiesMember lng:CCHInterestRateDerivativesMember 2019-12-31 0000003570 lng:NoncurrentDerivativeAssetsMember us-gaap:InterestRateContractMember 2018-12-31 0000003570 lng:NoncurrentDerivativeLiabilitiesMember us-gaap:InterestRateContractMember 2018-12-31 0000003570 srt:MinimumMember lng:PhysicalLiquefactionSupplyDerivativesMember us-gaap:FairValueInputsLevel3Member us-gaap:ValuationTechniqueOptionPricingModelMember 2019-01-01 2019-12-31 0000003570 srt:MinimumMember lng:PhysicalLiquefactionSupplyDerivativesMember us-gaap:FairValueInputsLevel3Member us-gaap:MarketApproachValuationTechniqueMember 2019-01-01 2019-12-31 0000003570 srt:MaximumMember lng:PhysicalLiquefactionSupplyDerivativesMember us-gaap:FairValueInputsLevel3Member us-gaap:ValuationTechniqueOptionPricingModelMember 2019-01-01 2019-12-31 0000003570 srt:MaximumMember lng:PhysicalLiquefactionSupplyDerivativesMember us-gaap:FairValueInputsLevel3Member us-gaap:MarketApproachValuationTechniqueMember 2019-01-01 2019-12-31 0000003570 lng:CorpusChristiLiquefactionMember lng:NaturalGasSupplyAgreementMember 2018-10-01 2018-12-31 0000003570 lng:CorpusChristiLiquefactionMember lng:NaturalGasSupplyAgreementMember 2017-01-01 2017-12-31 0000003570 lng:CheniereLNGOMServicesLLCMember us-gaap:ServiceAgreementsMember lng:MidshipPipelineMember 2019-12-31 0000003570 lng:CheniereLNGOMServicesLLCMember us-gaap:ServiceAgreementsMember lng:MidshipPipelineMember 2018-12-31 0000003570 lng:CheniereLNGOMServicesLLCMember us-gaap:ServiceAgreementsMember lng:MidshipPipelineMember 2019-01-01 2019-12-31 0000003570 lng:CorpusChristiLiquefactionMember lng:NaturalGasTransportationAgreementMember lng:MidshipPipelineMember 2019-01-01 2019-12-31 0000003570 lng:MidshipHoldingsLLCMember 2018-12-31 0000003570 lng:CheniereLNGOMServicesLLCMember us-gaap:ServiceAgreementsMember lng:MidshipPipelineMember 2018-01-01 2018-12-31 0000003570 lng:MidshipPipelineMember 2019-01-01 2019-12-31 0000003570 lng:EIGGlobalEnergyPartnersMember srt:MaximumMember 2019-12-31 0000003570 lng:MidshipPipelineMember lng:MidshipPipelineLetterofCreditMember lng:CorpusChristiLiquefactionMember 2018-05-31 0000003570 lng:MidshipPipelineMember lng:MidshipPipelineLetterofCreditMember lng:CorpusChristiLiquefactionMember 2019-12-31 0000003570 lng:MidshipHoldingsLLCMember 2019-12-31 0000003570 lng:CheniereLNGOMServicesLLCMember us-gaap:ServiceAgreementsMember lng:MidshipPipelineMember 2017-01-01 2017-12-31 0000003570 lng:CheniereEnergyPartnersLPMember lng:CommonUnitsMember 2019-12-31 0000003570 lng:CheniereEnergyPartnersGPLLCMember lng:BlackstoneCqpHoldcoLpMember 2019-01-01 2019-12-31 0000003570 lng:CheniereEnergyPartnersGPLLCMember lng:BlackstoneCQPHoldcoLPAndCheniereEnergyIncMember 2019-01-01 2019-12-31 0000003570 lng:CheniereEnergyPartnersLPMember lng:ClassBUnitsMember lng:BlackstoneCqpHoldcoLpMember 2012-01-01 2012-12-31 0000003570 lng:CheniereEnergyPartnersGPLLCMember lng:CheniereEnergyIncMember 2019-01-01 2019-12-31 0000003570 lng:BlackstoneCqpHoldcoLpMember 2019-01-01 2019-12-31 0000003570 lng:CheniereEnergyPartnersLPMember lng:SubordinatedUnitsMember 2019-12-31 0000003570 lng:CheniereEnergyPartnersLPMember lng:DirectorAppointmentEntitlementMinimumMember lng:BlackstoneCqpHoldcoLpMember 2019-01-01 2019-12-31 0000003570 lng:CheniereEnergyPartnersLPMember 2018-12-31 0000003570 lng:A2045ConvertibleSeniorNotesMember 2019-12-31 0000003570 lng:A2025ConvertibleSeniorNotesMember 2019-01-01 2019-12-31 0000003570 lng:A2021ConvertibleUnsecuredNotesMember 2019-12-31 0000003570 lng:A2025ConvertibleSeniorNotesMember 2019-12-31 0000003570 lng:A2045ConvertibleSeniorNotesMember 2019-01-01 2019-12-31 0000003570 lng:A2021ConvertibleUnsecuredNotesMember 2019-01-01 2019-12-31 0000003570 lng:A2026SabinePassLiquefactionSeniorNotesMember 2019-12-31 0000003570 lng:A2037SabinePassLiquefactionNotesMember 2019-12-31 0000003570 lng:A2037SabinePassLiquefactionNotesMember 2018-12-31 0000003570 lng:WorkingCapitalFacilityMember 2019-12-31 0000003570 lng:A2027CorpusChristiHoldingsSeniorNotesMember 2019-12-31 0000003570 lng:A2016CQPCreditFacilitiesMember 2018-12-31 0000003570 lng:A2019CQPCreditFacilitiesMember 2019-12-31 0000003570 lng:A2025CorpusChristiHoldingsSeniorNotesMember 2018-12-31 0000003570 lng:A2024CorpusChristiHoldingsSeniorNotesMember 2018-12-31 0000003570 lng:A2027SabinePassLiquefactionSeniorNotesMember 2018-12-31 0000003570 lng:A2026SabinePassLiquefactionSeniorNotesMember 2018-12-31 0000003570 lng:A2025SabinePassLiquefactionSeniorNotesMember 2018-12-31 0000003570 lng:A2028SabinePassLiquefactionSeniorNotesMember 2018-12-31 0000003570 lng:WorkingCapitalFacilityMember 2018-12-31 0000003570 lng:CorpusChristiHoldingsWorkingCapitalFacilityMember 2019-12-31 0000003570 lng:A2021SabinePassLiquefactionSeniorNotesMember 2019-12-31 0000003570 lng:A2028SabinePassLiquefactionSeniorNotesMember 2019-12-31 0000003570 lng:A2025SabinePassLiquefactionSeniorNotesMember 2019-12-31 0000003570 lng:A2039CorpusChristiHoldingsSeniorNotesMember 2018-12-31 0000003570 lng:A2015CCHTermLoanFacilityMember 2019-12-31 0000003570 lng:A2021ConvertibleUnsecuredNotesMember 2018-12-31 0000003570 lng:A2025CheniereEnergyPartnersSeniorNotesMember 2019-12-31 0000003570 lng:A2026CheniereEnergyPartnersSeniorNotesMember 2018-12-31 0000003570 lng:A2025CorpusChristiHoldingsSeniorNotesMember 2019-12-31 0000003570 lng:CheniereRevolvingCreditFacilityMember 2019-12-31 0000003570 lng:A2029CheniereEnergyPartnersSeniorNotesMember 2018-12-31 0000003570 lng:A2025ConvertibleSeniorNotesMember 2018-12-31 0000003570 lng:CorpusChristiHoldingsWorkingCapitalFacilityMember 2018-12-31 0000003570 lng:A2027SabinePassLiquefactionSeniorNotesMember 2019-12-31 0000003570 lng:CheniereMarketingTradeFinanceFacilitiesMember 2018-12-31 0000003570 lng:A2029CheniereEnergyPartnersSeniorNotesMember 2019-12-31 0000003570 lng:A2016CQPCreditFacilitiesMember 2019-12-31 0000003570 lng:A2027CorpusChristiHoldingsSeniorNotesMember 2018-12-31 0000003570 lng:A2021SabinePassLiquefactionSeniorNotesMember 2018-12-31 0000003570 lng:A2026CheniereEnergyPartnersSeniorNotesMember 2019-12-31 0000003570 lng:A2022SabinePassLiquefactionSeniorNotesMember 2019-12-31 0000003570 lng:A2019CQPCreditFacilitiesMember 2018-12-31 0000003570 lng:CheniereMarketingTradeFinanceFacilitiesMember 2019-12-31 0000003570 lng:A2024SabinePassLiquefactionSeniorNotesMember 2018-12-31 0000003570 lng:A2024SabinePassLiquefactionSeniorNotesMember 2019-12-31 0000003570 lng:A2023SabinePassLiquefactionSeniorNotesMember 2019-12-31 0000003570 lng:A2022SabinePassLiquefactionSeniorNotesMember 2018-12-31 0000003570 lng:A2015CCHTermLoanFacilityMember 2018-12-31 0000003570 lng:A2025CheniereEnergyPartnersSeniorNotesMember 2018-12-31 0000003570 lng:A2039CorpusChristiHoldingsSeniorNotesMember 2019-12-31 0000003570 lng:A20393.925CorpusChristiHoldingsSeniorNotesMember 2019-12-31 0000003570 lng:A20393.925CorpusChristiHoldingsSeniorNotesMember 2018-12-31 0000003570 lng:A2045ConvertibleSeniorNotesMember 2018-12-31 0000003570 lng:A2029CorpusChristiHoldingsSeniorNotesMember 2019-12-31 0000003570 lng:A2029CorpusChristiHoldingsSeniorNotesMember 2018-12-31 0000003570 lng:CheniereRevolvingCreditFacilityMember 2018-12-31 0000003570 lng:A2024CorpusChristiHoldingsSeniorNotesMember 2019-12-31 0000003570 lng:A2023SabinePassLiquefactionSeniorNotesMember 2018-12-31 0000003570 us-gaap:ConvertibleDebtMember 2017-01-01 2017-12-31 0000003570 us-gaap:ConvertibleDebtMember 2019-01-01 2019-12-31 0000003570 us-gaap:ConvertibleDebtMember 2018-01-01 2018-12-31 0000003570 lng:DebtExcludingCapitalLeaseAndConvertibleDebtMember 2019-01-01 2019-12-31 0000003570 lng:DebtExcludingCapitalLeaseAndConvertibleDebtMember 2017-01-01 2017-12-31 0000003570 lng:DebtExcludingCapitalLeaseAndConvertibleDebtMember 2018-01-01 2018-12-31 0000003570 lng:A20393.925CorpusChristiHoldingsSeniorNotesMember us-gaap:EstimateOfFairValueFairValueDisclosureMember 2019-12-31 0000003570 lng:A2021ConvertibleUnsecuredNotesMember us-gaap:CarryingReportedAmountFairValueDisclosureMember 2018-12-31 0000003570 lng:A2021ConvertibleUnsecuredNotesMember us-gaap:EstimateOfFairValueFairValueDisclosureMember 2018-12-31 0000003570 lng:A2045ConvertibleSeniorNotesMember us-gaap:CarryingReportedAmountFairValueDisclosureMember 2018-12-31 0000003570 us-gaap:SeniorNotesMember us-gaap:CarryingReportedAmountFairValueDisclosureMember 2018-12-31 0000003570 lng:A2039CorpusChristiHoldingsSeniorNotesMember us-gaap:CarryingReportedAmountFairValueDisclosureMember 2018-12-31 0000003570 lng:A2037SabinePassLiquefactionNotesMember us-gaap:EstimateOfFairValueFairValueDisclosureMember 2019-12-31 0000003570 us-gaap:SeniorNotesMember us-gaap:EstimateOfFairValueFairValueDisclosureMember 2019-12-31 0000003570 lng:A2021ConvertibleUnsecuredNotesMember us-gaap:EstimateOfFairValueFairValueDisclosureMember 2019-12-31 0000003570 lng:A2037SabinePassLiquefactionNotesMember us-gaap:EstimateOfFairValueFairValueDisclosureMember 2018-12-31 0000003570 lng:A20393.925CorpusChristiHoldingsSeniorNotesMember us-gaap:EstimateOfFairValueFairValueDisclosureMember 2018-12-31 0000003570 lng:A20393.925CorpusChristiHoldingsSeniorNotesMember us-gaap:CarryingReportedAmountFairValueDisclosureMember 2019-12-31 0000003570 lng:A20393.925CorpusChristiHoldingsSeniorNotesMember us-gaap:CarryingReportedAmountFairValueDisclosureMember 2018-12-31 0000003570 us-gaap:LineOfCreditMember us-gaap:CarryingReportedAmountFairValueDisclosureMember 2018-12-31 0000003570 us-gaap:LineOfCreditMember us-gaap:EstimateOfFairValueFairValueDisclosureMember 2018-12-31 0000003570 lng:A2021ConvertibleUnsecuredNotesMember us-gaap:CarryingReportedAmountFairValueDisclosureMember 2019-12-31 0000003570 lng:A2037SabinePassLiquefactionNotesMember us-gaap:CarryingReportedAmountFairValueDisclosureMember 2019-12-31 0000003570 us-gaap:SeniorNotesMember us-gaap:EstimateOfFairValueFairValueDisclosureMember 2018-12-31 0000003570 us-gaap:SeniorNotesMember us-gaap:CarryingReportedAmountFairValueDisclosureMember 2019-12-31 0000003570 lng:A2025ConvertibleSeniorNotesMember us-gaap:EstimateOfFairValueFairValueDisclosureMember 2019-12-31 0000003570 lng:A2037SabinePassLiquefactionNotesMember us-gaap:CarryingReportedAmountFairValueDisclosureMember 2018-12-31 0000003570 us-gaap:LineOfCreditMember us-gaap:EstimateOfFairValueFairValueDisclosureMember 2019-12-31 0000003570 lng:A2025ConvertibleSeniorNotesMember us-gaap:CarryingReportedAmountFairValueDisclosureMember 2019-12-31 0000003570 lng:A2039CorpusChristiHoldingsSeniorNotesMember us-gaap:EstimateOfFairValueFairValueDisclosureMember 2018-12-31 0000003570 lng:A2045ConvertibleSeniorNotesMember us-gaap:EstimateOfFairValueFairValueDisclosureMember 2019-12-31 0000003570 lng:A2039CorpusChristiHoldingsSeniorNotesMember us-gaap:EstimateOfFairValueFairValueDisclosureMember 2019-12-31 0000003570 lng:A2025ConvertibleSeniorNotesMember us-gaap:EstimateOfFairValueFairValueDisclosureMember 2018-12-31 0000003570 lng:A2045ConvertibleSeniorNotesMember us-gaap:EstimateOfFairValueFairValueDisclosureMember 2018-12-31 0000003570 lng:A2045ConvertibleSeniorNotesMember us-gaap:CarryingReportedAmountFairValueDisclosureMember 2019-12-31 0000003570 lng:A2039CorpusChristiHoldingsSeniorNotesMember us-gaap:CarryingReportedAmountFairValueDisclosureMember 2019-12-31 0000003570 us-gaap:LineOfCreditMember us-gaap:CarryingReportedAmountFairValueDisclosureMember 2019-12-31 0000003570 lng:A2025ConvertibleSeniorNotesMember us-gaap:CarryingReportedAmountFairValueDisclosureMember 2018-12-31 0000003570 lng:CheniereCorpusChristiHoldingsLLCMember lng:A2015CCHTermLoanFacilityMember 2018-05-01 0000003570 lng:CheniereCorpusChristiHoldingsLLCMember lng:CorpusChristiHoldingsWorkingCapitalFacilityMember 2018-12-31 0000003570 lng:CheniereEnergyPartnersLPMember lng:A2029CheniereEnergyPartnersSeniorNotesMember 2019-09-12 0000003570 lng:CheniereCorpusChristiHoldingsLLCMember lng:CorpusChristiHoldingsWorkingCapitalFacilityMember 2019-01-01 2019-12-31 0000003570 lng:DrawnPortionMember lng:CheniereCorpusChristiHoldingsLLCMember lng:CCHLCLoanMember us-gaap:BaseRateMember 2019-01-01 2019-12-31 0000003570 lng:SabinePassLiquefactionMember lng:A2026SPLSeniorNotes2027SPLSeniorNotes2028SPLSeniorNotesand2037SPLSeniorNotesMember 2019-01-01 2019-12-31 0000003570 lng:CheniereCorpusChristiHoldingsLLCMember srt:MaximumMember lng:CorpusChristiHoldingsWorkingCapitalFacilityRevolvingLoansMember us-gaap:LondonInterbankOfferedRateLIBORMember 2019-01-01 2019-12-31 0000003570 lng:A2021ConvertibleUnsecuredNotesMember 2014-11-30 0000003570 lng:FromandAfterTriggerPointMember lng:CheniereRevolvingCreditFacilityMember 2019-01-01 2019-12-31 0000003570 lng:CheniereCorpusChristiHoldingsLLCMember srt:MaximumMember lng:CorpusChristiHoldingsWorkingCapitalFacilityRevolvingLoansMember us-gaap:BaseRateMember 2019-01-01 2019-12-31 0000003570 lng:SabinePassLiquefactionMember srt:MaximumMember lng:WorkingCapitalFacilityMember 2019-01-01 2019-12-31 0000003570 lng:BaseRateDeterminationLIBORMember lng:SabinePassLiquefactionMember lng:WorkingCapitalFacilityMember us-gaap:BaseRateMember 2019-01-01 2019-12-31 0000003570 lng:BaseRateDeterminationLIBORMember lng:CheniereEnergyPartnersLPMember lng:A2019CQPCreditFacilitiesMember 2019-01-01 2019-12-31 0000003570 lng:CheniereCorpusChristiHoldingsLLCMember srt:MinimumMember lng:A2015CCHTermLoanFacilityMember 2019-01-01 2019-12-31 0000003570 lng:CheniereEnergyPartnersLPMember lng:A2029CheniereEnergyPartnersSeniorNotesMember 2019-12-31 0000003570 lng:CheniereCCHHoldcoIILLCMember lng:CheniereCCHHoldcoIILLCMember lng:A2025ConvertibleSeniorNotesMember 2019-01-01 2019-12-31 0000003570 lng:SabinePassLiquefactionMember lng:SabinePassLiquefactionSeniorNotesExcluding2026SPLSeniorNotes2027SPLSeniorNotes2028SPLSeniorNotesand2037SPLSeniorNotesMember 2019-01-01 2019-12-31 0000003570 lng:CheniereEnergyPartnersLPMember srt:MaximumMember lng:A2019CQPCreditFacilitiesCQPRevolvingFacilityMember us-gaap:BaseRateMember 2019-01-01 2019-12-31 0000003570 lng:CheniereEnergyPartnersLPMember lng:A2019CQPCreditFacilitiesCQPTermFacilityMember us-gaap:LondonInterbankOfferedRateLIBORMember 2019-01-01 2019-12-31 0000003570 lng:DrawnPortionMember lng:SabinePassLiquefactionMember us-gaap:LetterOfCreditMember 2019-12-31 0000003570 lng:CheniereCorpusChristiHoldingsLLCMember lng:A2015CCHTermLoanFacilityMember 2019-01-01 2019-12-31 0000003570 lng:BaseRateDeterminationLIBORMember lng:CheniereCorpusChristiHoldingsLLCMember lng:CorpusChristiHoldingsWorkingCapitalFacilityRevolvingLoansMember us-gaap:BaseRateMember 2019-01-01 2019-12-31 0000003570 srt:MaximumMember lng:CheniereRevolvingCreditFacilityMember us-gaap:LondonInterbankOfferedRateLIBORMember 2019-01-01 2019-12-31 0000003570 lng:BaseRateDeterminationFederalFundsRateMember lng:CheniereEnergyPartnersLPMember lng:A2019CQPCreditFacilitiesMember 2019-01-01 2019-12-31 0000003570 lng:CheniereEnergyPartnersLPMember lng:A2029CheniereEnergyPartnersSeniorNotesMember 2019-01-01 2019-12-31 0000003570 lng:CheniereEnergyPartnersLPMember lng:A2019CQPCreditFacilitiesMember 2019-01-01 2019-12-31 0000003570 lng:CheniereEnergyPartnersLPMember srt:MaximumMember lng:CheniereEnergyPartnersSeniorNotesMember 2019-01-01 2019-12-31 0000003570 lng:SabinePassLiquefactionMember lng:WorkingCapitalFacilityMember 2015-09-30 0000003570 lng:CheniereCCHHoldcoIILLCMember lng:A2025ConvertibleSeniorNotesMember 2019-01-01 2019-12-31 0000003570 lng:CheniereCCHHoldcoIILLCMember lng:A2025ConvertibleSeniorNotesMember 2019-12-31 0000003570 lng:CheniereEnergyPartnersLPMember srt:MinimumMember lng:A2019CQPCreditFacilitiesCQPRevolvingFacilityMember us-gaap:LondonInterbankOfferedRateLIBORMember 2019-01-01 2019-12-31 0000003570 lng:CheniereCorpusChristiHoldingsLLCMember srt:MinimumMember lng:A2015CCHTermLoanFacilityMember 2019-12-31 0000003570 lng:SabinePassLiquefactionMember srt:MaximumMember lng:SwingLineLoanMember 2019-01-01 2019-12-31 0000003570 lng:CheniereCorpusChristiHoldingsLLCMember lng:CCHWorkingCapitalLoanMember 2019-01-01 2019-12-31 0000003570 lng:BaseRateDeterminationLIBORMember lng:CheniereRevolvingCreditFacilityMember us-gaap:BaseRateMember 2019-01-01 2019-12-31 0000003570 lng:CheniereCorpusChristiHoldingsLLCMember lng:CorpusChristiHoldingsSeniorNotesMember 2019-01-01 2019-12-31 0000003570 lng:PortionissuedandnotdrawnMember lng:CheniereCorpusChristiHoldingsLLCMember lng:CCHWorkingCapitalFacilityLetterofCreditMember 2019-01-01 2019-12-31 0000003570 lng:DrawnPortionMember lng:CheniereRevolvingCreditFacilityMember us-gaap:BaseRateMember 2019-01-01 2019-12-31 0000003570 srt:MinimumMember lng:CheniereRevolvingCreditFacilityMember us-gaap:LondonInterbankOfferedRateLIBORMember 2019-01-01 2019-12-31 0000003570 lng:A2045ConvertibleSeniorNotesMember 2015-03-31 0000003570 lng:CheniereEnergyPartnersLPMember srt:MinimumMember lng:A2019CQPCreditFacilitiesCQPRevolvingFacilityMember us-gaap:BaseRateMember 2019-01-01 2019-12-31 0000003570 lng:CheniereCorpusChristiHoldingsLLCMember srt:WeightedAverageMember lng:A2039CorpusChristiHoldingsSeniorNotesMember 2019-01-01 2019-12-31 0000003570 lng:CheniereCorpusChristiHoldingsLLCMember lng:A2039CorpusChristiHoldingsSeniorNotesMember 2019-12-31 0000003570 lng:CheniereCorpusChristiHoldingsLLCMember lng:A2015CCHTermLoanFacilityMember us-gaap:BaseRateMember 2019-01-01 2019-12-31 0000003570 lng:CheniereCorpusChristiHoldingsLLCMember lng:A2029CorpusChristiHoldingsSeniorNotesMember 2019-11-06 0000003570 lng:CheniereCorpusChristiHoldingsLLCMember srt:MinimumMember lng:CorpusChristiHoldingsWorkingCapitalFacilityRevolvingLoansMember us-gaap:BaseRateMember 2019-01-01 2019-12-31 0000003570 lng:CheniereEnergyPartnersLPMember lng:CheniereEnergyPartnersSeniorNotesMember 2019-01-01 2019-12-31 0000003570 lng:CheniereCorpusChristiHoldingsLLCMember lng:A2015CCHTermLoanFacilityMember 2018-01-01 2018-12-31 0000003570 lng:CheniereRevolvingCreditFacilityMember 2019-01-01 2019-12-31 0000003570 lng:CheniereRevolvingCreditFacilityMember 2018-12-01 0000003570 lng:CheniereEnergyPartnersLPMember lng:A2019CQPCreditFacilitiesCQPTermFacilityMember us-gaap:BaseRateMember 2019-01-01 2019-12-31 0000003570 lng:CheniereEnergyPartnersLPMember lng:A2026CheniereEnergyPartnersSeniorNotesMember 2019-01-01 2019-12-31 0000003570 lng:CheniereEnergyPartnersLPMember lng:A2019CQPCreditFacilitiesCQPTermFacilityMember 2019-09-12 0000003570 lng:CheniereCorpusChristiHoldingsLLCMember lng:A2039CorpusChristiHoldingsSeniorNotesMember 2019-09-27 0000003570 lng:CheniereCorpusChristiHoldingsLLCMember lng:A20393.925CorpusChristiHoldingsSeniorNotesMember 2019-10-17 0000003570 lng:NoteHoldersMember lng:A2021ConvertibleUnsecuredNotesMember 2019-01-01 2019-12-31 0000003570 lng:CheniereCorpusChristiHoldingsLLCMember lng:CorpusChristiHoldingsWorkingCapitalFacilityMember 2018-06-30 0000003570 srt:MinimumMember lng:CheniereRevolvingCreditFacilityMember us-gaap:BaseRateMember 2019-01-01 2019-12-31 0000003570 lng:CheniereCCHHoldcoIILLCMember lng:NoteHoldersMember lng:A2025ConvertibleSeniorNotesMember 2019-12-31 0000003570 lng:BaseRateDeterminationFederalFundsRateMember lng:CheniereRevolvingCreditFacilityMember us-gaap:BaseRateMember 2019-01-01 2019-12-31 0000003570 lng:PortionissuedandnotdrawnMember lng:SabinePassLiquefactionMember lng:WorkingCapitalFacilityMember 2019-01-01 2019-12-31 0000003570 lng:CheniereCorpusChristiHoldingsLLCMember srt:MinimumMember lng:CorpusChristiHoldingsWorkingCapitalFacilityRevolvingLoansMember us-gaap:LondonInterbankOfferedRateLIBORMember 2019-01-01 2019-12-31 0000003570 lng:SabinePassLiquefactionMember lng:SabinePassLiquefactionSeniorNotesMember 2019-01-01 2019-12-31 0000003570 lng:CheniereCorpusChristiHoldingsLLCMember lng:A2029CorpusChristiHoldingsSeniorNotesMember 2019-12-31 0000003570 lng:CheniereEnergyPartnersLPMember lng:A2019CQPCreditFacilitiesCQPTermFacilityMember 2019-05-31 0000003570 lng:DrawnPortionMember lng:SabinePassLiquefactionMember us-gaap:LetterOfCreditMember us-gaap:BaseRateMember 2019-01-01 2019-12-31 0000003570 lng:CheniereCCHHoldcoIILLCMember lng:NoteHoldersMember lng:A2025ConvertibleSeniorNotesMember 2019-01-01 2019-12-31 0000003570 lng:CheniereCCHHoldcoIILLCMember lng:CheniereCCHHoldcoIILLCMember lng:A2025ConvertibleSeniorNotesMember 2019-12-31 0000003570 lng:CheniereCorpusChristiHoldingsLLCMember lng:A2015CCHTermLoanFacilityMember 2018-05-31 0000003570 lng:BaseRateDeterminationFederalFundsRateMember lng:SabinePassLiquefactionMember lng:WorkingCapitalFacilityMember us-gaap:BaseRateMember 2019-01-01 2019-12-31 0000003570 lng:CheniereEnergyPartnersLPMember srt:MaximumMember lng:A2019CQPCreditFacilitiesCQPRevolvingFacilityMember us-gaap:LondonInterbankOfferedRateLIBORMember 2019-01-01 2019-12-31 0000003570 lng:CheniereCorpusChristiHoldingsLLCMember lng:A20393.925CorpusChristiHoldingsSeniorNotesMember 2019-12-31 0000003570 lng:CheniereCCHHoldcoIILLCMember lng:CheniereCCHHoldcoILLCMember lng:A2025ConvertibleSeniorNotesMember 2019-01-01 2019-12-31 0000003570 lng:PriortoTriggerPointMember lng:CheniereRevolvingCreditFacilityMember 2019-01-01 2019-12-31 0000003570 lng:CheniereCCHHoldcoIILLCMember lng:A2025ConvertibleSeniorNotesMember 2019-01-01 2019-12-31 0000003570 lng:CapitalAllocationFrameworkMember lng:A2015CCHTermLoanFacilityMember 2019-12-31 0000003570 lng:SabinePassLiquefactionMember lng:WorkingCapitalFacilityMember us-gaap:LondonInterbankOfferedRateLIBORMember 2019-01-01 2019-12-31 0000003570 srt:MaximumMember lng:CheniereRevolvingCreditFacilityMember us-gaap:BaseRateMember 2019-01-01 2019-12-31 0000003570 lng:CheniereCorpusChristiHoldingsLLCMember lng:A2015CCHTermLoanFacilityMember 2018-12-31 0000003570 lng:SabinePassLiquefactionMember lng:WorkingCapitalLoanMember 2019-01-01 2019-12-31 0000003570 lng:SabinePassLiquefactionMember lng:WorkingCapitalFacilityMember us-gaap:BaseRateMember 2019-01-01 2019-12-31 0000003570 lng:CheniereEnergyPartnersLPMember lng:A2019CQPCreditFacilitiesCQPRevolvingFacilityMember 2019-12-31 0000003570 lng:CheniereCorpusChristiHoldingsLLCMember lng:CorpusChristiHoldingsWorkingCapitalFacilityRevolvingLoansMember 2019-01-01 2019-12-31 0000003570 lng:SabinePassLiquefactionMember srt:MaximumMember lng:LCLoanMember 2019-01-01 2019-12-31 0000003570 lng:NoteHoldersMember lng:A2021ConvertibleUnsecuredNotesMember 2019-12-31 0000003570 lng:BaseRateDeterminationFederalFundsRateMember lng:CheniereCorpusChristiHoldingsLLCMember lng:CorpusChristiHoldingsWorkingCapitalFacilityRevolvingLoansMember us-gaap:BaseRateMember 2019-01-01 2019-12-31 0000003570 lng:CheniereEnergyPartnersLPMember lng:A2025CheniereEnergyPartnersSeniorNotesMember 2019-01-01 2019-12-31 0000003570 lng:CheniereEnergyPartnersLPMember lng:CheniereEnergyPartnersSeniorNotesMember 2019-12-31 0000003570 lng:SabinePassLiquefactionMember lng:WorkingCapitalFacilityMember 2019-01-01 2019-12-31 0000003570 lng:CheniereCorpusChristiHoldingsLLCMember lng:A2015CCHTermLoanFacilityMember us-gaap:LondonInterbankOfferedRateLIBORMember 2019-01-01 2019-12-31 0000003570 lng:CheniereCorpusChristiHoldingsLLCMember lng:CorpusChristiHoldingsWorkingCapitalFacilityMember 2018-06-01 0000003570 lng:CheniereEnergyPartnersLPMember lng:A2019CQPCreditFacilitiesCQPRevolvingFacilityMember 2019-05-31 0000003570 lng:CheniereEnergyPartnersLPMember lng:A2029CorpusChristiHoldingsSeniorNotesMember 2019-01-01 2019-12-31 0000003570 lng:CheniereCorpusChristiHoldingsLLCMember srt:MaximumMember lng:CCHLCLoanMember 2019-01-01 2019-12-31 0000003570 lng:A2015CCHTermLoanFacilityMember 2019-01-01 2019-12-31 0000003570 lng:WorkingCapitalFacilityMember 2019-01-01 2019-12-31 0000003570 lng:A2019CQPCreditFacilitiesMember 2019-01-01 2019-12-31 0000003570 lng:CorpusChristiHoldingsWorkingCapitalFacilityMember 2019-01-01 2019-12-31 0000003570 srt:MaximumMember lng:A2019CQPCreditFacilitiesMember us-gaap:BaseRateMember 2019-01-01 2019-12-31 0000003570 lng:WorkingCapitalFacilityMember us-gaap:LondonInterbankOfferedRateLIBORMember 2019-01-01 2019-12-31 0000003570 srt:MaximumMember lng:CorpusChristiHoldingsWorkingCapitalFacilityMember us-gaap:BaseRateMember 2019-01-01 2019-12-31 0000003570 srt:MaximumMember lng:CorpusChristiHoldingsWorkingCapitalFacilityMember us-gaap:LondonInterbankOfferedRateLIBORMember 2019-01-01 2019-12-31 0000003570 lng:A2015CCHTermLoanFacilityMember us-gaap:BaseRateMember 2019-01-01 2019-12-31 0000003570 srt:MinimumMember lng:CorpusChristiHoldingsWorkingCapitalFacilityMember us-gaap:BaseRateMember 2019-01-01 2019-12-31 0000003570 srt:MinimumMember lng:CorpusChristiHoldingsWorkingCapitalFacilityMember us-gaap:LondonInterbankOfferedRateLIBORMember 2019-01-01 2019-12-31 0000003570 srt:MinimumMember lng:A2019CQPCreditFacilitiesMember us-gaap:LondonInterbankOfferedRateLIBORMember 2019-01-01 2019-12-31 0000003570 lng:WorkingCapitalFacilityMember us-gaap:BaseRateMember 2019-01-01 2019-12-31 0000003570 lng:A2015CCHTermLoanFacilityMember us-gaap:LondonInterbankOfferedRateLIBORMember 2019-01-01 2019-12-31 0000003570 srt:MinimumMember lng:A2019CQPCreditFacilitiesMember us-gaap:BaseRateMember 2019-01-01 2019-12-31 0000003570 srt:MaximumMember lng:A2019CQPCreditFacilitiesMember us-gaap:LondonInterbankOfferedRateLIBORMember 2019-01-01 2019-12-31 0000003570 lng:CheniereCorpusChristiHoldingsLLCMember srt:WeightedAverageMember lng:A20393.925CorpusChristiHoldingsSeniorNotesMember 2019-01-01 2019-12-31 0000003570 lng:CheniereEnergyPartnersLPMember lng:A2019CQPCreditFacilitiesMember us-gaap:LondonInterbankOfferedRateLIBORMember 2019-01-01 2019-12-31 0000003570 lng:SabinePassLiquefactionMember lng:SwingLineLoanMember 2019-01-01 2019-12-31 0000003570 lng:CheniereEnergyPartnersLPMember lng:A2019CQPCreditFacilitiesCQPTermFacilityMember 2019-09-30 0000003570 lng:A2019CQPCreditFacilitiesCQPRevolvingFacilityMember 2019-12-31 0000003570 srt:MaximumMember 2019-12-31 0000003570 us-gaap:OperatingExpenseMember 2019-01-01 2019-12-31 0000003570 us-gaap:InterestExpenseMember 2019-01-01 2019-12-31 0000003570 lng:DepreciationandAmortizationExpenseMember 2019-01-01 2019-12-31 0000003570 us-gaap:PropertyPlantAndEquipmentMember 2019-12-31 0000003570 lng:OperatingLeaseAssetsMember 2019-12-31 0000003570 lng:CurrentOperatingLeaseLiabilitiesMember 2019-12-31 0000003570 us-gaap:OtherCurrentLiabilitiesMember 2019-12-31 0000003570 lng:NonCurrentOperatingLeaseLiabilitiesMember 2019-12-31 0000003570 us-gaap:OtherNoncurrentLiabilitiesMember 2019-12-31 0000003570 lng:LiquefiedNaturalGasMember 2019-12-31 0000003570 lng:RegasificationServiceMember 2018-12-31 0000003570 lng:RegasificationServiceMember 2019-12-31 0000003570 lng:LiquefiedNaturalGasMember 2018-12-31 0000003570 lng:EachTUACustomerMember 2019-01-01 2019-12-31 0000003570 lng:TUACustomersMember 2019-01-01 2019-12-31 0000003570 lng:LiquefiedNaturalGasProcuredFromThirdPartiesMemberMember 2019-01-01 2019-12-31 0000003570 lng:TerminalUseAgreementRegasificationCapacityPartialMember 2019-01-01 2019-12-31 0000003570 lng:TerminalUseAgreementRegasificationCapacityPartialMember 2017-01-01 2017-12-31 0000003570 lng:TerminalUseAgreementRegasificationCapacityPartialMember 2018-01-01 2018-12-31 0000003570 lng:LiquefiedNaturalGasProcuredFromThirdPartiesMemberMember 2018-01-01 2018-12-31 0000003570 lng:LiquefiedNaturalGasProcuredFromThirdPartiesMemberMember 2017-01-01 2017-12-31 0000003570 lng:SabinePassLiquefactionCorpusChristiLiquefactionandCheniereCorpusChristiLiquefactionStageIIIMember lng:NaturalGasSupplyTransportationAndStorageServiceAgreementsMember 2019-01-01 2019-12-31 0000003570 srt:ParentCompanyMember 2019-01-01 2019-12-31 0000003570 us-gaap:DomesticCountryMember 2019-12-31 0000003570 us-gaap:StateAndLocalJurisdictionMember 2019-01-01 2019-12-31 0000003570 us-gaap:DomesticCountryMember us-gaap:InvestmentCreditMember 2019-12-31 0000003570 us-gaap:StateAndLocalJurisdictionMember 2019-12-31 0000003570 lng:StateandForeignCountryMember 2019-01-01 2019-12-31 0000003570 us-gaap:DomesticCountryMember 2019-01-01 2019-12-31 0000003570 us-gaap:PhantomShareUnitsPSUsMember 2019-01-01 2019-12-31 0000003570 us-gaap:PhantomShareUnitsPSUsMember 2019-12-31 0000003570 us-gaap:RestrictedStockMember 2019-12-31 0000003570 lng:RestrictedShareUnitAndPerformanceStockUnitAwardsMember 2019-01-01 2019-12-31 0000003570 us-gaap:RestrictedStockMember 2019-01-01 2019-12-31 0000003570 lng:RestrictedShareUnitAndPerformanceStockUnitAwardsMember 2019-12-31 0000003570 lng:RestrictedShareUnitAndPerformanceStockUnitAwardsMember 2018-12-31 0000003570 us-gaap:RestrictedStockMember 2018-12-31 0000003570 lng:A2003StockIncentivePlanMember 2019-12-31 0000003570 lng:A2011IncentivePlanMember 2017-01-01 2017-01-31 0000003570 us-gaap:PerformanceSharesMember 2019-01-01 2019-12-31 0000003570 lng:A2015InducementPlanMember 2019-12-31 0000003570 us-gaap:RestrictedStockUnitsRSUMember 2019-01-01 2019-12-31 0000003570 srt:MinimumMember us-gaap:PerformanceSharesMember 2019-01-01 2019-12-31 0000003570 srt:MaximumMember us-gaap:PerformanceSharesMember 2019-01-01 2019-12-31 0000003570 us-gaap:PhantomShareUnitsPSUsMember 2017-01-01 2017-12-31 0000003570 us-gaap:PhantomShareUnitsPSUsMember 2018-01-01 2018-12-31 0000003570 us-gaap:RestrictedStockMember 2018-01-01 2018-12-31 0000003570 us-gaap:RestrictedStockMember 2017-01-01 2017-12-31 0000003570 lng:A2011IncentivePlanMember 2019-12-31 0000003570 lng:RestrictedShareUnitAndPerformanceStockUnitAwardsMember 2017-01-01 2017-12-31 0000003570 lng:RestrictedShareUnitAndPerformanceStockUnitAwardsMember 2018-01-01 2018-12-31 0000003570 lng:LiabilityAwardsMember 2019-01-01 2019-12-31 0000003570 lng:LiabilityAwardsMember 2018-01-01 2018-12-31 0000003570 lng:LiabilityAwardsMember 2017-01-01 2017-12-31 0000003570 lng:EquityAwardsMember 2017-01-01 2017-12-31 0000003570 lng:EquityAwardsMember 2018-01-01 2018-12-31 0000003570 lng:EquityAwardsMember 2019-01-01 2019-12-31 0000003570 us-gaap:PhantomShareUnitsPSUsMember 2018-12-31 0000003570 lng:A2021CheniereConvertibleNotes2025CCHHoldCoIIConvertibleNotesAnd2045CheniereConvertibleNotesMember 2019-01-01 2019-12-31 0000003570 lng:StockOptionsWarrantsAndUnvestedStockMember 2019-01-01 2019-12-31 0000003570 lng:A2021CheniereConvertibleNotesAnd2045CheniereConvertibleNotesMember 2017-01-01 2017-12-31 0000003570 lng:StockOptionsWarrantsAndUnvestedStockMember 2017-01-01 2017-12-31 0000003570 lng:A2021CheniereConvertibleNotesAnd2045CheniereConvertibleNotesMember 2018-01-01 2018-12-31 0000003570 lng:StockOptionsWarrantsAndUnvestedStockMember 2018-01-01 2018-12-31 0000003570 lng:RestrictedStockWithUnsatisfiedPerformanceConditionsMember 2018-01-01 2018-12-31 0000003570 lng:RestrictedStockWithUnsatisfiedPerformanceConditionsMember 2019-01-01 2019-12-31 0000003570 lng:RestrictedStockWithUnsatisfiedPerformanceConditionsMember 2017-01-01 2017-12-31 0000003570 lng:SabinePassLiquefactionCorpusChristiLiquefactionandCheniereCorpusChristiLiquefactionStageIIIMember lng:NaturalGasSupplyTransportationAndStorageServiceAgreementsMember 2019-12-31 0000003570 lng:CheniereLNGTerminalsLLCMember lng:ParallaxEnterprisesMember 2015-12-31 0000003570 lng:SabinePassLiquefactionAndCorpusChristiLiquefactionMember lng:BechtelEPCContractsMember 2019-01-01 2019-12-31 0000003570 lng:SabinePassLiquefactionCorpusChristiLiquefactionandCheniereCorpusChristiLiquefactionStageIIIMember srt:MaximumMember us-gaap:InventoriesMember 2019-01-01 2019-12-31 0000003570 lng:SabinePassLiquefactionAndCorpusChristiLiquefactionMember srt:MaximumMember us-gaap:NaturalGasGatheringTransportationMarketingAndProcessingMember 2019-01-01 2019-12-31 0000003570 lng:SabinePassLiquefactionMember srt:MaximumMember us-gaap:NaturalGasStorageMember 2019-01-01 2019-12-31 0000003570 lng:CheniereLNGTerminalsLLCMember lng:ParallaxEnterprisesMember 2016-03-11 2016-03-11 0000003570 lng:SabinePassLiquefactionMember lng:BechtelEPCContractTrainSixMember 2019-01-01 2019-12-31 0000003570 lng:CorpusChristiLiquefactionMember srt:MaximumMember 2019-12-31 0000003570 lng:CorpusChristiLiquefactionMember lng:BechtelEPCContractTrainThreeMember 2019-01-01 2019-12-31 0000003570 lng:CorpusChristiLiquefactionMember srt:MaximumMember us-gaap:NaturalGasStorageMember 2019-01-01 2019-12-31 0000003570 lng:SabinePassLiquefactionMember srt:MaximumMember 2019-12-31 0000003570 lng:CorpusChristiStage3LiquefactionMember srt:MaximumMember 2019-12-31 0000003570 country:KR us-gaap:GeographicConcentrationRiskMember 2017-01-01 2017-12-31 0000003570 country:GB us-gaap:GeographicConcentrationRiskMember 2019-01-01 2019-12-31 0000003570 country:IE us-gaap:GeographicConcentrationRiskMember 2019-01-01 2019-12-31 0000003570 country:IE us-gaap:GeographicConcentrationRiskMember 2018-01-01 2018-12-31 0000003570 country:IN us-gaap:GeographicConcentrationRiskMember 2018-01-01 2018-12-31 0000003570 us-gaap:GeographicConcentrationRiskMember 2017-01-01 2017-12-31 0000003570 us-gaap:GeographicConcentrationRiskMember 2018-01-01 2018-12-31 0000003570 country:JP us-gaap:GeographicConcentrationRiskMember 2017-01-01 2017-12-31 0000003570 country:GB us-gaap:GeographicConcentrationRiskMember 2018-01-01 2018-12-31 0000003570 lng:OtherNonUsMember us-gaap:GeographicConcentrationRiskMember 2017-01-01 2017-12-31 0000003570 us-gaap:GeographicConcentrationRiskMember 2019-01-01 2019-12-31 0000003570 country:IN us-gaap:GeographicConcentrationRiskMember 2017-01-01 2017-12-31 0000003570 country:ES us-gaap:GeographicConcentrationRiskMember 2018-01-01 2018-12-31 0000003570 country:US us-gaap:GeographicConcentrationRiskMember 2017-01-01 2017-12-31 0000003570 country:GB us-gaap:GeographicConcentrationRiskMember 2017-01-01 2017-12-31 0000003570 lng:OtherNonUsMember us-gaap:GeographicConcentrationRiskMember 2018-01-01 2018-12-31 0000003570 country:SG us-gaap:GeographicConcentrationRiskMember 2017-01-01 2017-12-31 0000003570 country:KR us-gaap:GeographicConcentrationRiskMember 2018-01-01 2018-12-31 0000003570 country:IE us-gaap:GeographicConcentrationRiskMember 2017-01-01 2017-12-31 0000003570 country:US us-gaap:GeographicConcentrationRiskMember 2018-01-01 2018-12-31 0000003570 country:SG us-gaap:GeographicConcentrationRiskMember 2019-01-01 2019-12-31 0000003570 lng:OtherNonUsMember us-gaap:GeographicConcentrationRiskMember 2019-01-01 2019-12-31 0000003570 country:JP us-gaap:GeographicConcentrationRiskMember 2018-01-01 2018-12-31 0000003570 country:KR us-gaap:GeographicConcentrationRiskMember 2019-01-01 2019-12-31 0000003570 country:ES us-gaap:GeographicConcentrationRiskMember 2019-01-01 2019-12-31 0000003570 country:ES us-gaap:GeographicConcentrationRiskMember 2017-01-01 2017-12-31 0000003570 country:IN us-gaap:GeographicConcentrationRiskMember 2019-01-01 2019-12-31 0000003570 country:US us-gaap:GeographicConcentrationRiskMember 2019-01-01 2019-12-31 0000003570 country:SG us-gaap:GeographicConcentrationRiskMember 2018-01-01 2018-12-31 0000003570 country:JP us-gaap:GeographicConcentrationRiskMember 2019-01-01 2019-12-31 0000003570 lng:CustomerAMember us-gaap:AccountsReceivableMember 2019-01-01 2019-12-31 0000003570 lng:CustomerEMember us-gaap:SalesRevenueNetMember 2017-01-01 2017-12-31 0000003570 lng:CustomerCMember us-gaap:SalesRevenueNetMember 2017-01-01 2017-12-31 0000003570 lng:CustomerFMember us-gaap:AccountsReceivableMember 2019-01-01 2019-12-31 0000003570 lng:CustomerDMember us-gaap:SalesRevenueNetMember 2018-01-01 2018-12-31 0000003570 lng:CustomerAMember us-gaap:SalesRevenueNetMember 2018-01-01 2018-12-31 0000003570 lng:CustomerBMember us-gaap:AccountsReceivableMember 2018-01-01 2018-12-31 0000003570 lng:CustomerAMember us-gaap:SalesRevenueNetMember 2017-01-01 2017-12-31 0000003570 lng:CustomerBMember us-gaap:SalesRevenueNetMember 2019-01-01 2019-12-31 0000003570 lng:CustomerAMember us-gaap:SalesRevenueNetMember 2019-01-01 2019-12-31 0000003570 lng:CustomerBMember us-gaap:SalesRevenueNetMember 2017-01-01 2017-12-31 0000003570 lng:CustomerCMember us-gaap:SalesRevenueNetMember 2019-01-01 2019-12-31 0000003570 lng:CustomerEMember us-gaap:AccountsReceivableMember 2018-01-01 2018-12-31 0000003570 lng:CustomerCMember us-gaap:SalesRevenueNetMember 2018-01-01 2018-12-31 0000003570 lng:CustomerDMember us-gaap:SalesRevenueNetMember 2019-01-01 2019-12-31 0000003570 lng:CustomerAMember us-gaap:AccountsReceivableMember 2018-01-01 2018-12-31 0000003570 lng:CustomerFMember us-gaap:AccountsReceivableMember 2018-01-01 2018-12-31 0000003570 lng:CustomerBMember us-gaap:SalesRevenueNetMember 2018-01-01 2018-12-31 0000003570 lng:CustomerCMember us-gaap:AccountsReceivableMember 2018-01-01 2018-12-31 0000003570 lng:CustomerEMember us-gaap:AccountsReceivableMember 2019-01-01 2019-12-31 0000003570 lng:CustomerCMember us-gaap:AccountsReceivableMember 2019-01-01 2019-12-31 0000003570 2019-04-01 2019-06-30 0000003570 2019-10-01 2019-12-31 0000003570 2019-01-01 2019-03-31 0000003570 2018-04-01 2018-06-30 0000003570 2018-01-01 2018-03-31 0000003570 2019-07-01 2019-09-30 0000003570 2018-10-01 2018-12-31 0000003570 2018-07-01 2018-09-30 0000003570 srt:ParentCompanyMember 2019-12-31 0000003570 srt:ParentCompanyMember 2018-12-31 0000003570 srt:ParentCompanyMember 2018-01-01 2018-12-31 0000003570 srt:ParentCompanyMember 2017-01-01 2017-12-31 0000003570 srt:ParentCompanyMember us-gaap:AdditionalPaidInCapitalMember 2019-12-31 0000003570 srt:ParentCompanyMember us-gaap:TreasuryStockMember 2017-01-01 2017-12-31 0000003570 srt:ParentCompanyMember us-gaap:CommonStockMember 2017-12-31 0000003570 srt:ParentCompanyMember us-gaap:AdditionalPaidInCapitalMember 2019-01-01 2019-12-31 0000003570 srt:ParentCompanyMember us-gaap:RetainedEarningsMember 2016-12-31 0000003570 srt:ParentCompanyMember us-gaap:CommonStockMember 2016-12-31 0000003570 srt:ParentCompanyMember 2017-12-31 0000003570 srt:ParentCompanyMember us-gaap:TreasuryStockMember 2019-01-01 2019-12-31 0000003570 srt:ParentCompanyMember us-gaap:RetainedEarningsMember 2019-12-31 0000003570 srt:ParentCompanyMember us-gaap:AdditionalPaidInCapitalMember 2017-01-01 2017-12-31 0000003570 srt:ParentCompanyMember us-gaap:CommonStockMember 2018-12-31 0000003570 srt:ParentCompanyMember us-gaap:TreasuryStockMember 2018-01-01 2018-12-31 0000003570 srt:ParentCompanyMember us-gaap:RetainedEarningsMember 2018-01-01 2018-12-31 0000003570 srt:ParentCompanyMember us-gaap:AdditionalPaidInCapitalMember 2017-12-31 0000003570 srt:ParentCompanyMember us-gaap:AdditionalPaidInCapitalMember 2018-01-01 2018-12-31 0000003570 srt:ParentCompanyMember us-gaap:RetainedEarningsMember 2017-12-31 0000003570 srt:ParentCompanyMember 2016-12-31 0000003570 srt:ParentCompanyMember us-gaap:TreasuryStockMember 2018-12-31 0000003570 srt:ParentCompanyMember us-gaap:RetainedEarningsMember 2018-12-31 0000003570 srt:ParentCompanyMember us-gaap:AdditionalPaidInCapitalMember 2016-12-31 0000003570 srt:ParentCompanyMember us-gaap:TreasuryStockMember 2019-12-31 0000003570 srt:ParentCompanyMember us-gaap:AdditionalPaidInCapitalMember 2018-12-31 0000003570 srt:ParentCompanyMember us-gaap:TreasuryStockMember 2017-12-31 0000003570 srt:ParentCompanyMember us-gaap:RetainedEarningsMember 2017-01-01 2017-12-31 0000003570 srt:ParentCompanyMember us-gaap:CommonStockMember 2019-12-31 0000003570 srt:ParentCompanyMember us-gaap:RetainedEarningsMember 2019-01-01 2019-12-31 0000003570 srt:ParentCompanyMember us-gaap:TreasuryStockMember 2016-12-31 0000003570 srt:ParentCompanyMember lng:CheniereRevolvingCreditFacilityMember 2019-12-31 0000003570 srt:ParentCompanyMember srt:MaximumMember 2019-12-31 0000003570 srt:ParentCompanyMember lng:CheniereRevolvingCreditFacilityMember 2018-12-31 0000003570 srt:ParentCompanyMember us-gaap:AccountingStandardsUpdate201602Member 2019-01-01 0000003570 srt:ParentCompanyMember lng:CheniereRevolvingCreditFacilityMember 2018-12-01 0000003570 srt:ParentCompanyMember lng:CurrentOperatingLeaseLiabilitiesMember 2019-12-31 0000003570 srt:ParentCompanyMember lng:NonCurrentOperatingLeaseLiabilitiesMember 2019-12-31 0000003570 srt:ParentCompanyMember lng:OperatingLeaseAssetsMember 2019-12-31 0000003570 srt:ParentCompanyMember lng:A2021ConvertibleUnsecuredNotesMember 2018-12-31 0000003570 srt:ParentCompanyMember lng:A2021ConvertibleUnsecuredNotesMember 2019-12-31 0000003570 srt:ParentCompanyMember lng:A2045ConvertibleSeniorNotesMember 2019-12-31 0000003570 srt:ParentCompanyMember lng:A2045ConvertibleSeniorNotesMember 2018-12-31 lng:unit xbrli:shares iso4217:USD lng:customer utreg:mi lng:item lng:tbtu lng:milliontonnes utreg:Y lng:trains iso4217:USD xbrli:shares xbrli:pure utreg:D lng:members utreg:Rate utreg:bcf utreg:D



 
UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
Washington, D.C. 20549
FORM 10-K
ANNUAL REPORT PURSUANT TO SECTION 13 OR 15(d) OF THE SECURITIES EXCHANGE ACT OF 1934
For the fiscal year ended December 31, 2019
or
TRANSITION REPORT PURSUANT TO SECTION 13 OR 15(d) OF THE SECURITIES EXCHANGE ACT OF 1934
For the transition period from            to            
Commission file number 001-16383
colorlogoonwhitecmyka49.gif
CHENIERE ENERGY, INC.
(Exact name of registrant as specified in its charter)
Delaware
95-4352386
(State or other jurisdiction of incorporation or organization)
(I.R.S. Employer Identification No.)
700 Milam Street, Suite 1900
Houston, Texas 77002
(Address of principal executive offices) (Zip Code)
(713375-5000
(Registrant’s telephone number, including area code)
Securities registered pursuant to Section 12(b) of the Act: 
Title of each class
Trading Symbol
Name of each exchange on which registered
Common Stock, $ 0.003 par value
LNG
NYSE American
Securities registered pursuant to Section 12(g) of the Act: None 
Indicate by check mark if the registrant is a well-known seasoned issuer, as defined in Rule 405 of the Securities Act.  Yes    No 
Indicate by check mark if the registrant is not required to file reports pursuant to Section 13 or Section 15(d) of the Act. Yes    No   
Indicate by check mark whether the registrant (1) has filed all reports required to be filed by Section 13 or 15(d) of the Securities Exchange Act of 1934 during the preceding 12 months (or for such shorter period that the registrant was required to file such reports), and (2) has been subject to such filing requirements for the past 90 days. Yes    No 
Indicate by check mark whether the registrant has submitted electronically every Interactive Data File required to be submitted pursuant to Rule 405 of Regulation S-T (§232.405 of this chapter) during the preceding 12 months (or for such shorter period that the registrant was required to submit such files).  Yes     No 
Indicate by check mark whether the registrant is a large accelerated filer, an accelerated filer, a non-accelerated filer, a smaller reporting company, or an emerging growth company. See the definitions of “large accelerated filer,” “accelerated filer,” “smaller reporting company” and “emerging growth company” in Rule 12b-2 of the Exchange Act.
 
Large accelerated filer
 
Accelerated filer
 
Non-accelerated filer
 
Smaller reporting company
 
 
 
 
Emerging growth company
If an emerging growth company, indicate by check mark if the registrant has elected not to use the extended transition period for complying with any new or revised financial accounting standards provided pursuant to Section 13(a) of the Exchange Act.
Indicate by check mark whether the registrant is a shell company (as defined in Rule 12b-2 of the Act). Yes    No   
The aggregate market value of the registrant’s Common Stock held by non-affiliates of the registrant was approximately $17.5 billion as of June 28, 2019.
As of February 19, 2020, the issuer had 254,084,493 shares of Common Stock outstanding.
Documents incorporated by reference: The definitive proxy statement for the registrant’s Annual Meeting of Stockholders (to be filed within 120 days of the close of the registrant’s fiscal year) is incorporated by reference into Part III.
 



CHENIERE ENERGY, INC.
TABLE OF CONTENTS





i


DEFINITIONS
As used in this annual report, the terms listed below have the following meanings: 

Common Industry and Other Terms
Bcf
 
billion cubic feet
Bcf/d
 
billion cubic feet per day
Bcf/yr
 
billion cubic feet per year
Bcfe
 
billion cubic feet equivalent
DOE
 
U.S. Department of Energy
EPC
 
engineering, procurement and construction
FERC
 
Federal Energy Regulatory Commission
FTA countries
 
countries with which the United States has a free trade agreement providing for national treatment for trade in natural gas
GAAP
 
generally accepted accounting principles in the United States
Henry Hub
 
the final settlement price (in USD per MMBtu) for the New York Mercantile Exchange’s Henry Hub natural gas futures contract for the month in which a relevant cargo’s delivery window is scheduled to begin
LIBOR
 
London Interbank Offered Rate
LNG
 
liquefied natural gas, a product of natural gas that, through a refrigeration process, has been cooled to a liquid state, which occupies a volume that is approximately 1/600th of its gaseous state
MMBtu
 
million British thermal units, an energy unit
mtpa
 
million tonnes per annum
non-FTA countries
 
countries with which the United States does not have a free trade agreement providing for national treatment for trade in natural gas and with which trade is permitted
SEC
 
U.S. Securities and Exchange Commission
SPA
 
LNG sale and purchase agreement
TBtu
 
trillion British thermal units, an energy unit
Train
 
an industrial facility comprised of a series of refrigerant compressor loops used to cool natural gas into LNG
TUA
 
terminal use agreement


1


Abbreviated Legal Entity Structure

The following diagram depicts our abbreviated legal entity structure as of December 31, 2019, including our ownership of certain subsidiaries, and the references to these entities used in this annual report:
ceiorgchart63019a02.gif
Unless the context requires otherwise, references to “Cheniere,” the “Company,” “we,” “us” and “our” refer to Cheniere Energy, Inc. and its consolidated subsidiaries, including our publicly traded subsidiary, Cheniere Partners.
Unless the context requires otherwise, references to the “CCH Group” refer to CCH HoldCo II, CCH HoldCo I, CCH, CCL and CCP, collectively.
During the year ended December 31, 2018, we closed the merger of Cheniere Energy Partners LP Holdings, LLC (“Cheniere Holdings”) with and into our wholly owned subsidiary. As a result of the merger, Cheniere Holdings is no longer a publicly-traded company.


2


CAUTIONARY STATEMENT
REGARDING FORWARD-LOOKING STATEMENTS


This annual report contains certain statements that are, or may be deemed to be, “forward-looking statements” within the meaning of Section 27A of the Securities Act of 1933, as amended (the “Securities Act”), and Section 21E of the Securities Exchange Act of 1934, as amended (the “Exchange Act”). All statements, other than statements of historical or present facts or conditions, included herein or incorporated herein by reference are “forward-looking statements.” Included among “forward-looking statements” are, among other things: 
statements that we expect to commence or complete construction of our proposed LNG terminals, liquefaction facilities, pipeline facilities or other projects, or any expansions or portions thereof, by certain dates, or at all;
statements regarding future levels of domestic and international natural gas production, supply or consumption or future levels of LNG imports into or exports from North America and other countries worldwide or purchases of natural gas, regardless of the source of such information, or the transportation or other infrastructure or demand for and prices related to natural gas, LNG or other hydrocarbon products;
statements regarding any financing transactions or arrangements, or our ability to enter into such transactions;
statements regarding the amount and timing of share repurchases;
statements relating to the construction of our Trains and pipelines, including statements concerning the engagement of any EPC contractor or other contractor and the anticipated terms and provisions of any agreement with any EPC or other contractor, and anticipated costs related thereto;
statements regarding any SPA or other agreement to be entered into or performed substantially in the future, including any revenues anticipated to be received and the anticipated timing thereof, and statements regarding the amounts of total LNG regasification, natural gas liquefaction or storage capacities that are, or may become, subject to contracts;
statements regarding counterparties to our commercial contracts, construction contracts and other contracts;
statements regarding our planned development and construction of additional Trains or pipelines, including the financing of such Trains or pipelines;
statements that our Trains, when completed, will have certain characteristics, including amounts of liquefaction capacities;
statements regarding our business strategy, our strengths, our business and operation plans or any other plans, forecasts, projections, or objectives, including anticipated revenues, capital expenditures, maintenance and operating costs and cash flows, any or all of which are subject to change;
statements regarding legislative, governmental, regulatory, administrative or other public body actions, approvals, requirements, permits, applications, filings, investigations, proceedings or decisions;
statements regarding our anticipated LNG and natural gas marketing activities; and
any other statements that relate to non-historical or future information.
All of these types of statements, other than statements of historical or present facts or conditions, are forward-looking statements. In some cases, forward-looking statements can be identified by terminology such as “may,” “will,” “could,” “should,” “achieve,” “anticipate,” “believe,” “contemplate,” “continue,” “estimate,” “expect,” “intend,” “plan,” “potential,” “predict,” “project,” “pursue,” “target,” the negative of such terms or other comparable terminology. The forward-looking statements contained in this annual report are largely based on our expectations, which reflect estimates and assumptions made by our management. These estimates and assumptions reflect our best judgment based on currently known market conditions and other factors. Although we believe that such estimates are reasonable, they are inherently uncertain and involve a number of risks and uncertainties beyond our control. In addition, assumptions may prove to be inaccurate. We caution that the forward-looking statements contained in this annual report are not guarantees of future performance and that such statements may not be realized or the forward-looking statements or events may not occur. Actual results may differ materially from those anticipated or implied in forward-looking statements as a result of a variety of factors described in this annual report and in the other reports and other information that we file with the SEC. All forward-looking statements attributable to us or persons acting on our behalf are expressly qualified in their entirety by these risk factors. These forward-looking statements speak only as of the date made, and other than as required by law, we undertake no obligation to update or revise any forward-looking statement or provide reasons why actual results may differ, whether as a result of new information, future events or otherwise.


3




PART I

ITEMS 1. AND 2.
BUSINESS AND PROPERTIES

General
 
Cheniere Energy, Inc. (“Cheniere”), a Delaware corporation, was organized in 1983 and is a Houston-based energy infrastructure company primarily engaged in LNG-related businesses. We provide clean, secure and affordable LNG to integrated energy companies, utilities and energy trading companies around the world. We aspire to conduct our business in a safe and responsible manner, delivering a reliable, competitive and integrated source of LNG to our customers. We own and operate the Sabine Pass LNG terminal in Louisiana, one of the largest LNG production facilities in the world, through our ownership interest in and management agreements with Cheniere Energy Partners, L.P. (“Cheniere Partners”), which is a publicly traded limited partnership that we created in 2007. As of December 31, 2019, we owned 100% of the general partner interest and 48.6% of the limited partner interest in Cheniere Partners. We also own and operate the Corpus Christi LNG terminal in Texas, which is wholly owned by us.

The Sabine Pass LNG terminal is located in Cameron Parish, Louisiana, on the Sabine-Neches Waterway less than four miles from the Gulf Coast. Cheniere Partners, through its subsidiary Sabine Pass Liquefaction, LLC (“SPL”), is currently operating five natural gas liquefaction Trains and is constructing one additional Train for a total production capacity of approximately 30 mtpa of LNG (the “SPL Project”) at the Sabine Pass LNG terminal. The Sabine Pass LNG terminal has operational regasification facilities owned by Cheniere Partners’ subsidiary, Sabine Pass LNG, L.P. (“SPLNG”), that include pre-existing infrastructure of five LNG storage tanks with aggregate capacity of approximately 17 Bcfe, two marine berths that can each accommodate vessels with nominal capacity of up to 266,000 cubic meters and vaporizers with regasification capacity of approximately 4 Bcf/d. Cheniere Partners also owns a 94-mile pipeline through its subsidiary, Cheniere Creole Trail Pipeline, L.P. (“CTPL”), that interconnects the Sabine Pass LNG terminal with a number of large interstate pipelines (the “Creole Trail Pipeline”).

We also own the Corpus Christi LNG terminal near Corpus Christi, Texas, and are currently operating two Trains and are constructing one additional Train for a total production capacity of approximately 15 mtpa of LNG. Additionally, we are operating a 23-mile natural gas supply pipeline that interconnects the Corpus Christi LNG terminal with several interstate and intrastate natural gas pipelines (the “Corpus Christi Pipeline” and together with the Trains, the “CCL Project”) through our subsidiaries Corpus Christi Liquefaction, LLC (“CCL”) and Cheniere Corpus Christi Pipeline, L.P. (“CCP”), respectively. The CCL Project, once fully constructed, will contain three LNG storage tanks with aggregate capacity of approximately 10 Bcfe and two marine berths that can each accommodate vessels with nominal capacity of up to 266,000 cubic meters.

We have contracted approximately 85% of the total production capacity from the SPL Project and the CCL Project (collectively, the “Liquefaction Projects”) on a term basis. This includes volumes contracted under SPAs in which the customers are required to pay a fixed fee with respect to the contracted volumes irrespective of their election to cancel or suspend deliveries of LNG cargoes, as well as volumes contracted under integrated production marketing (“IPM”) gas supply agreements.

Additionally, separate from the CCH Group, we are developing an expansion of the Corpus Christi LNG terminal adjacent to the CCL Project (“Corpus Christi Stage 3”) through our subsidiary Cheniere Corpus Christi Liquefaction Stage III, LLC (“CCL Stage III”) for up to seven midscale Trains with an expected total production capacity of approximately 10 mtpa of LNG. We received approval from FERC in November 2019 to site, construct and operate the expansion project.

We remain focused on operational excellence and customer satisfaction. Increasing demand of LNG has allowed us to expand our liquefaction infrastructure in a financially disciplined manner. We hold significant land positions at both the Sabine Pass LNG terminal and the Corpus Christi LNG terminal which provide opportunity for further liquefaction capacity expansion. The development of these sites or other projects, including infrastructure projects in support of natural gas supply and LNG demand, will require, among other things, acceptable commercial and financing arrangements before we can make a final investment decision (“FID”).

4




Although results are consolidated for financial reporting, Cheniere, Cheniere Partners, SPL and the CCH Group operate with independent capital structures. The following diagram depicts our abbreviated capital structure as of December 31, 2019:
ceicapitalstructure2019.gif

Our Business Strategy

Our primary business strategy is to be a full service LNG provider to worldwide end-use customers. We accomplish this objective by owning, constructing and operating LNG and natural gas infrastructure facilities to meet our long-term customers’ energy demands and: 
safely, efficiently and reliably operating and maintaining our assets;
procuring natural gas and pipeline transport capacity to our facilities;
commencing commercial delivery for our long-term SPA customers, of which we have initiated for 13 of 19 long-term SPA customers as of December 31, 2019;
safely, on-time and on-budget completing our expansion construction projects, including the development of Corpus Christi Stage 3;
maximizing the production of LNG to serve our long-term customers and generating steady and stable revenues and operating cash flows; and
maintaining a flexible capital structure to finance the acquisition, development, construction and operation of the energy assets needed to supply our customers.


5




LNG Terminals and Marketing
 
We shipped our first LNG cargo in February 2016 and we shipped our 1,000th cargo in January 2020. Cheniere’s LNG has been shipped to over 30 countries and regions around the world.

Sabine Pass LNG Terminal

Liquefaction Facilities

The SPL Project is one of the largest LNG production facilities in the world. Through Cheniere Partners, we are currently operating five Trains and two marine berths at the SPL Project and are constructing one additional Train. We have received authorization from the FERC to site, construct and operate Trains 1 through 6. We have achieved substantial completion of the first five Trains of the SPL Project and commenced commercial operating activities for each Train at various times starting in May 2016. The following table summarizes the project completion and construction status of Train 6 of the SPL Project as of December 31, 2019:
 
 
SPL Train 6
Overall project completion percentage
 
43.7%
Completion percentage of:
 

Engineering
 
91.5%
Procurement
 
60.9%
Subcontract work
 
37.4%
Construction
 
9.7%
Date of expected substantial completion
 
1H 2023

The following orders have been issued by the DOE authorizing the export of domestically produced LNG by vessel from the Sabine Pass LNG terminal:
Trains 1 through 4—FTA countries for a 30-year term, which commenced in May 2016, and non-FTA countries for a 20-year term, which commenced in June 2016, in an amount up to a combined total of the equivalent of 16 mtpa (approximately 803 Bcf/yr of natural gas).
Trains 1 through 4—FTA countries for a 25-year term and non-FTA countries for a 20-year term, both of which commenced in December 2018, in an amount up to a combined total of the equivalent of approximately 203 Bcf/yr of natural gas (approximately 4 mtpa).
Trains 5 and 6—FTA countries and non-FTA countries for a 20-year term, which partially commenced in June 2019 and the remainder commenced in September 2019, in an amount up to a combined total of 503.3 Bcf/yr of natural gas (approximately 10 mtpa).

In each case, the terms of these authorizations began on the earlier of the date of first export thereunder or the date specified in the particular order. In addition, SPL received an order providing for a three-year makeup period with respect to each of the non-FTA orders for LNG volumes SPL was authorized but unable to export during any portion of the initial 20-year export period of such order.

The DOE issued orders authorizing SPL to export domestically produced LNG by vessel from the Sabine Pass LNG terminal to FTA countries and non-FTA countries over a two-year period commencing January 2020, in an aggregate amount up to the equivalent of 600 Bcf of natural gas (however, exports under this order, when combined with exports under the orders above, may not exceed 1,509 Bcf/yr).

An application was filed in September 2019 to authorize additional exports from the SPL Project to FTA countries for a 25-year term and to non-FTA countries for a 20-year term in an amount up to the equivalent of approximately 153 Bcf/yr of natural gas, for a total SPL Project export of approximately 1,662 Bcf/yr. The terms of the authorizations are requested to commence on the date of first commercial export from the SPL Project of the volumes contemplated in the application. The application is currently pending before DOE.


6




Customers

SPL has entered into fixed price long-term SPAs generally with terms of 20 years (plus extension rights) with eight third parties for Trains 1 through 6 of the SPL Project. Under these SPAs, the customers will purchase LNG from SPL on a free on board (“FOB”) basis for a price consisting of a fixed fee per MMBtu of LNG (a portion of which is subject to annual adjustment for inflation) plus a variable fee per MMBtu of LNG equal to approximately 115% of Henry Hub. The customers may elect to cancel or suspend deliveries of LNG cargoes, with advance notice as governed by each respective SPA, in which case the customers would still be required to pay the fixed fee with respect to the contracted volumes that are not delivered as a result of such cancellation or suspension. We refer to the fee component that is applicable regardless of a cancellation or suspension of LNG cargo deliveries under the SPAs as the fixed fee component of the price under SPL’s SPAs. We refer to the fee component that is applicable only in connection with LNG cargo deliveries as the variable fee component of the price under SPL’s SPAs. The variable fees under SPL’s SPAs were generally sized at the time of entry into each SPA with the intent to cover the costs of gas purchases and transportation and liquefaction fuel to produce the LNG to be sold under each such SPA. The SPAs and contracted volumes to be made available under the SPAs are not tied to a specific Train; however, the term of each SPA generally commences upon the date of first commercial delivery of a specified Train.

In aggregate, the annual fixed fee portion to be paid by the third-party SPA customers is approximately $2.9 billion for Trains 1 through 5. After giving effect to an SPA that Cheniere has committed to provide to SPL by the end of 2020, the annual fixed fee portion to be paid by the third-party SPA customers would increase to at least $3.3 billion, which is expected to occur upon the date of first commercial delivery of Train 6.

In addition, Cheniere Marketing has agreements with SPL to purchase, at Cheniere Marketing’s option, any LNG produced by SPL in excess of that required for other customers. See Marketing section for additional information regarding agreements entered into by Cheniere Marketing.

The annual contracted cash flows from fixed fees of each buyer of LNG under SPL’s third-party SPAs that constitute more than 10% of SPL’s aggregate fixed fees under all its SPAs are:
approximately $720 million from BG Gulf Coast LNG, LLC (“BG”), which is guaranteed by BG Energy Holdings Limited;
approximately $550 million from Korea Gas Corporation (“KOGAS”);
approximately $550 million from GAIL;
approximately $450 million from Naturgy LNG GOM, Limited (formerly known as Gas Natural Fenosa LNG GOM, Limited) (“Naturgy”), which is guaranteed by Naturgy Energy Group, S.A. (formerly known as Gas Natural SDG S.A.); and
approximately $310 million from Total Gas & Power North America, Inc. (“Total”), which is guaranteed by Total S.A.

The annual aggregate fixed fees for all of SPL’s other SPAs with third-parties is approximately $490 million, prior to giving effect to an SPA that Cheniere has committed to provide to SPL by the end of 2020.

Natural Gas Transportation, Storage and Supply

To ensure SPL is able to transport adequate natural gas feedstock to the Sabine Pass LNG terminal, it has entered into transportation precedent and other agreements to secure firm pipeline transportation capacity with CTPL and third-party pipeline companies. SPL has entered into firm storage services agreements with third parties to assist in managing variability in natural gas needs for the SPL Project. SPL has also entered into enabling agreements and long-term natural gas supply contracts with third parties in order to secure natural gas feedstock for the SPL Project. As of December 31, 2019, SPL had secured up to approximately 3,850 TBtu of natural gas feedstock through long-term and short-term natural gas supply contracts with remaining terms that range up to 10 years, a portion of which is subject to conditions precedent.

Construction

SPL entered into lump sum turnkey contracts with Bechtel Oil, Gas and Chemicals, Inc. (“Bechtel”) for the engineering, procurement and construction of Trains 1 through 6 of the SPL Project, under which Bechtel charges a lump sum for all work

7




performed and generally bears project cost, schedule and performance risks unless certain specified events occur, in which case Bechtel may cause SPL to enter into a change order, or SPL agrees with Bechtel to a change order.
The total contract price of the EPC contract for Train 6 of the SPL Project is approximately $2.5 billion, including estimated costs for an optional third marine berth. As of December 31, 2019, we have incurred $1.1 billion under this contract.

Regasification Facilities
 
The Sabine Pass LNG terminal has operational regasification capacity of approximately 4 Bcf/d and aggregate LNG storage capacity of approximately 17 Bcfe. Approximately 2 Bcf/d of the regasification capacity at the Sabine Pass LNG terminal has been reserved under two long-term third-party TUAs, under which SPLNG’s customers are required to pay fixed monthly fees, whether or not they use the LNG terminal.  Each of Total and Chevron U.S.A. Inc. (“Chevron”) has reserved approximately 1 Bcf/d of regasification capacity and is obligated to make monthly capacity payments to SPLNG aggregating approximately $125 million annually, prior to inflation adjustments, for 20 years that commenced in 2009. Total S.A. has guaranteed Total’s obligations under its TUA up to $2.5 billion, subject to certain exceptions, and Chevron Corporation has guaranteed Chevron’s obligations under its TUA up to 80% of the fees payable by Chevron.

The remaining approximately 2 Bcf/d of capacity has been reserved under a TUA by SPL. SPL is obligated to make monthly capacity payments to SPLNG aggregating approximately $250 million annually, prior to inflation adjustments, continuing until at least May 2036. SPL entered into a partial TUA assignment agreement with Total, whereby upon substantial completion of Train 5 of the SPL Project, SPL gained access to substantially all of Total’s capacity and other services provided under Total’s TUA with SPLNG. This agreement provides SPL with additional berthing and storage capacity at the Sabine Pass LNG terminal that may be used to provide increased flexibility in managing LNG cargo loading and unloading activity, permit SPL to more flexibly manage its LNG storage capacity and accommodate the development of Train 6. Notwithstanding any arrangements between Total and SPL, payments required to be made by Total to SPLNG will continue to be made by Total to SPLNG in accordance with its TUA. During the years ended December 31, 2019, 2018 and 2017, SPL recorded $104 million, $30 million and $23 million, respectively, as operating and maintenance expense under this partial TUA assignment agreement.

Under each of these TUAs, SPLNG is entitled to retain 2% of the LNG delivered to the Sabine Pass LNG terminal.

Corpus Christi LNG Terminal

Liquefaction Facilities

We are currently operating two Trains and one marine berth at the CCL Project and are constructing one additional Train and marine berth. We have received authorization from the FERC to site, construct and operate Trains 1 through 3 of the CCL Project. We completed construction of Trains 1 and 2 of the CCL Project and commenced commercial operating activities in February 2019 and August 2019, respectively. The following table summarizes the project completion and construction status of Train 3 of the CCL Project, including the related infrastructure, as of December 31, 2019:
 
 
CCL Train 3
Overall project completion percentage
 
74.8%
Completion percentage of:
 
 
Engineering
 
98.7%
Procurement
 
99.5%
Subcontract work
 
28.3%
Construction
 
49.5%
Expected date of substantial completion
 
1H 2021

Separate from the CCH Group, we are also developing Corpus Christi Stage 3 through our subsidiary CCL Stage III, adjacent to the CCL Project. We received approval from FERC in November 2019 to site, construct and operate seven midscale Trains with an expected total production capacity of approximately 10 mtpa of LNG.


8




The following orders have been issued by the DOE authorizing the export of domestically produced LNG by vessel from the Corpus Christi LNG terminal:
CCL ProjectFTA countries for a 25-year term and to non-FTA countries for a 20-year term, both of which commenced in June 2019, up to a combined total of the equivalent of 767 Bcf/yr (approximately 15 mtpa) of natural gas.
Corpus Christi Stage 3FTA countries for a 25-year term and to non-FTA countries for a 20-year term in an amount equivalent to 582.14 Bcf/yr (approximately 11 mtpa) of natural gas.

In each case, the terms of these authorizations begin on the earlier of the date of first export thereunder or the date specified in the particular order, which ranges from seven to 10 years from the date the order was issued.

An application was filed in September 2019 to authorize additional exports from the CCL Project to FTA countries for a 25-year term and to non-FTA countries for a 20-year term in an amount up to the equivalent of approximately 108 Bcf/yr of natural gas, for a total CCL Project export of 875.16 Bcf/yr. The terms of the authorizations are requested to commence on the date of first commercial export from the CCL Project of the volumes contemplated in the application. The application is currently pending before DOE.

Customers

CCL has entered into fixed price long-term SPAs generally with terms of 20 years (plus extension rights) with nine third parties for Trains 1 through 3 of the CCL Project. Under these SPAs, the customers will purchase LNG from CCL on a FOB basis for a price consisting of a fixed fee per MMBtu of LNG (a portion of which is subject to annual adjustment for inflation) plus a variable fee per MMBtu of LNG equal to approximately 115% of Henry Hub. The customers may elect to cancel or suspend deliveries of LNG cargoes, with advance notice as governed by each respective SPA, in which case the customers would still be required to pay the fixed fee with respect to the contracted volumes that are not delivered as a result of such cancellation or suspension. We refer to the fee component that is applicable regardless of a cancellation or suspension of LNG cargo deliveries under the SPAs as the fixed fee component of the price under our SPAs. We refer to the fee component that is applicable only in connection with LNG cargo deliveries as the variable fee component of the price under our SPAs. The variable fee under CCL’s SPAs entered into in connection with the development of the CCL Project was sized at the time of entry into each SPA with the intent to cover the costs of gas purchases and transportation and liquefaction fuel to produce the LNG to be sold under each such SPA. The SPAs and contracted volumes to be made available under the SPAs are not tied to a specific Train; however, the term of each SPA generally commences upon the date of first commercial delivery for the applicable Train, as specified in each SPA.

In aggregate, the minimum fixed fee portion to be paid by the third-party SPA customers is approximately $550 million for Train 1, increasing to approximately $1.4 billion upon the date of first commercial delivery for Train 2 and further increasing to approximately $1.8 billion following the substantial completion of Train 3 of the CCL Project.

The annual contracted cash flows from fixed fees of each buyer of LNG under CCL’s third-party SPAs that constitute more than 10% of CCL’s aggregate fixed fees under all its SPAs for Trains 1 through 3 of the CCL Project are:
approximately $410 million from Endesa S.A.;
approximately $280 million from PT Pertamina (Persero); and
approximately $270 million from Naturgy, which is guaranteed by Naturgy Energy Group, S.A.

The average annual contracted cash flow from fixed fees for all of CCL’s other SPAs with third-parties is approximately $790 million.

In addition, Cheniere Marketing has agreements with CCL to purchase: (1) 15 TBtu per annum of LNG with an approximate term of 23 years, (2) any LNG produced by CCL in excess of that required for other customers at Cheniere Marketing’s option and (3) 0.85 mtpa of LNG with a term of up to seven years associated with an IPM gas supply agreement, as described below. See Marketing section for additional information regarding agreements entered into by Cheniere Marketing.

Natural Gas Transportation, Storage and Supply

To ensure CCL is able to transport adequate natural gas feedstock to the Corpus Christi LNG terminal, it has entered into transportation precedent agreements to secure firm pipeline transportation capacity with CCP and certain third-party pipeline

9




companies. CCL has entered into a firm storage services agreement with a third party to assist in managing variability in natural gas needs for the CCL Project. CCL has also entered into enabling agreements and long-term natural gas supply contracts with third parties, and will continue to enter into such agreements, in order to secure natural gas feedstock for the CCL Project. As of December 31, 2019, CCL had secured up to approximately 2,999 TBtu of natural gas feedstock through long-term natural gas supply contracts with remaining terms that range up to eight years, a portion of which is subject to the achievement of certain project milestones and other conditions precedent.
CCL Stage III has also entered into long-term natural gas supply contracts with third parties, and anticipates continuing to enter into such agreements, in order to secure natural gas feedstock for Corpus Christi Stage 3. As of December 31, 2019, CCL Stage III had secured up to approximately 2,361 TBtu of natural gas feedstock through long-term natural gas supply contracts with remaining terms that range up to approximately 15 years, which is subject to the achievement of certain project milestones and other conditions precedent.

A portion of the natural gas feedstock transactions for CCL and CCL Stage III are IPM transactions, in which the natural gas producers are paid based on a global gas market price less a fixed liquefaction fee and certain costs incurred by us.
  
Construction

CCL entered into separate lump sum turnkey contracts with Bechtel for the engineering, procurement and construction of Trains 1 through 3 of the CCL Project under which Bechtel charges a lump sum for all work performed and generally bears project cost, schedule and performance risks unless certain specified events occur, in which case Bechtel may cause CCL to enter into a change order, or CCL agrees with Bechtel to a change order.

The total contract price of the EPC contract for Train 3, which is currently under construction, is approximately $2.4 billion, reflecting amounts incurred under change orders through December 31, 2019. As of December 31, 2019, we have incurred $2.0 billion under this contract.

Final Investment Decision for Corpus Christi Stage 3

FID for Corpus Christi Stage 3 will be subject to, among other things, entering into an EPC contract, obtaining additional commercial support for the project and securing the necessary financing arrangements.

Pipeline Facilities

In December 2014, the FERC issued a certificate of public convenience and necessity under Section 7(c) of the Natural Gas Act of 1938, as amended (the “NGA”), authorizing CCP to construct and operate the Corpus Christi Pipeline. The Corpus Christi Pipeline is designed to transport 2.25 Bcf/d of natural gas feedstock required by the CCL Project from the existing regional natural gas pipeline grid. The construction of the Corpus Christi Pipeline was completed in the second quarter of 2018.

In November 2019, the FERC authorized CCP to construct and operate the pipeline for Corpus Christi Stage 3. The pipeline will be designed to transport 1.5 Bcf/d of natural gas feedstock required by Corpus Christi Stage 3 from the existing regional natural gas pipeline grid.

Marketing

We market and sell LNG produced by the Liquefaction Projects that is not required for other customers through our integrated marketing function. We have, and continue to develop, a portfolio of long-, medium- and short-term SPAs to transport and unload commercial LNG cargoes to locations worldwide. These volumes are expected to be primarily sourced by LNG produced by the Liquefaction Projects but supplemented by volumes procured from other locations worldwide, as needed. As of December 31, 2019, we have sold or have options to sell approximately 4,935 TBtu of LNG to be delivered to customers between 2020 and 2045, excluding volumes for agreements anticipated to be assigned to SPL in the future.  The cargoes have been sold either on a FOB basis (delivered to the customer at the Sabine Pass LNG terminal or the Corpus Christi LNG terminal, as applicable) or a delivered at terminal (“DAT”) basis (delivered to the customer at their LNG receiving terminal). We have chartered LNG vessels to be utilized for cargoes sold on a DAT basis. In addition, we have entered into a long-term agreement to sell LNG cargoes on a DAT basis that is conditioned upon the buyer achieving certain milestones.


10




Significant Customers

The following table shows customers with revenues of 10% or greater of total revenues from external customers:
 
Percentage of Total Revenues from External Customers
 
Year Ended December 31,
 
2019
 
2018
 
2017
BG and its affiliates
16%
 
18%
 
24%
Naturgy
10%
 
14%
 
14%
KOGAS
11%
 
19%
 
14%
GAIL
11%
 
13%
 
*
JERA Co., Inc.
*
 
*
 
17%
 
* Less than 10%

Competition

If and when SPL, CCL or our integrated marketing function need to replace any existing SPA or enter into new SPAs, they will compete on the basis of price per contracted volume of LNG with each other and other natural gas liquefaction projects throughout the world. Revenues associated with any incremental volumes, including those sold by our integrated marketing function discussed above, will also be subject to market-based price competition. Many of the companies with which we compete are major energy corporations with longer operating histories, more development experience, greater name recognition, greater financial, technical and marketing resources and greater access to markets than us. We have proximity to our customers, with offices located in Houston, London, Singapore, Beijing and Tokyo.

SPLNG currently does not experience competition for its terminal capacity because the entire approximately 4 Bcf/d of regasification capacity that is available at the Sabine Pass LNG terminal has been fully contracted. If and when SPLNG has to replace any TUAs, it will compete with other then-existing LNG terminals for customers.

Governmental Regulation
 
Our LNG terminals and pipelines are subject to extensive regulation under federal, state and local statutes, rules, regulations and laws. These laws require that we engage in consultations with appropriate federal and state agencies and that we obtain and maintain applicable permits and other authorizations. These regulatory requirements increase the cost of construction and operation, and failure to comply with such laws could result in substantial penalties and/or loss of necessary authorizations.

Federal Energy Regulatory Commission
The design, construction, operation, maintenance and expansion of our liquefaction facilities, the import or export of LNG and the purchase and transportation of natural gas in interstate commerce through our pipelines (including our Creole Trail Pipeline and Corpus Christi Pipeline) are highly regulated activities subject to the jurisdiction of the FERC pursuant to the NGA. Under the NGA, the FERC’s jurisdiction generally extends to the transportation of natural gas in interstate commerce, to the sale for resale of natural gas in interstate commerce, to natural gas companies engaged in such transportation or sale and to the construction, operation, maintenance and expansion of LNG terminals and interstate natural gas pipelines.

 The FERC’s authority to regulate interstate natural gas pipelines and the services that they provide generally includes regulation of:

rates and charges, and terms and conditions for natural gas transportation, storage and related services;
the certification and construction of new facilities and modification of existing facilities;
the extension and abandonment of services and facilities;
the administration of accounting and financial reporting regulations, including the maintenance of accounts and records;
the acquisition and disposition of facilities;

11




the initiation and discontinuation of services; and
various other matters.

Under the NGA, our pipelines are not permitted to unduly discriminate or grant undue preference as to rates or the terms and conditions of service to any shipper, including its own marketing affiliate. Those rates, terms and conditions must be public, and on file with the FERC. In contrast to pipeline regulation, the FERC does not require LNG terminal owners to provide open-access services at cost-based or regulated rates. Although the provisions that codified FERC’s policy in this area expired on January 1, 2015, we see no indication that the FERC intends to change its policy in this area.

We are permitted to make sales of natural gas for resale in interstate commerce pursuant to a blanket marketing certificate automatically granted by the FERC to our marketing affiliates. Our sales of natural gas will be affected by the availability, terms and cost of pipeline transportation. As noted above, the price and terms of access to pipeline transportation are subject to extensive federal and state regulation.

In order to site, construct and operate our LNG terminals, we received and are required to maintain authorizations from the FERC under Section 3 of the NGA as well as other material governmental and regulatory approvals and permits. The Energy Policy Act of 2005 (the “EPAct”) amended Section 3 of the NGA to establish or clarify the FERC’s exclusive authority to approve or deny an application for the siting, construction, expansion or operation of LNG terminals, unless specifically provided otherwise in the EPAct, amendments to the NGA. For example, nothing in the EPAct amendments to the NGA were intended to affect otherwise applicable law related to any other federal agency’s authorities or responsibilities related to LNG terminals or those of a state acting under federal law.

The FERC issued final orders in April and July 2012 approving our application for an order under Section 3 of the NGA authorizing the siting, construction and operation of Trains 1 through 4 of the SPL Project (and related facilities). Subsequently, the FERC issued written approval to commence site preparation work for Trains 1 through 4. In October 2012, we applied to amend the FERC approval to reflect certain modifications to the SPL Project, and in August 2013, the FERC issued an order approving the modifications. In October 2013, we applied to further amend the FERC approval, requesting authorization to increase the total permitted LNG production capacity of Trains 1 through 4 from the then authorized 803 Bcf/yr to 1,006 Bcf/yr so as to more accurately reflect the estimated maximum LNG production capacity of Trains 1 through 4. In February 2014, the FERC issued an order approving the October 2013 application (the “February 2014 Order”). A party to the proceeding requested a rehearing of the February 2014 Order, and in September 2014, the FERC issued an order denying the rehearing request (the “FERC Order Denying Rehearing”). The party petitioned the U.S. Court of Appeals for the District of Columbia Circuit (the “Court of Appeals”) to review the February 2014 Order and the FERC Order Denying Rehearing. The court denied the petition in June 2016. In September 2013, we filed an application with the FERC for authorization to add Trains 5 and 6 to the SPL Project, which was granted by the FERC in an order issued in April 2015 and an order denying rehearing issued in June 2015. These orders are not subject to appellate court review. In October of 2018, SPL applied to the FERC for authorization to add a third marine berth to the Sabine Pass LNG terminal facilities.

The Creole Trail Pipeline, which interconnects with the Sabine Pass LNG terminal, holds a certificate of public convenience and necessity from the FERC under Section 7 of the NGA. The FERC’s approval under Section 7 of the NGA, as well as several other material governmental and regulatory approvals and permits, may be required prior to making any modifications to the Creole Trail Pipeline as it is a regulated, interstate natural gas pipeline. In 2013, the FERC approved CTPL’s application for authorization to construct, own, operate and maintain certain new facilities in order to enable bi-directional natural gas flow on the Creole Trail Pipeline system to allow for the delivery of up to 1,530,000 Dekatherms per day of feed gas to the Sabine Pass LNG terminal. In November 2013, CTPL received approval from the Louisiana Department of Environmental Quality (“LDEQ”) for the proposed modifications and, with subsequent final FERC clearance, construction was completed in 2015. In September 2013, we filed an application with the FERC for authorization to construct and operate an extension and expansion of Creole Trail Pipeline and related facilities in order to deliver additional domestic natural gas supplies to the Sabine Pass LNG terminal, which was granted by the FERC in an order issued in April 2015 and an order denying rehearing issued in June 2015. These orders are not subject to appellate court review.
In December 2014, the FERC issued an order granting CCL authorization under Section 3 of the NGA to site, construct and operate Trains 1 through 3 of the CCL Project and issued a certificate of public convenience and necessity under Section 7(c) of the NGA authorizing construction and operation of the Corpus Christi Pipeline (the “December 2014 Order”). A party to the proceeding requested a rehearing of the December 2014 Order, and in May 2015, the FERC denied rehearing (the “Order Denying Rehearing”). The party petitioned the relevant Court of Appeals to review the December 2014 Order and the Order Denying

12




Rehearing; that petition was denied on November 4, 2016. In June of 2018, CCL Stage III, CCL and CCP filed an application with the FERC for authorization under section 3 of the NGA to site, construct and operate additional facilities for the liquefaction and export of domestically-produced natural gas (“Corpus Christi Stage 3”) at the existing CCL Project. In November 2019, the FERC authorized CCP to construct and operate the pipeline for Corpus Christi Stage 3. Corpus Christi Stage 3 consists of the addition of seven midscale Trains and related facilities. The order is not subject to appellate court review.

On September 27, 2019, CCL and SPL filed a request with the FERC pursuant to section 3 of the NGA, requesting authorization to increase the total LNG production capacity of each terminal from currently authorized levels to an amount which reflects more accurately the capacity of each facility based on enhancements during the engineering, design and construction process, as well as operational experience to date. The requested authorizations do not involve construction of new facilities. Corresponding applications for authorization to export the incremental volumes were also submitted to the DOE.

The FERC’s Standards of Conduct apply to interstate pipelines that conduct transmission transactions with an affiliate that engages in natural gas marketing functions. The general principles of the FERC Standards of Conduct are: (1) independent functioning, which requires transmission function employees to function independently of marketing function employees; (2) no-conduit rule, which prohibits passing transmission function information to marketing function employees; and (3) transparency, which imposes posting requirements to detect undue preference due to the improper disclosure of non-public transmission function information. We have established the required policies, procedures and training to comply with the FERC’s Standards of Conduct.

All of our FERC construction, operation, reporting, accounting and other regulated activities are subject to audit by the FERC, which may conduct routine or special inspections and issue data requests designed to ensure compliance with FERC rules, regulations, policies and procedures. The FERC’s jurisdiction under the NGA allows it to impose civil and criminal penalties for any violations of the NGA and any rules, regulations or orders of the FERC up to approximately $1.3 million per day per violation, including any conduct that violates the NGA’s prohibition against market manipulation.

Several other material governmental and regulatory approvals and permits will be required throughout the life of our LNG terminals and our pipelines. In addition, our FERC orders require us to comply with certain ongoing conditions, reporting obligations and maintain other regulatory agency approvals throughout the life of our facilities. For example, throughout the life of our LNG terminals and our pipelines, we are subject to regular reporting requirements to the FERC, the Department of Transportation’s (“DOT”) Pipeline and Hazardous Materials Safety Administration (“PHMSA”) and applicable federal and state regulatory agencies regarding the operation and maintenance of our facilities. To date, we have been able to obtain and maintain required approvals as needed, and the need for these approvals and reporting obligations have not materially affected our construction or operations.

DOE Export License

The DOE has authorized the export of domestically produced LNG by vessel from the Sabine Pass LNG terminal as discussed in Sabine Pass LNG TerminalLiquefaction Facilities and the Corpus Christi LNG terminal as discussed in Corpus Christi LNG TerminalLiquefaction Facilities. Although it is not expected to occur, the loss of an export authorization could be a force majeure event under our SPAs.

Under Section 3 of the NGA applications for exports of natural gas to FTA countries, which allow for national treatment for trade in natural gas, are “deemed to be consistent with the public interest” and shall be granted by the DOE without “modification or delay.” FTA countries currently recognized by the DOE for exports of LNG include Australia, Bahrain, Canada, Chile, Colombia, Dominican Republic, El Salvador, Guatemala, Jordan, Mexico, Morocco, Nicaragua, Oman, Panama, Peru, Republic of Korea and Singapore. Applications for export of LNG to non-FTA countries are considered by the DOE in a notice and comment proceeding whereby the public and other interveners are provided the opportunity to comment and may assert that such authorization would not be consistent with the public interest.
Pipeline and Hazardous Materials Safety Administration

Our LNG terminals as well as the Creole Trail Pipeline and the Corpus Christi Pipeline are subject to regulation by PHMSA. PHMSA is authorized by the applicable pipeline safety laws to establish minimum safety standards for certain pipelines and LNG facilities. The regulatory standards PHMSA has established are applicable to the design, installation, testing, construction, operation, maintenance and management of natural gas and hazardous liquid pipeline facilities and LNG facilities that affect interstate or foreign commerce. PHMSA has also established training, worker qualification and reporting requirements.


13




In October 2019, PHMSA published final rules revising its regulations governing the safety of certain gas transmission pipelines (effective July 1, 2020) and established new enforcement procedures for the issuance of temporary emergency orders (effective December 2, 2019).

PHMSA performs inspections of pipeline and LNG facilities and has authority to undertake enforcement actions, including issuance of civil penalties up to approximately $218,000 per day per violation, with a maximum administrative civil penalty of approximately $2 million for any related series of violations.

Other Governmental Permits, Approvals and Authorizations

Construction and operation of the Sabine Pass LNG terminal and the CCL Project require additional permits, orders, approvals and consultations to be issued by various federal and state agencies, including the DOT, U.S. Army Corps of Engineers (“USACE”), U.S. Department of Commerce, National Marine Fisheries Services, U.S. Department of the Interior, U.S. Fish and Wildlife Service, the U.S. Environmental Protection Agency (the “EPA”), U.S. Department of Homeland Security, the LDEQ, the Texas Commission on Environmental Quality (“TCEQ”) and the Railroad Commission of Texas (“RRC”).

The USACE issues its permits under the authority of the Clean Water Act (Section 404) and the Rivers and Harbors Act (Section 10) (the “Section 10/404 Permit”). The EPA administers the Clean Air Act, and has delegated authority to the TCEQ and LDEQ to issue the Title V Operating Permit (the “Title V Permit”) and the Prevention of Significant Deterioration Permit (the “PSD Permit”). These two permits are issued by the LDEQ for the Sabine Pass LNG terminal and CTPL and by the TCEQ for the CCL Project.

Commodity Futures Trading Commission (“CFTC”)

The Dodd-Frank Wall Street Reform and Consumer Protection Act (the “Dodd-Frank Act”) amended the Commodity Exchange Act to provide for federal regulation of the over-the-counter derivatives market and entities, such as us, that participate in that market. The regulatory regime created by the Dodd-Frank Act is designed primarily to (1) regulate certain participants in the swaps markets, including entities falling within the categories of “Swap Dealer” and “Major Swap Participant,” (2) require clearing and exchange trading of standardized swaps of certain classes as designated by the CFTC, (3) increase swap market transparency through robust reporting and recordkeeping requirements, (4) reduce financial risks in the derivatives market by imposing margin or collateral requirements on both cleared and, in certain cases, uncleared swaps, (5) provide the CFTC with expanded authority to establish position limits on certain physical commodity futures and options contracts and their economically equivalent swaps as it finds necessary and appropriate and (6) otherwise enhance the rulemaking and enforcement authority of the CFTC and the SEC regarding the derivatives markets. Most of the regulations are already in effect, while other rules and regulations, including the proposed margin rules, position limits and commodity clearing requirements, remain to be finalized or effectuated. Therefore, the impact of those rules and regulations on our business continues to be uncertain.

A provision of the Dodd-Frank Act requires the CFTC, in order to diminish or prevent excessive speculation in commodity markets, to adopt rules, as it finds necessary and appropriate, imposing new position limits on certain physical commodity futures contracts and options thereon, as well as economically equivalent swaps traded on registered swap trading platforms and on over-the-counter swaps that perform a significant price discovery function with respect to certain markets. In that regard, the CFTC has re-proposed position limits rules that would modify and expand the applicability of limits on speculative positions in certain physical commodity futures contracts and economically equivalent futures, options and swaps for or linked to certain physical commodities, including Henry Hub natural gas, that market participants may hold, subject to limited exemptions for certain bona fide hedging and other types of transactions. It is uncertain at this time whether, when and in what form the CFTC’s proposed new position limits rules may become final and effective.

Pursuant to rules adopted by the CFTC, certain interest rate swaps and index credit default swaps must be cleared through a derivatives clearing organization and executed on an exchange or swap execution facility. The CFTC has not yet proposed to designate swaps in any other asset classes, including swaps relating to physical commodities, for mandatory clearing and trade execution, but could do so in the future. Although we expect to qualify for the end-user exception from the mandatory clearing and exchange-trading requirements applicable to any swaps that we enter into to hedge our commercial risks, the mandatory clearing and exchange-trading requirements may apply to other market participants, including our counterparties (who may be registered as Swap Dealers), with respect to other swaps, and the application of such rules may change the market cost and general availability in the market of swaps of the type we enter into to hedge our commercial risks and, thus, the cost and availability of the swaps that we use for hedging.

14




As required by provisions of the Dodd-Frank Act, the CFTC and federal banking regulators have adopted rules to require Swap Dealers and Major Swap Participants, including those that are regulated financial institutions, to collect initial and/or variation margin with respect to uncleared swaps from their counterparties that are financial end users, registered swap dealers or major swap participants. These rules do not require collection of margin from non-financial-entity end users who qualify for the end user exception from the mandatory clearing requirement or from non-financial end users or certain other counterparties in certain instances. We expect to qualify as such a non-financial-entity end user with respect to the swaps that we enter into to hedge our commercial risks.

Any new rules or changes to existing rules promulgated under the Dodd-Frank Act could (1) impair the availability of derivatives, (2) materially increase the cost of, or decrease the liquidity of, the derivatives we use to hedge, (3) significantly alter the terms and conditions of derivatives and (4) potentially increase our exposure to less creditworthy counterparties. Further, any resulting reduction in the use of derivatives could make cash flow more volatile and less predictable, which in turn could adversely affect our ability to plan for and fund capital expenditures.

Pursuant to the Dodd-Frank Act, the CFTC has adopted additional anti-manipulation and anti-disruptive trading practices regulations that prohibit, among other things, manipulative, deceptive or fraudulent schemes or material misrepresentation in the futures, options, swaps and cash markets. In addition, separate from the Dodd-Frank Act, our use of futures and options on commodities is subject to the Commodity Exchange Act and CFTC regulations, as well as the rules of futures exchanges on which any of these instruments are executed. Should we violate any of these laws and regulations, we could be subject to a CFTC or an exchange enforcement action and material penalties, possibly resulting in changes in the rates we can charge.

United Kingdom /European Regulations

Our European Union (“EU”) trading activities, which are primarily established in the United Kingdom (“UK”), are subject to a number of EU-wide and UK specific laws and regulations. These are described further below:

European Market Infrastructure Regulation (“EMIR”)

EMIR is an EU regulation (with text that is relevant across the European Economic Area (“EEA”)) designed to increase the transparency and stability of the EEA derivatives markets, including by: (1) imposing requirements on market participants trading derivatives, including relating to reporting, clearing and risk mitigation; and (2) imposing rules and standards that apply to central counterparties (i.e. clearing houses) and trade repositories. The precise impact of these rules will depend on a number of factors, including the regulatory status of the counterparty that is trading derivative instruments, as well as the volume and types of instruments it is trading. We currently are categorized under EMIR as a non-financial counterparty below the clearing threshold, which is a type of market participant subject to a lower regulatory burden. However, were we to engage in activities that resulted in a change to our status, we could be subject to more onerous regulations (including clearing and margining) which could significantly increase the cost of our derivatives trading activity, and materially alter the terms of the derivatives contracts we enter into.

Regulation on Wholesale Energy Market Integrity and Transparency (“REMIT”)

REMIT is an EU regulation (with EEA relevance) that prohibits market manipulation and insider trading in European wholesale energy markets and imposes various obligations on participants in these markets. Market participants, such as us, cannot use inside information (i.e., non-public information that would likely have a significant effect on the price of wholesale energy products if it were made public) to (1) buy or sell wholesale energy products for their own account or on behalf of a third party, directly or indirectly; (2) induce others to buy or sell wholesale energy products based on inside information; or (3) disclose such inside information to any other person except in the normal course of employment. A market participant is also prohibited from manipulating or attempting to manipulate any wholesale energy market, and is required to publicly disclose inside information which it possesses in respect of business or facilities which it or its affiliates either owns or controls, or for whose operational matters it or they are responsible, either in whole or in part.

Markets in Financial Instruments Directive and Regulation (“MiFID II”)

MiFID II consists of an EU directive, a regulation and a number of delegated acts, rules and guidance, that replaced the original 2004 Markets in Financial Instruments Directive (“MiFID”). MiFID II (with relevance throughout the EEA), sets forth

15




an EEA-wide financial services framework, including rules for firms engaging in investment services and activities in connection with certain financial instruments in the EEA. Firms engaging in such activities must be authorized unless an exemption applies.

We are eligible to trade on our own account in commodity derivatives as a result of the “ancillary activity” exemption under MiFID II. To avail ourselves of this exemption, amongst other things, we must be able to demonstrate, on the basis of a methodology set out in certain delegated MiFID II text, that our activities in commodity derivatives are ancillary to the main business of our group. Provided we meet the requirements, we must notify the UK regulator that we are availing ourselves of this exemption on an annual basis. If, in the future, we are no longer able to meet the requirements of the “ancillary activity” exemption, and no other exemption is available to us, we would be required to become authorized as an investment firm under MiFID II. This may result in us being subject to the regulatory capital requirements under the EU’s Capital Requirements Directive IV.

Market Abuse Regulation (“MAR”)

MAR is intended to update and strengthen the existing EU market abuse framework and applies to all financial instruments listed or traded on EU trading venues as well as other over-the-counter (“OTC”) financial instruments priced on, or impacting, the trading venue contract. Generally, MAR applies to entities trading on, or in a manner that impacts EU markets. MAR contains a number of “insider dealing” and “market manipulation” (including “attempted manipulation”) based offences. Under MAR, any person professionally arranging or executing transactions in financial instruments is required to establish and maintain effective arrangements, systems and procedures to detect and report suspicious orders and transactions.

UK-Specific Rules

In addition to the various EU/EEA rules described above, other UK-specific laws, such as the UK’s Financial Services and Markets Act of 200 (“FSMA”) and Financial Services and Markets Act 2000 (Regulated Activities) Order 2001 (“RAO”), also apply to our trading activities.

Any violation of the foregoing laws and regulations could result in investigations, and possible fine and penalties, and in some scenarios, criminal offenses.

Brexit

The UK withdrew from the EU (“Brexit”) on January 31, 2020, and the withdrawal may have an impact on the applicability of the current EU Regulations and Directives that govern our various trading activities. The precise impacts will depend on the negotiations that will occur during the transition period, which is currently scheduled to end on December 31, 2020, as well as other factors that may or may not be addressed during the negotiations.  We anticipate that impacts could include a possible requirement to register in the EU for certain activities, the possible reclassification of products traded on UK exchanges for EU purposes and products traded on EU exchanges for UK purposes and possible impacts on our treatment related to various regulatory statuses (e.g., clearing threshold classifications and other safe harbors and exemptions).  During this transition period, the UK will continue to be subject to EU Regulations and Rules, with the objective being to provide as smooth a transition as possible for businesses.  Until additional clarity surrounding Brexit is obtained, other impacts pertaining to our trading activities could occur.

Environmental Regulation
  
Our LNG terminals are subject to various federal, state and local laws and regulations relating to the protection of the environment and natural resources. These environmental laws and regulations require significant expenditures for compliance, can affect the cost and output of operations and may impose substantial penalties for non-compliance and substantial liabilities for pollution. Many of these laws and regulations, such as those noted below, restrict or prohibit impacts to the environment or the types, quantities and concentration of substances that can be released into the environment and can lead to substantial administrative, civil and criminal fines and penalties for non-compliance.
 
Clean Air Act (“CAA”)
 
Our LNG terminals are subject to the federal CAA and comparable state and local laws. We may be required to incur certain capital expenditures over the next several years for air pollution control equipment in connection with maintaining or obtaining permits and approvals addressing air emission-related issues. We do not believe, however, that our operations, or the construction and operations of our liquefaction facilities, will be materially and adversely affected by any such requirements.

16




In 2009, the EPA promulgated and finalized the Mandatory Greenhouse Gas Reporting Rule requiring annual reporting of greenhouse gas (“GHG”) emissions from stationary sources in a variety of industries. In 2010, the EPA expanded the rule to include reporting obligations for LNG terminals. In addition, the EPA has defined GHG emissions thresholds that would subject GHG emissions from new and modified industrial sources to regulation if the source is subject to PSD Permit requirements due to its emissions of non-GHG criteria pollutants. While the EPA subsequently took a number of additional actions primarily relating to GHG emissions from the electric power generation and the oil and gas exploration and production industries, those rules have largely been stayed or repealed including by amendments adopted by the EPA on February 23, 2018, additional proposed amendments to new source performance standards for the oil and gas industry on September 24, 2019, and the EPA’s June 19, 2019 adoption of the Affordable Clean Energy rule for power generation.

From time to time, Congress has considered proposed legislation directed at reducing GHG emissions. In addition, many states have already taken regulatory action to monitor and/or reduce emissions of GHGs, primarily through the development of GHG emission inventories or regional GHG cap and trade programs. It is not possible at this time to predict how future regulations or legislation may address GHG emissions and impact our business. However, future regulations and laws could result in increased compliance costs or additional operating restrictions and could have a material adverse effect on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.

Coastal Zone Management Act (“CZMA”)
 
The siting and construction of our LNG terminals within the coastal zone is subject to the requirements of the CZMA. The CZMA is administered by the states (in Louisiana, by the Department of Natural Resources, and in Texas, by the General Land Office). This program is implemented to ensure that impacts to coastal areas are consistent with the intent of the CZMA to manage the coastal areas.

Clean Water Act (“CWA”)
 
Our LNG terminals are subject to the federal CWA and analogous state and local laws. The CWA imposes strict controls on the discharge of pollutants into the navigable waters of the United States, including discharges of wastewater and storm water runoff and fill/discharges into waters of the United States. Permits must be obtained prior to discharging pollutants into state and federal waters. The CWA is administered by the EPA, the USACE and by the states (in Louisiana, by the LDEQ, and in Texas, by the TCEQ).

Resource Conservation and Recovery Act (“RCRA”)
 
The federal RCRA and comparable state statutes govern the generation, handling and disposal of solid and hazardous wastes and require corrective action for releases into the environment. When such wastes are generated in connection with the operations of our facilities, we are subject to regulatory requirements affecting the handling, transportation, treatment, storage and disposal of such wastes.
 
Protection of Species, Habitats and Wetlands

Various federal and state statutes, such as the Endangered Species Act (the “ESA”), the Migratory Bird Treaty Act (“MBTA”), the CWA and the Oil Pollution Act, prohibit certain activities that may adversely affect endangered or threatened animal, fish and plant species and/or their designated habitats, wetlands, or other natural resources. If one of our LNG terminals or pipelines adversely affects a protected species or its habitat, we may be required to develop and follow a plan to avoid those impacts. In that case, siting, construction or operation may be delayed or restricted and cause us to incur increased costs.
In August 2019, the U.S. Fish and Wildlife Service (the “FWS”) announced a series of changes to the rules implementing the ESA, including revisions to the regulations governing interagency cooperation, listing species and delisting critical habitat, and prohibitions related to threatened wildlife and plants. The revisions are intended to streamline these processes and create more flexibility for the FWS when making ESA-related decisions.

In addition, in December 2017, the Department of Interior’s (“DOI’s”) Solicitor’s Office issued an official opinion that the MBTA’s broad prohibition on “taking” migratory birds applies only to affirmative actions and does prohibit incidental harm. In April 2018, the FWS issued guidance consistent with the DOI’s opinion and on January 30, 2020, the FWS issued a proposed rule defining the scope of the MBTA to cover only actions directed at migratory birds, their nests or their eggs.

17




We do not believe that our operations, or the construction and operations of our liquefaction facilities, will be materially and adversely affected by these recent regulatory actions.

Market Factors

Our ability to enter into additional long-term SPAs to underpin the development of additional Trains, sale of LNG by Cheniere Marketing, or development of new projects is subject to market factors. These factors include changes in worldwide supply and demand for natural gas, LNG and substitute products, the relative prices for natural gas, crude oil and substitute products in North America and international markets, the rate of fuel switching for power generation from coal, nuclear or oil to natural gas and economic growth in developing countries. In addition, our ability to obtain additional funding to execute our business strategy is subject to the investment community’s appetite for investment in LNG and natural gas infrastructure and our ability to access capital markets.

We expect that global demand for natural gas and LNG will continue to increase as nations seek more abundant, reliable and environmentally cleaner fuel alternatives to oil and coal.  Global demand for natural gas is projected by the International Energy Agency to grow by approximately 27 trillion cubic feet (“Tcf”) between 2018 and 2030 and 39 Tcf between 2018 and 2035. LNG’s share is seen growing from about 11% in 2018 to about 16% of the global gas market in 2030 and 18% in 2035.  Wood Mackenzie Limited (“WoodMac”) forecasts that global demand for LNG will increase by approximately 79%, from approximately 316 mtpa, or 15.2 Tcf, in 2018, to approximately 566 mtpa, or 27.2 Tcf, in 2030 and to 678 mtpa or 32.6 Tcf in 2035. WoodMac also forecasts LNG production from existing operational facilities and new facilities already under construction will be able to supply the market with approximately 469 mtpa in 2030, declining to 430 mtpa in 2035. This will result in a market need for construction of an additional approximately 97 mtpa of LNG production by 2030 and about 248 mtpa by 2035.  We believe the capital and operating costs of the uncommitted capacity of our Liquefaction Projects and Corpus Christi Stage 3 are competitive with new proposed projects globally and we are well-positioned to capture a portion of this incremental market need.
We have limited exposure to the decline in oil prices as we have contracted a significant portion of our LNG production capacity under long-term sale and purchase agreements. These agreements contain fixed fees that are required to be paid even if the customers elect to cancel or suspend delivery of LNG cargoes.  We have contracted approximately 85% of the total production capacity from the Liquefaction Projects on a term basis, which includes volumes contracted under SPAs in which the customers are required to pay a fixed fee with respect to the contracted volumes irrespective of their election to cancel or suspend deliveries of LNG cargoes, as well as volumes contracted under IPM gas supply agreements. As of January 31, 2020, U.S. natural gas prices indicate that LNG exported from the U.S. continues to be competitively priced, supporting the opportunity for U.S. LNG to fill uncontracted future demand through the execution of long-term and medium-term contracting of LNG from our terminals.

Subsidiaries
 
Our assets are generally held by our subsidiaries. We conduct most of our business through these subsidiaries, including the development, construction and operation of our LNG terminal business and the development and operation of our LNG and natural gas marketing business.

Employees
 
We had 1,530 full-time employees at January 31, 2020.  

Available Information

Our common stock has been publicly traded since March 24, 2003 and is traded on the NYSE American under the symbol “LNG.” Our principal executive offices are located at 700 Milam Street, Suite 1900, Houston, Texas 77002, and our telephone number is (713) 375-5000. Our internet address is www.cheniere.com. We provide public access to our annual reports on Form 10-K, quarterly reports on Form 10-Q, current reports on Form 8-K and amendments to these reports as soon as reasonably practicable after we electronically file those materials with, or furnish those materials to, the SEC under the Exchange Act. These reports may be accessed free of charge through our internet website. We make our website content available for informational purposes only. The website should not be relied upon for investment purposes and is not incorporated by reference into this Form 10-K.


18




We will also make available to any stockholder, without charge, copies of our annual report on Form 10-K as filed with the SEC. For copies of this, or any other filing, please contact: Cheniere Energy, Inc., Investor Relations Department, 700 Milam Street Suite 1900, Houston, Texas 77002 or call (713) 375-5000. The SEC maintains an internet site (www.sec.gov) that contains reports, proxy and information statements and other information regarding issuers.

ITEM 1A.
RISK FACTORS
 
The following are some of the important factors that could affect our financial performance or could cause actual results to differ materially from estimates or expectations contained in our forward-looking statements. We may encounter risks in addition to those described below. Additional risks and uncertainties not currently known to us, or that we currently deem to be immaterial, may also impair or adversely affect our business, contracts, financial condition, operating results, cash flows, liquidity and prospects.
The risk factors in this report are grouped into the following categories:
Risks Relating to Our Financial Matters; 
Risks Relating to Our LNG Terminal Operations and Commercialization; 
Risks Relating to Our LNG Business in General; and 
Risks Relating to Our Business in General.

Risks Relating to Our Financial Matters
 
Our existing level of cash resources and significant debt could cause us to have inadequate liquidity and could materially and adversely affect our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.
 
As of December 31, 2019, we had $2.5 billion of cash and cash equivalents, $520 million of current restricted cash and $31.5 billion of total debt outstanding on a consolidated basis (before unamortized premium, discount and debt issuance costs), excluding $1.5 billion aggregate outstanding letters of credit. We incur, and will incur, significant interest expense relating to the assets at the Sabine Pass and Corpus Christi LNG terminals, and we anticipate needing to incur additional debt to finance the construction of Corpus Christi Stage 3. Our ability to fund our capital expenditures and refinance our indebtedness will depend on our ability to access additional project financing as well as the debt and equity capital markets. A variety of factors beyond our control could impact the availability or cost of capital, including domestic or international economic conditions, increases in key benchmark interest rates and/or credit spreads, the adoption of new or amended banking or capital market laws or regulations and the repricing of market risks and volatility in capital and financial markets. Our financing costs could increase or future borrowings or equity offerings may be unavailable to us or unsuccessful, which could cause us to be unable to pay or refinance our indebtedness or to fund our other liquidity needs. We also rely on borrowings under our credit facilities to fund our capital expenditures. If any of the lenders in the syndicates backing these facilities was unable to perform on its commitments, we may need to seek replacement financing, which may not be available as needed, or may be available in more limited amounts or on more expensive or otherwise unfavorable terms.

We have not always been profitable historically. We may not achieve profitability or generate positive operating cash flow in the future.
 
We had net loss attributable to common stockholders of $393 million for the year ended December 31, 2017 and had losses in prior years. In the future, we may incur operating losses and experience negative operating cash flow. We may not be able to reduce costs, increase revenues or reduce our debt service obligations sufficiently to maintain our cash resources, which could cause us to have inadequate liquidity to continue our business.

We will continue to incur significant capital and operating expenditures while we develop and construct the Liquefaction Projects, Corpus Christi Stage 3 and other projects. Any delays beyond the expected development period for these projects could cause operating losses and negative operating cash flows. Our future liquidity may also be affected by the timing of construction financing availability in relation to the incurrence of construction costs and other outflows and by the timing of receipt of cash flows under third-party agreements in relation to the incurrence of project and operating expenses. Moreover, many factors (including factors beyond our control) could result in a disparity between liquidity sources and cash needs, including factors such as construction delays and breaches of agreements. Our ability to generate any significant positive operating cash flow and achieve profitability in the future is dependent on our ability to successfully and timely complete and operate the applicable project.


19




We may sell equity or equity-related securities or assets, including equity interests in Cheniere Partners. Such sales could dilute our stockholders’ proportionate indirect interests in our assets, business operations and proposed liquefaction and other projects of Cheniere Partners or other subsidiaries, and could adversely affect the market price of our common stock.
 
We have historically pursued a number of alternatives in order to finance the construction of our Trains, including potential issuances and sales of additional equity or equity-related securities by us or Cheniere Partners. Such sales, in one or more transactions, could dilute our stockholders’ proportionate indirect interests in our assets, business operations and proposed projects of Cheniere Partners, including the SPL Project, or in other subsidiaries or projects, including the CCL Project. In addition, such sales, or the anticipation of such sales, could adversely affect the market price of our common stock.

Our stockholders may experience dilution upon the conversion of our convertible notes.

In November 2014, we issued an aggregate principal amount of $1.0 billion Convertible Unsecured Notes due 2021 (the “2021 Cheniere Convertible Unsecured Notes”) to RRJ Capital II Ltd, Baytree Investments (Mauritius) Pte Ltd and Seatown Lionfish Pte. Ltd. In March 2015, we issued $625 million aggregate principal amount of 4.25% Convertible Senior Notes due 2045 (the “2045 Cheniere Convertible Senior Notes”) to certain investors through a registered direct offering. In May 2015, CCH HoldCo II issued $1.0 billion aggregate principal amount of 11.0% Convertible Senior Secured Notes due 2025 (the “2025 CCH HoldCo II Convertible Senior Notes” and together with the 2021 Cheniere Convertible Unsecured Notes and the 2045 Cheniere Convertible Senior Notes, the “Convertible Notes”) to EIG Management Company, LLC.  
We have the option to satisfy the 2021 Cheniere Convertible Unsecured Notes and the 2045 Cheniere Convertible Senior Notes conversion obligations with cash, common stock or a combination thereof. The 2025 CCH HoldCo II Convertible Senior Notes conversion obligations must be satisfied with common stock. The 2021 Cheniere Convertible Unsecured Notes are convertible at an initial conversion price of $93.64. Prior to December 15, 2044, the 2045 Cheniere Convertible Senior Notes will be convertible upon the occurrence of certain conditions, and on and after such date they will become freely convertible. The 2045 Cheniere Convertible Senior Notes will become convertible into the common stock of Cheniere at an initial conversion price of $138.38 per share. Provided the total market capitalization of Cheniere at that time is not less than $10.0 billion and certain other conditions are satisfied, the 2025 CCH HoldCo II Convertible Senior Notes will be convertible at CCH HoldCo II’s option on or after March 1, 2020 (the “Eligible Conversion Date”). The conversion price for 2025 CCH HoldCo II Convertible Senior Notes converted at CCH HoldCo II’s option is the lower of (1) a 10% discount to the average of the daily volume-weighted average price (“VWAP”) of our common stock for the 90 trading day period prior to the date on which notice of conversion is provided and (2) a 10% discount to the closing price of our common stock on the trading day preceding the date on which notice of conversion is provided. At the option of the holders, the 2025 CCH HoldCo II Convertible Senior Notes are convertible on or after the six-month anniversary of the Eligible Conversion Date, provided the total market capitalization of Cheniere at that time is not less than $10.0 billion and certain other conditions are satisfied, at a conversion price equal to the average of the daily VWAP of our common stock for the 90 trading day period prior to the date on which notice of conversion is provided.

The conversion of some or all of the Convertible Notes into shares of our common stock will dilute the ownership percentages and voting power of our existing stockholders.  Based on the initial conversion price, if we elect to satisfy the entire conversion obligations of the 2021 Cheniere Convertible Unsecured Notes and the 2045 Cheniere Convertible Senior Notes with common stock, an aggregate of approximately 19.1 million shares of our common stock would be issued upon the conversion, assuming the notes are converted at maturity and all interest on the notes is paid in kind for the 2021 Cheniere Convertible Unsecured Notes. Because the conversion rate for the 2025 CCH HoldCo II Convertible Senior Notes will depend on the price of our common stock at the time of conversion, we cannot meaningfully estimate the number of shares of our common stock, if any, that would be issued upon the conversion of such notes; however, under these convertible notes, a maximum of 47,108,466 shares of our common stock (subject to adjustment in the event of a stock split) may be issued in the aggregate upon the conversion of all of the 2025 CCH HoldCo II Convertible Senior Notes.  Any sales in the public market of the shares issuable upon conversion of the Convertible Notes could adversely affect the prevailing market prices of our common stock.  In addition, the existence of the Convertible Notes may encourage short selling by market participants because the conversion of the Convertible Notes could be used to satisfy short positions, or the anticipated conversion of the Convertible Notes into shares of our common stock could depress the price of our common stock.


20




Our ability to generate cash is substantially dependent upon the performance by customers under long-term contracts that we have entered into, and we could be materially and adversely affected if any customer fails to perform its contractual obligations for any reason.

Our future results and liquidity are substantially dependent upon performance by our customers to make payments under long-term contracts. As of December 31, 2019, SPL had SPAs with eight third-party customers, CCL had SPAs with nine third-party customers and our integrated marketing function had a limited number of SPAs with third-party customers. In addition, SPLNG had TUAs with two third-party customers. We are dependent on each customer’s continued willingness and ability to perform its obligations under its SPA or TUA. We are exposed to the credit risk of any guarantor of these customers’ obligations under their respective agreements in the event that we must seek recourse under a guaranty. If any customer fails to perform its obligations under its SPA or TUA, our business, contracts, financial condition, operating results, cash flow, liquidity and prospects could be materially and adversely affected, even if we were ultimately successful in seeking damages from that customer or its guarantor for a breach of the agreement.

Each of our customer contracts is subject to termination under certain circumstances.
  
Each of the SPAs contains various termination rights allowing our customers to terminate their SPAs, including, without limitation: (1) upon the occurrence of certain events of force majeure; (2) if we fail to make available specified scheduled cargo quantities; and (3) delays in the commencement of commercial operations. We may not be able to replace these SPAs on desirable terms, or at all, if they are terminated.

Each of SPLNG’s long-term TUAs contains various termination rights. For example, each customer may terminate its TUA if the Sabine Pass LNG terminal experiences a force majeure delay for longer than 18 months, fails to redeliver a specified amount of natural gas in accordance with the customer’s redelivery nominations or fails to accept and unload a specified number of the customer’s proposed LNG cargoes. SPLNG may not be able to replace these TUAs on desirable terms, or at all, if they are terminated.

Our subsidiaries may be restricted under the terms of their indebtedness from making distributions under certain circumstances, which may limit Cheniere Partners’ ability to pay or increase distributions to us or inhibit our access to cash flows from the CCL Project and could materially and adversely affect us.
 
The agreements governing our subsidiaries’ indebtedness restrict payments that our subsidiaries can make to Cheniere Partners or us in certain events and limit the indebtedness that our subsidiaries can incur. For example, SPL is restricted from making distributions under agreements governing its indebtedness generally until, among other requirements, deposits are made into debt service reserve accounts and a debt service coverage ratio of 1.25:1.00 is satisfied.

CCH is generally restricted from making distributions under agreements governing its indebtedness until, among other requirements, the completion of the construction of Trains 1 through 3 of the CCL Project, funding of a debt service reserve account equal to six months of debt service and achieving a historical debt service coverage ratio and fixed projected debt service coverage ratio of at least 1.25:1.00.

CCH HoldCo II is restricted from making distributions to Cheniere under agreements governing its indebtedness generally until, among other requirements, a historical debt service coverage ratio and a projected fixed debt services coverage ratio of 1.20:1.00 are achieved.

Our subsidiaries’ inability to pay distributions to Cheniere Partners or us or to incur additional indebtedness as a result of the foregoing restrictions in the agreements governing their indebtedness may inhibit Cheniere Partners’ ability to pay or increase distributions to us and its other unitholders or inhibit our access to cash flows from the CCL Project, which could have a material adverse effect on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.


21




Restrictions in agreements governing us and our subsidiaries’ indebtedness may prevent us and our subsidiaries from engaging in certain beneficial transactions.
 
In addition to restrictions on the ability of us, Cheniere Partners, SPL, CCH and CCH HoldCo II to make distributions or incur additional indebtedness, the agreements governing our indebtedness also contain various other covenants that may prevent us from engaging in beneficial transactions, including limitations on our ability to:
make certain investments;
purchase, redeem or retire equity interests;
issue preferred stock;
sell or transfer assets;
incur liens;
enter into transactions with affiliates;
consolidate, merge, sell or lease all or substantially all of our assets; and
enter into sale and leaseback transactions.
Our use of hedging arrangements may adversely affect our future operating results or liquidity.

To reduce our exposure to fluctuations in the price, volume and timing risk associated with the purchase of natural gas, we use futures, swaps and option contracts traded or cleared on the Intercontinental Exchange and the New York Mercantile Exchange or over-the-counter options and swaps with other natural gas merchants and financial institutions. Hedging arrangements could expose us to risk of financial loss in some circumstances, including when:
expected supply is less than the amount hedged;
the counterparty to the hedging contract defaults on its contractual obligations; or
there is a change in the expected differential between the underlying price in the hedging agreement and actual prices received.
The use of derivatives also may require the posting of cash collateral with counterparties, which can impact working capital when commodity prices change.
The regulatory and other provisions of the Dodd-Frank Act and the rules adopted thereunder and other regulations, including EMIR and REMIT, could adversely affect our ability to hedge risks associated with our business and our operating results and cash flows.

The provisions of the Dodd-Frank Act and the rules adopted and to be adopted by the CFTC, the SEC and other federal regulators establishing federal regulation of the OTC derivatives market and entities like us that participate in that market may adversely affect our ability to manage certain of our risks on a cost effective basis. Such laws and regulations may also adversely affect our ability to execute our strategies with respect to hedging our exposure to variability in expected future cash flows attributable to the future sale of our LNG inventory and to price risk attributable to future purchases of natural gas to be utilized as fuel to operate our LNG terminals and to secure natural gas feedstock for our liquefaction facilities.

The CFTC has re-proposed position limits rules that would modify and expand the applicability of position limits on the amounts of certain speculative futures contracts, as well as economically equivalent options, futures and swaps for or linked to certain physical commodities, including Henry Hub natural gas, that market participants may hold, subject to limited exemptions for certain bona fide hedging positions and other types of transactions. To the extent the revised CFTC position limits proposal becomes final, our ability to execute our hedging strategies described above could be limited. It is uncertain at this time whether, when and in what form the CFTC’s proposed new position limits rules may become final and effective.

Under the Dodd-Frank Act and the rules adopted thereunder, certain swaps may be required to be cleared through a derivatives clearing organization. While the CFTC has designated certain interest rate swaps and index credit default swaps for mandatory clearing, it has not yet finalized rules designating any physical commodity swaps, for mandatory clearing or mandatory exchange trading. Further, we qualify for the end-user exception from the mandatory clearing and trade execution requirements for our

22




swaps entered into to hedge our commercial risks. If we fail to qualify for that exception as to any swap we enter into and have to clear that swap through a derivatives clearing organization, we could be required to post margin (or post higher margin than if we entered into an uncleared OTC swap) with respect to such swap, our cost of entering into and maintaining such swap could increase and we would not enjoy the same flexibility with the cleared swaps that we enjoy with the uncleared OTC swaps we enter into. Moreover, the application of the mandatory clearing and trade execution requirements to other market participants, such as swap dealers, may change the market cost and general availability in the market of swaps of the type we enter into to hedge our commercial risks and, thus, the cost and availability of the swaps that we use for hedging.

As required by the Dodd-Frank Act, the CFTC and federal banking regulators have adopted rules to require certain market participants to collect and post initial and/or variation margin with respect to uncleared swaps from their counterparties that are financial end users and certain registered swap dealers and major swap participants. Although we believe we will not be required to post margin with respect to any uncleared swaps we enter into in the future, were we required to post margin as to our uncleared swaps in the future, our cost of entering into and maintaining swaps would be increased. Our counterparties that are subject to the regulations imposing the Basel III capital requirements on them may increase the cost to us of entering into swaps with them or, although not required to collect margin from us under the margin rules, contractually require us to post collateral with them in connection with such swaps in order to offset their increased capital costs or to reduce their capital costs to maintain those swaps on their balance sheets.

The Dodd-Frank Act also imposes other regulatory requirements on swaps market participants, including end users of swaps, such as regulations relating to swap documentation, reporting and recordkeeping, and certain business conduct rules applicable to swap dealers and major swap participants. Together with the Basel III capital requirements on certain swaps market participants, the regulatory requirements of the Dodd-Frank Act and the rules thereunder relating to swaps and derivatives market participants could significantly increase the cost of derivative contracts (including through requirements to post margin or collateral), materially alter the terms of derivative contracts, reduce the availability of derivatives to protect against certain risks that we encounter and reduce our ability to monetize or restructure our existing derivative contracts and to execute our hedging strategies. If, as a result of the swaps regulatory regime discussed above, we were to reduce our use of swaps to hedge our risks, such as commodity price risks that we encounter in our operations, our operating results and cash flows may become more volatile and could be otherwise adversely affected.

The Federal Reserve Board also has proposed rules that would limit certain physical commodity activities of financial holding companies. Such rules, if adopted, may adversely affect our ability to execute our strategies by restricting our available counterparties for certain types of transactions, limiting our ability to obtain certain services, and reducing liquidity in physical and financial markets. It is uncertain at this time whether, when and in what form the Federal Reserve’s proposed rules regarding financial holding companies may become final and effective.
European and UK-specific regulations, including but not limited to EMIR, MiFID II, REMIT, MAR, FSMA and RAO, govern our trading activities and our compliance with such laws may result in increased costs and risks to the business similar to the impacts stated above with respect to the Dodd-Frank Act. The increased costs may also have an adverse impact on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects. Further, any violation of the foregoing laws and regulations could result in investigations, and possible fines and penalties, and in some scenarios, criminal offenses.

Further, given the current lack of clarity relating to how UK and EU financial and commodity market regulatory regimes will interact following the UK’s withdrawal from the EU on January 31, 2020, including the impact such withdrawal will have on parties subject to the referenced regulations, additional regulatory risks may result.  However, until negotiations between the UK and EU are completed during the transition period, which is currently scheduled to expire on December 31, 2020, it is impossible at this point to address with certainty the impact of Brexit on our operations.

We expect that our hedging activities will remain subject to significant and developing regulations and regulatory oversight. However, the full impact of the various U.S. (and non-U.S.) regulatory developments in connection with these activities will not be known with certainty until such derivatives market regulations are fully implemented and related market practices and structures are fully developed.


23




Risks Relating to Our LNG Terminal Operations and Commercialization
 
Operation of the Sabine Pass LNG terminal, the Liquefaction Projects, our pipelines and other facilities that we may construct involves significant risks.
 
As more fully discussed in these Risk Factors, the Sabine Pass LNG terminal, the Liquefaction Projects, our pipelines and our other existing and proposed LNG facilities face operational risks, including the following:
the facilities’ performing below expected levels of efficiency;
breakdown or failures of equipment;
operational errors by vessel or tug operators;
operational errors by us or any contracted facility operator;
labor disputes; and
weather-related interruptions of operations.

Cost overruns and delays in the completion of one or more Trains, as well as difficulties in obtaining sufficient financing to pay for such costs and delays, could have a material adverse effect on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.
 
The actual construction costs of the Trains may be significantly higher than our current estimates as a result of many factors, including change orders under existing or future EPC contracts resulting from the occurrence of certain specified events that may give Bechtel the right to cause us to enter into change orders or resulting from changes with which we otherwise agree. We have already experienced increased costs due to change orders. As construction progresses, we may decide or be forced to submit change orders to our contractor that could result in longer construction periods, higher construction costs or both, including change orders to comply with existing or future environmental or other regulations.

Delays in the construction of one or more Trains beyond the estimated development periods, as well as change orders to the EPC contracts with Bechtel or any future EPC contract related to additional Trains, could increase the cost of completion beyond the amounts that we estimate, which could require us to obtain additional sources of financing to fund our operations until the applicable liquefaction project is fully constructed (which could cause further delays). Our ability to obtain financing that may be needed to provide additional funding to cover increased costs will depend, in part, on factors beyond our control. Accordingly, we may not be able to obtain financing on terms that are acceptable to us, or at all. Even if we are able to obtain financing, we may have to accept terms that are disadvantageous to us or that may have a material adverse effect on our current or future business, contracts, financial condition, operating results, cash flow, liquidity and prospects.

Our ability to complete development of additional Trains will be contingent on our ability to obtain additional funding. If we are unable to obtain sufficient funding, we may be unable to fully execute our business strategy.
 
We will require significant additional funding to be able to commence construction of additional Trains, which we may not be able to obtain at a cost that results in positive economics, or at all. The inability to achieve acceptable funding may cause a delay in the development of additional Trains, and we may not be able to complete our business plan. Even if we are able to obtain funding, the funding may be inadequate to cover any increases in costs or delays in completion of additional Trains, which may cause a delay in the receipt of revenues projected therefrom or cause a loss of one or more future customers in the event of significant delays. As a result, any significant construction delay, whatever the cause, could have a material adverse effect on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.

Hurricanes or other disasters could result in an interruption of our operations, a delay in the completion of our liquefaction projects, damage to our liquefaction projects and increased insurance costs, all of which could adversely affect us.
 
Hurricanes Katrina and Rita in 2005, Hurricane Ike in 2008 and Hurricane Harvey in 2017 caused temporary suspension in construction of our liquefaction projects or caused minor damage to our liquefaction projects. Future storms and related storm activity and collateral effects, or other disasters such as explosions, fires, floods or accidents, could result in damage to, or interruption of operations at, the Sabine Pass LNG terminal, the Corpus Christi terminal or related infrastructure, as well as delays or cost increases in the construction and the development of the Liquefaction Projects, Corpus Christi Stage 3 or our other facilities

24




and increase our insurance premiums. The U.S. Global Change Research Program has reported that the U.S.’s energy and transportation systems are expected to be increasingly disrupted by climate change and extreme weather events. An increase in frequency and severity of extreme weather events such as storms, floods, fires and rising sea levels could have an adverse effect on our operations.
 
Failure to obtain and maintain approvals and permits from governmental and regulatory agencies with respect to the design, construction and operation of our facilities, the development and operation of our pipelines and the export of LNG could impede operations and construction and could have a material adverse effect on us.

The design, construction and operation of interstate natural gas pipelines, LNG terminals, including the Liquefaction Projects, Corpus Christi Stage 3 and other facilities, and the import and export of LNG and the purchase and transportation of natural gas, are highly regulated activities. Approvals of the FERC and DOE under Section 3 and Section 7 of the NGA, as well as several other material governmental and regulatory approvals and permits, including several under the CAA and the CWA, are required in order to construct and operate an LNG facility and an interstate natural gas pipeline and export LNG. Although the FERC has issued orders under Section 3 of the NGA authorizing the siting, construction and operation of the six Trains and related facilities of the SPL Project, the three Trains and related facilities of the CCL Project and the seven midscale Trains and related facilities for Corpus Christi Stage 3, as well as orders under Section 7 of the NGA authorizing the construction and operation of the Creole Trail Pipeline, the Corpus Christi Pipeline and the pipeline for Corpus Christi Stage 3, the FERC orders require us to comply with certain ongoing conditions and obtain certain additional approvals in conjunction with ongoing construction and operations of our liquefaction and pipeline facilities. We will be required to obtain similar approvals and permits with respect to any expansion or modification of our liquefaction and pipeline facilities. We cannot control the outcome of the regulatory review and approval processes. Certain of these governmental permits, approvals and authorizations are or may be subject to rehearing requests, appeals and other challenges.

Authorizations obtained from the FERC, DOE and other federal and state regulatory agencies also contain ongoing conditions, and additional approval and permit requirements may be imposed. We do not know whether or when any such approvals or permits can be obtained, or whether any existing or potential interventions or other actions by third parties will interfere with our ability to obtain and maintain such permits or approvals. If we are unable to obtain and maintain the necessary approvals and permits, including as a result of untimely notices or filings, we may not be able to recover our investment in our projects. Additionally, government disruptions, such as a U.S. government shutdown, may delay or halt our ability to obtain and maintain necessary approvals and permits. There is no assurance that we will obtain and maintain these governmental permits, approvals and authorizations, or that we will be able to obtain them on a timely basis, and failure to obtain and maintain any of these permits, approvals or authorizations could have a material adverse effect on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.

Delays in the completion of one or more Trains could lead to reduced revenues or termination of one or more of the SPAs by our customers.
 
Any delay in completion of a Train could cause a delay in the receipt of revenues projected therefrom or cause a loss of one or more customers in the event of significant delays. In particular, each of our SPAs provides that the customer may terminate that SPA if the relevant Train does not timely commence commercial operations. As a result, any significant construction delay, whatever the cause, could have a material adverse effect on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.

We are dependent on Bechtel and other contractors for the successful completion of the Liquefaction Projects.

Timely and cost-effective completion of the Liquefaction Projects in compliance with agreed specifications is central to our business strategy and is highly dependent on the performance of Bechtel and our other contractors under their agreements. The ability of Bechtel and our other contractors to perform successfully under their agreements is dependent on a number of factors, including their ability to:
design and engineer each Train to operate in accordance with specifications;
engage and retain third-party subcontractors and procure equipment and supplies;
respond to difficulties such as equipment failure, delivery delays, schedule changes and failure to perform by subcontractors, some of which are beyond their control;

25




attract, develop and retain skilled personnel, including engineers;
post required construction bonds and comply with the terms thereof;
manage the construction process generally, including coordinating with other contractors and regulatory agencies; and
maintain their own financial condition, including adequate working capital.
Although some agreements may provide for liquidated damages if the contractor fails to perform in the manner required with respect to certain of its obligations, the events that trigger a requirement to pay liquidated damages may delay or impair the operation of the Liquefaction Projects, and any liquidated damages that we receive may not be sufficient to cover the damages that we suffer as a result of any such delay or impairment. The obligations of Bechtel and our other contractors to pay liquidated damages under their agreements are subject to caps on liability, as set forth therein.

Furthermore, we may have disagreements with our contractors about different elements of the construction process, which could lead to the assertion of rights and remedies under their contracts and increase the cost of the Liquefaction Projects or result in a contractor’s unwillingness to perform further work on the Liquefaction Projects. If any contractor is unable or unwilling to perform according to the negotiated terms and timetable of its respective agreement for any reason or terminates its agreement, we would be required to engage a substitute contractor. This would likely result in significant project delays and increased costs, which could have a material adverse effect on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.

If third-party pipelines and other facilities interconnected to our pipelines and facilities are or become unavailable to transport natural gas, this could have a material adverse effect on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.
 
We depend upon third-party pipelines and other facilities that provide gas delivery options to our liquefaction facilities and pipelines. If the construction of new or modified pipeline connections is not completed on schedule or any pipeline connection were to become unavailable for current or future volumes of natural gas due to repairs, damage to the facility, lack of capacity or any other reason, our ability to meet our SPA obligations and continue shipping natural gas from producing regions or to end markets could be restricted, thereby reducing our revenues which could have a material adverse effect on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.

We may not be able to purchase or receive physical delivery of sufficient natural gas to satisfy our delivery obligations under the SPAs, which could have a material adverse effect on us.

Under the SPAs with our customers, we are required to make available to them a specified amount of LNG at specified times. However, we may not be able to purchase or receive physical delivery of sufficient quantities of natural gas to satisfy those obligations, which may provide affected SPA customers with the right to terminate their SPAs. Our failure to purchase or receive physical delivery of sufficient quantities of natural gas could have a material adverse effect on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.
 
Our interstate natural gas pipelines and their FERC gas tariffs are subject to FERC regulation.
 
Our interstate natural gas pipelines are subject to regulation by the FERC under the NGA and the Natural Gas Policy Act of 1978 (the “NGPA”). The FERC regulates the purchase and transportation of natural gas in interstate commerce, including the construction and operation of pipelines, the rates, terms and conditions of service and abandonment of facilities. Under the NGA, the rates charged by our interstate natural gas pipelines must be just and reasonable, and we are prohibited from unduly preferring or unreasonably discriminating against any person with respect to pipeline rates or terms and conditions of service. If we fail to comply with all applicable statutes, rules, regulations and orders, our interstate pipelines could be subject to substantial penalties and fines.
In addition, as a natural gas market participant, should we fail to comply with all applicable FERC-administered statutes, rules, regulations and orders, we could be subject to substantial penalties and fines. Under the EPAct, the FERC has civil penalty authority under the NGA and the NGPA to impose penalties for current violations of up to $1.3 million per day for each violation.
 

26




Pipeline safety integrity programs and repairs may impose significant costs and liabilities on us.
 
The PHMSA requires pipeline operators to develop integrity management programs to comprehensively evaluate certain areas along their pipelines and to take additional measures to protect pipeline segments located in “high consequence areas” where a leak or rupture could potentially do the most harm. As an operator, we are required to:
perform ongoing assessments of pipeline integrity;
identify and characterize applicable threats to pipeline segments that could impact a “high consequence area”;
improve data collection, integration and analysis;
repair and remediate the pipeline as necessary; and
implement preventative and mitigating actions.
We are required to maintain pipeline integrity testing programs that are intended to assess pipeline integrity. Any repair, remediation, preventative or mitigating actions may require significant capital and operating expenditures. Should we fail to comply with applicable statutes and the Office of Pipeline Safety’s rules and related regulations and orders, we could be subject to significant penalties and fines.
 
Any reduction in the capacity of, or the allocations to, interconnecting, third-party pipelines could cause a reduction of volumes transported in our pipelines, which would adversely affect our revenues and cash flow.
 
We are dependent upon third-party pipelines and other facilities to provide delivery options to and from our pipelines. If any pipeline connection were to become unavailable for volumes of natural gas due to repairs, damage to the facility, lack of capacity or any other reason, our ability to continue shipping natural gas to end markets could be restricted, thereby reducing our revenues. Any permanent interruption at any key pipeline interconnect which causes a material reduction in volumes transported on our pipelines could have a material adverse effect on our business, financial condition, operating results, cash flow, liquidity and prospects.
 
Our business could be materially and adversely affected if we lose the right to situate our pipelines on property owned by third parties.
 
We do not own the land on which our pipelines are situated, and we are subject to the possibility of increased costs to retain necessary land use rights. If we were to lose these rights or be required to relocate our pipelines, our business could be materially and adversely affected.

We are relying on estimates for the future capacity ratings and performance capabilities of the Liquefaction Projects, and these estimates may prove to be inaccurate.
    
We are relying on third parties, principally Bechtel, for the design and engineering services underlying our estimates of the future capacity ratings and performance capabilities of the Liquefaction Projects. If any Train, when actually constructed, fails to have the capacity ratings and performance capabilities that we intend, our estimates may not be accurate. Failure of any of our Trains to achieve our intended capacity ratings and performance capabilities could prevent us from achieving the commercial start dates under our SPAs and could have a material adverse effect on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.

Any failure to perform by our counterparties under agreements may adversely affect our operating results, liquidity and access to financing.
 
Our integrated marketing function involves our entering into various purchase and sale, hedging and other transactions with numerous third parties (commonly referred to as “counterparties”). In such arrangements, we are exposed to the performance and credit risks of our counterparties, including the risk that one or more counterparties fails to perform its obligation to make deliveries of commodities and/or to make payments. These risks may increase during periods of commodity price volatility. Defaults by suppliers and other counterparties may adversely affect our operating results, liquidity and access to financing.


27




We may not be able to contract with customers to sell LNG produced in excess of the aggregate annual contract quantities committed to SPL’s and CCL’s third-party SPAs.
 
We expect to sell any LNG produced in excess of the aggregate annual contract quantity committed to SPL’s and CCL’s third-party SPAs through our integrated marketing function. We are developing a portfolio of long-, medium- and short-term SPAs to transport and unload commercial LNG cargoes to locations worldwide, which is primarily sourced by LNG produced by the Liquefaction Projects in excess of the contract quantities committed to SPL’s and CCL’s third party SPAs, supplemented by volume procured from other locations worldwide, as needed. Excess LNG from the Liquefaction Projects competes with other sources of LNG that are priced to indices other than Henry Hub, and any collapse in the spread between global LNG prices and the Henry Hub index could impact the ability of our integrated marketing function to profitably sell any such excess LNG. Failure to secure buyers for a sufficient amount of LNG could materially and adversely affect our operating results, cash flows and liquidity.

Risks Relating to Our LNG Businesses in General
 
We may not construct or operate all of our proposed LNG facilities or Trains or any additional LNG facilities or Trains beyond those currently planned, which could limit our growth prospects.

We may not construct some of our proposed LNG facilities or Trains, whether due to lack of commercial interest or inability to obtain financing or otherwise. Our ability to develop additional liquefaction facilities will also depend on the availability and pricing of LNG and natural gas in North America and other places around the world. Competitors may have longer operating histories, more development experience, greater name recognition, larger staffs and substantially greater financial, technical and marketing resources and access to sources of natural gas and LNG than we do. If we are unable or unwilling to construct and operate additional LNG facilities, our prospects for growth will be limited.

Our cost estimates for Trains are subject to change as a result of cost overruns, change orders under existing or future construction contracts, changes in commodity prices (particularly nickel and steel), escalating labor costs and the potential need for additional funds to be expended to maintain construction schedules. In the event we experience cost overruns, delays or both, the amount of funding needed to complete a Train could exceed our available funds and result in our failure to complete such Train and thereby negatively impact our business and limit our growth prospects.

Cyclical or other changes in the demand for and price of LNG and natural gas may adversely affect our LNG business and the performance of our customers and could have a material adverse effect on our business, contracts, financial condition, operating results, cash flows, liquidity and prospects.
 
Our LNG business and the development of domestic LNG facilities and projects generally is based on assumptions about the future availability and price of natural gas and LNG, and the prospects for international natural gas and LNG markets. Natural gas and LNG prices have been, and are likely to continue to be, volatile and subject to wide fluctuations in response to one or more of the following factors:
additions to competitive regasification capacity in North America, Europe, Asia and other markets, which could divert LNG from the Sabine Pass LNG terminal and the Corpus Christi LNG terminal;
competitive liquefaction capacity in North America;
insufficient or oversupply of natural gas liquefaction or receiving capacity worldwide;
insufficient LNG tanker capacity;
weather conditions, including extreme weather events and temperature volatility resulting from climate change;
reduced demand and lower prices for natural gas;
increased natural gas production deliverable by pipelines, which could suppress demand for LNG;
decreased oil and natural gas exploration activities which may decrease the production of natural gas, including as a result of any potential ban on production of natural gas through hydraulic fracturing;
cost improvements that allow competitors to offer LNG regasification services or provide natural gas liquefaction capabilities at reduced prices;

28




changes in supplies of, and prices for, alternative energy sources such as coal, oil, nuclear, hydroelectric, wind and solar energy, which may reduce the demand for natural gas;
changes in regulatory, tax or other governmental policies regarding imported or exported LNG, natural gas or alternative energy sources, which may reduce the demand for imported or exported LNG and/or natural gas;
political conditions in natural gas producing regions;
sudden decreases in demand for LNG as a result of natural disasters or public health crises, including the occurrence of a pandemic, and other catastrophic events;
adverse relative demand for LNG compared to other markets, which may decrease LNG imports into or exports from North America; and
cyclical trends in general business and economic conditions that cause changes in the demand for natural gas.
Adverse trends or developments affecting any of these factors could result in decreases in the price of LNG and/or natural gas, which could materially and adversely affect the performance of our customers, and could have a material adverse effect on our business, contracts, financial condition, operating results, cash flows, liquidity and prospects.

Failure of imported or exported LNG to be a competitive source of energy for the United States or international markets could adversely affect our customers and could materially and adversely affect our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.

Operations of the Liquefaction Projects are dependent upon the ability of our SPA customers to deliver LNG supplies from the United States, which is primarily dependent upon LNG being a competitive source of energy internationally. The success of our business plan is dependent, in part, on the extent to which LNG can, for significant periods and in significant volumes, be supplied from North America and delivered to international markets at a lower cost than the cost of alternative energy sources. Through the use of improved exploration technologies, additional sources of natural gas may be discovered outside the United States, which could increase the available supply of natural gas outside the United States and could result in natural gas in those markets being available at a lower cost than LNG exported to those markets.

Although SPL has entered into arrangements to utilize up to approximately three-quarters of the regasification capacity at the Sabine Pass LNG terminal in connection with operations of the SPL Project, operations at the Sabine Pass LNG terminal are dependent, in part, upon the ability of our TUA customers to import LNG supplies into the United States, which is primarily dependent upon LNG being a competitive source of energy in North America. In North America, due mainly to a historically abundant supply of natural gas and discoveries of substantial quantities of unconventional, or shale, natural gas, imported LNG has not developed into a significant energy source. The success of the regasification services component of our business plan is dependent, in part, on the extent to which LNG can, for significant periods and in significant volumes, be produced internationally and delivered to North America at a lower cost than the cost to produce some domestic supplies of natural gas, or other alternative energy sources. Through the use of improved exploration technologies, additional sources of natural gas have recently been and may continue to be discovered in North America, which could further increase the available supply of natural gas and could result in natural gas being available at a lower cost than imported LNG.

Political instability in foreign countries that import or export natural gas, or strained relations between such countries and the United States, may also impede the willingness or ability of LNG purchasers or suppliers and merchants in such countries to import or export LNG from or to the United States. Furthermore, some foreign purchasers or suppliers of LNG may have economic or other reasons to obtain their LNG from, or direct their LNG to, non-U.S. markets or from or to our competitors’ liquefaction or regasification facilities in the United States.

In addition to natural gas, LNG also competes with other sources of energy, including coal, oil, nuclear, hydroelectric, wind and solar energy. LNG from the Liquefaction Projects also competes with other sources of LNG, including LNG that is priced to indices other than Henry Hub. Some of these sources of energy may be available at a lower cost than LNG from the Liquefaction Projects in certain markets. The cost of LNG supplies from the United States, including the Liquefaction Projects, may also be impacted by an increase in natural gas prices in the United States.
 
As a result of these and other factors, LNG may not be a competitive source of energy in the United States or internationally. The failure of LNG to be a competitive supply alternative to local natural gas, oil and other alternative energy sources in markets accessible to our customers could adversely affect the ability of our customers to deliver LNG from the United States or to the

29




United States on a commercial basis. Any significant impediment to the ability to deliver LNG to or from the United States generally, or to the Sabine Pass LNG terminal or the Corpus Christi LNG terminal or from the Liquefaction Projects specifically, could have a material adverse effect on our customers and on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.
 
Various economic and political factors could negatively affect the development, construction and operation of LNG facilities, including the Liquefaction Projects and expansion projects, which could have a material adverse effect on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.

Commercial development of an LNG facility takes a number of years, requires a substantial capital investment and may be delayed by factors such as:
increased construction costs;
economic downturns, increases in interest rates or other events that may affect the availability of sufficient financing for LNG projects on commercially reasonable terms;
decreases in the price of LNG, which might decrease the expected returns relating to investments in LNG projects;
the inability of project owners or operators to obtain governmental approvals to construct or operate LNG facilities;
political unrest or local community resistance to the siting of LNG facilities due to safety, environmental or security concerns; and
any significant explosion, spill or similar incident involving an LNG facility or LNG vessel.

There may be shortages of LNG vessels worldwide, which could have a material adverse effect on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.

The construction and delivery of LNG vessels require significant capital and long construction lead times, and the availability of the vessels could be delayed to the detriment of our business and our customers because of:
an inadequate number of shipyards constructing LNG vessels and a backlog of orders at these shipyards;
political or economic disturbances in the countries where the vessels are being constructed;
changes in governmental regulations or maritime self-regulatory organizations;
work stoppages or other labor disturbances at the shipyards;
bankruptcy or other financial crisis of shipbuilders;
quality or engineering problems;
weather interference or a catastrophic event, such as a major earthquake, tsunami or fire; and
shortages of or delays in the receipt of necessary construction materials.
We may not be able to secure firm pipeline transportation capacity on economic terms that is sufficient to meet our feed gas transportation requirements, which could have a material adverse effect on us.

We have contracted for firm capacity for our natural gas feedstock transportation requirements for the Liquefaction Projects and for Corpus Christi Stage 3.  If and when we need to replace one or more of our existing agreements with these interconnecting pipelines, we may not be able to do so on commercially reasonable terms or at all, which could impair our ability to fulfill our obligations under certain of our SPAs and could have a material adverse effect on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.

We face competition based upon the international market price for LNG.
    
Our liquefaction projects are subject to the risk of LNG price competition at times when we need to replace any existing SPA, whether due to natural expiration, default or otherwise, or enter into new SPAs. Factors relating to competition may prevent us from entering into a new or replacement SPA on economically comparable terms as existing SPAs, or at all. Such an event could have a material adverse effect on our business, contracts, financial condition, operating results, cash flow, liquidity and

30




prospects. Factors which may negatively affect potential demand for LNG from our liquefaction projects are diverse and include, among others:
increases in worldwide LNG production capacity and availability of LNG for market supply;
increases in demand for LNG but at levels below those required to maintain current price equilibrium with respect to supply;
increases in the cost to supply natural gas feedstock to our liquefaction projects;
decreases in the cost of competing sources of natural gas or alternate fuels such as coal, heavy fuel oil and diesel;
decreases in the price of non-U.S. LNG, including decreases in price as a result of contracts indexed to lower oil prices;
increases in capacity and utilization of nuclear power and related facilities; and
displacement of LNG by pipeline natural gas or alternate fuels in locations where access to these energy sources is not currently available.
Terrorist attacks, cyber incidents or military campaigns may adversely impact our business.

A terrorist attack, cyber incident or military incident involving an LNG facility, our infrastructure or an LNG vessel may result in delays in, or cancellation of, construction of new LNG facilities, including one or more of the Trains, which would increase our costs and decrease our cash flows. A terrorist incident or cyber incident may also result in temporary or permanent closure of our existing facilities, which could increase our costs and decrease our cash flows, depending on the duration and timing of the closure. Our operations could also become subject to increased governmental scrutiny that may result in additional security measures at a significant incremental cost to us. In addition, the threat of terrorism and the impact of military campaigns may lead to continued volatility in prices for natural gas that could adversely affect our business and our customers, including their ability to satisfy their obligations to us under our commercial agreements. Instability in the financial markets as a result of terrorism, cyber incidents or war could also materially adversely affect our ability to raise capital. The continuation of these developments may subject our construction and our operations to increased risks, as well as increased costs, and, depending on their ultimate magnitude, could have a material adverse effect on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.

Risks Relating to Our Business in General
 
We are subject to significant construction and operating hazards and uninsured risks, one or more of which may create significant liabilities and losses for us.

The construction and operation of our LNG terminals and our pipelines are, and will be, subject to the inherent risks associated with these types of operations, including explosions, pollution, release of toxic substances, fires, hurricanes and adverse weather conditions and other hazards, each of which could result in significant delays in commencement or interruptions of operations and/or in damage to or destruction of our facilities or damage to persons and property. In addition, our operations and the facilities and vessels of third parties on which our operations are dependent face possible risks associated with acts of aggression or terrorism.
 
We do not, nor do we intend to, maintain insurance against all of these risks and losses. We may not be able to maintain desired or required insurance in the future at rates that we consider reasonable. The occurrence of a significant event not fully insured or indemnified against could have a material adverse effect on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects. 
 
Existing and future environmental and similar laws and governmental regulations could result in increased compliance costs or additional operating costs or construction costs and restrictions.
    
Our business is and will be subject to extensive federal, state and local laws, rules and regulations applicable to our construction and operation activities relating to, among other things, air quality, water quality, waste management, natural resources and health and safety. Many of these laws and regulations, such as the CAA, the Oil Pollution Act, the CWA and the RCRA, and analogous state laws and regulations, restrict or prohibit the types, quantities and concentration of substances that can be released into the environment in connection with the construction and operation of our facilities, and require us to maintain permits and provide governmental authorities with access to our facilities for inspection and reports related to our compliance. In addition,

31




certain laws and regulations authorize regulators having jurisdiction over the construction and operation of our LNG terminals and pipelines, including FERC and PHMSA, to issue compliance orders, which may restrict or limit operations or increase compliance or operating costs. Violation of these laws and regulations could lead to substantial liabilities, compliance orders, fines and penalties or to capital expenditures that could have a material adverse effect on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects. Federal and state laws impose liability, without regard to fault or the lawfulness of the original conduct, for the release of certain types or quantities of hazardous substances into the environment. As the owner and operator of our facilities, we could be liable for the costs of cleaning up hazardous substances released into the environment at or from our facilities and for resulting damage to natural resources.
    
In 2009, the EPA promulgated and finalized the Mandatory Greenhouse Gas Reporting Rule requiring annual reporting of GHG emissions from stationary sources in a variety of industries. In 2010, the EPA expanded the rule to include reporting obligations for LNG terminals. In addition, the EPA has defined GHG emissions thresholds that would subject GHG emissions from new and modified industrial sources to regulation if the source is subject to PSD Permit requirements due to its emissions of non-GHG criteria pollutants. While the EPA subsequently took a number of additional actions primarily relating to GHG emissions from the electric power generation and the oil and gas exploration and production industries, those rules have largely been stayed or repealed including by amendments adopted by the EPA on February 23, 2018, additional proposed amendments to new source performance standards for the oil and gas industry on September 24, 2019 and the EPA’s June 19, 2019 adoption of the Affordable Clean Energy rule for power generation. However, Congress or a future Administration may reverse these decisions. Other federal and state initiatives may be considered in the future to address GHG emissions through, for example, United States treaty commitments, direct regulation, market-based regulations such as a carbon emissions tax or cap-and-trade programs or clean energy standards. Such initiatives could affect the demand for or cost of natural gas, which we consume at our terminals, or could increase compliance costs for our operations.
    
Other future legislation and regulations, such as those relating to the transportation and security of LNG imported to or exported from our terminals or climate policies of destination countries in relation to their obligations under the Paris Agreement or other national climate change-related policies, could cause additional expenditures, restrictions and delays in our business and to our proposed construction activities, the extent of which cannot be predicted and which may require us to limit substantially, delay or cease operations in some circumstances. Revised, reinterpreted or additional laws and regulations that result in increased compliance costs or additional operating or construction costs and restrictions could have a material adverse effect on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.

A major health and safety incident relating to our business could be costly in terms of potential liabilities and reputational damages.

Health and safety performance is critical to the success of all areas of our business. Any failure in health and safety performance may result in personal harm or injury, penalties for non-compliance with relevant regulatory requirements or litigation, and a failure that results in a significant health and safety incident is likely to be costly in terms of potential liabilities. Such a failure could generate public concern and have a corresponding impact on our reputation and our relationships with relevant regulatory agencies and local communities, which in turn could have a material adverse effect on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.
 
We may experience increased labor costs, and the unavailability of skilled workers or our failure to attract and retain qualified personnel could adversely affect us. In addition, changes in our senior management or other key personnel could affect our business results.
 
We are dependent upon the available labor pool of skilled employees. We compete with other energy companies and other employers to attract and retain qualified personnel with the technical skills and experience required to construct and operate our facilities and pipelines and to provide our customers with the highest quality service. Our affiliates who hire personnel on our behalf are also subject to the Fair Labor Standards Act, which governs such matters as minimum wage, overtime and other working conditions. A shortage in the labor pool of skilled workers or other general inflationary pressures or changes in applicable laws and regulations could make it more difficult for us to attract and retain qualified personnel and could require an increase in the wage and benefits packages that we offer, thereby increasing our operating costs. Any increase in our operating costs could materially and adversely affect our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.
 
We depend on our executive officers for various activities. We do not maintain key person life insurance policies on any of our personnel. Although we have arrangements relating to compensation and benefits with certain of our executive officers,

32




we do not have any employment contracts or other agreements with key personnel other than our employment agreement with our President and Chief Executive Officer binding them to provide services for any particular term. The loss of the services of any of these individuals could have a material adverse effect on our business.
 
Our lack of diversification could have an adverse effect on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.
 
Substantially all of our anticipated revenue in 2020 will be dependent upon our two facilities, the Sabine Pass LNG terminal located in southern Louisiana and the Corpus Christi LNG terminal in Texas. Due to our lack of asset and geographic diversification, an adverse development at the Sabine Pass LNG terminal or the Corpus Christi LNG terminal, including the related pipelines, or in the LNG industry, would have a significantly greater impact on our financial condition and operating results than if we maintained more diverse assets and operating areas.

We may incur impairments to goodwill or long-lived assets.
 
We test our long-lived assets for impairment whenever events or changes in circumstances indicate that the carrying amount of these assets may not be recoverable. We test goodwill for impairment annually during the fourth quarter, or more frequently as circumstances dictate. Significant negative industry or economic trends, including a significant decline in the market price of our common stock, reduced estimates of future cash flows for our business or disruptions to our business could lead to an impairment charge of our long-lived assets, including goodwill. Our valuation methodology for assessing impairment requires management to make judgments and assumptions based on historical experience and to rely heavily on projections of future operating performance. Projections of future operating results and cash flows may vary significantly from results. In addition, if our analysis results in an impairment to our goodwill or long-lived assets, we may be required to record a charge to earnings in our Consolidated Financial Statements during a period in which such impairment is determined to exist, which may negatively impact our operating results.

We cannot guarantee that our share repurchase program will be fully consummated or that it will enhance long-term stockholder value.

In June 2019, our Board authorized a three-year, $1 billion share repurchase program and as of December 31, 2019, up to $751 million remains available for repurchase. Our share repurchase program does not obligate us to acquire any particular amount of common stock. Our share repurchase program may be modified, suspended or terminated at any time, which may result in a decrease in the trading price of our common stock.

The market price of our common stock has fluctuated significantly in the past and is likely to fluctuate in the future. Our stockholders could lose all or part of their investment.

The market price of our common stock has historically experienced and may continue to experience volatility. For example, during the three-year period ended December 31, 2019, the market price of our common stock ranged between $40.36 and $71.03. Such fluctuations may continue as a result of a variety of factors, some of which are beyond our control, including:
domestic and worldwide supply of and demand for natural gas and corresponding fluctuations in the price of natural gas;
fluctuations in our quarterly or annual financial results or those of other companies in our industry;
issuance of additional equity securities which causes further dilution to stockholders;
sales of a high volume of shares of our common stock by our stockholders;
operating and stock price performance of companies that investors deem comparable to us;
events affecting other companies that the market deems comparable to us;
changes in government regulation or proposals applicable to us;
actual or potential non-performance by any customer or a counterparty under any agreement;
announcements made by us or our competitors of significant contracts;
changes in accounting standards, policies, guidance, interpretations or principles;

33




general conditions in the industries in which we operate;
general economic conditions;
the failure of securities analysts to cover our common stock or changes in financial or other estimates by analysts; and
other factors described in these “Risk Factors.”

In addition, the United States securities markets have experienced significant price and volume fluctuations. These fluctuations have often been unrelated to the operating performance of companies in these markets. Market fluctuations and broad market, economic and industry factors may negatively affect the price of our common stock, regardless of our operating performance. If we were to be the object of securities class litigation as a result of volatility in our common stock price or for other reasons, it could result in substantial diversion of our management’s attention and resources, which could negatively affect our financial results.

ITEM 1B.
UNRESOLVED STAFF COMMENTS
 
None.

ITEM 3.    LEGAL PROCEEDINGS

We may in the future be involved as a party to various legal proceedings, which are incidental to the ordinary course of business. We regularly analyze current information and, as necessary, provide accruals for probable liabilities on the eventual disposition of these matters.

LDEQ Matter

Certain of our subsidiaries are in discussions with the LDEQ to resolve self-reported deviations arising from operation of the Sabine Pass LNG terminal and the commissioning of the SPL Project, and relating to certain requirements under its Title V Permit. The matter involves deviations self-reported to LDEQ pursuant to the Title V Permit and covering the time period from January 1, 2012 through March 25, 2016. On April 11, 2016, certain of our subsidiaries received a Consolidated Compliance Order and Notice of Potential Penalty (the “Compliance Order”) from LDEQ covering deviations self-reported during that time period. Certain of our subsidiaries continue to work with LDEQ to resolve the matters identified in the Compliance Order. We do not expect that any ultimate sanction will have a material adverse impact on our financial results.

PHMSA Matter

In February 2018, the PHMSA issued a Corrective Action Order (the “CAO”) to SPL in connection with a minor LNG leak from one tank and minor vapor release from a second tank at the Sabine Pass LNG terminal. These two tanks have been taken out of operational service while we conduct analysis, repair and remediation. On April 20, 2018, SPL and PHMSA executed a Consent Agreement and Order (the “Consent Order”) that replaces and supersedes the CAO. On July 9, 2019, PHMSA and FERC issued a joint letter setting out operating conditions required to be met prior to SPL returning the tanks to service. We continue to coordinate with PHMSA and FERC to address the matters relating to the February 2018 leak, including repair approach and related analysis. We do not expect that the Consent Order and related analysis, repair and remediation will have a material adverse impact on our financial results or operations.

Parallax and Related Litigation

In 2015, our wholly owned subsidiary Cheniere LNG Terminals, LLC (“CLNGT”), entered into discussions with Parallax Enterprises, LLC (“Parallax Enterprises”) regarding the potential joint development of two liquefaction plants in Louisiana (the “Potential Liquefaction Transactions”). While the parties negotiated regarding the Potential Liquefaction Transactions, CLNGT loaned Parallax Enterprises approximately $46 million, as reflected in a secured note dated April 23, 2015, as amended on June 30, 2015, September 30, 2015 and November 4, 2015 (the “Secured Note”). The Secured Note was secured by all assets of Parallax Enterprises and its subsidiary entities. On June 30, 2015, Parallax Enterprises’ parent entity, Parallax Energy LLC (“Parallax Energy”), executed a Pledge and Guarantee Agreement further securing repayment of the Secured Note by providing a parent guaranty and a pledge of all of the equity of Parallax Enterprises in satisfaction of the Secured Note (the “Pledge Agreement”). CLNGT and Parallax Enterprises never executed a definitive agreement to pursue the Potential Liquefaction Transactions. The

34


Secured Note matured on December 11, 2015, and Parallax Enterprises failed to make payment. On February 3, 2016, CLNGT filed an action against Parallax Energy, Parallax Enterprises and certain of Parallax Enterprises’ subsidiary entities, styled Cause No. 4:16-cv-00286, Cheniere LNG Terminals, LLC v. Parallax Energy LLC, et al., in the United States District Court for the Southern District of Texas (the “Texas Federal Suit”). CLNGT asserted claims in the Texas Federal Suit for (1) recovery of all amounts due under the Secured Note and (2) declaratory relief establishing that CLNGT is entitled to enforce its rights under the Secured Note and Pledge Agreement in accordance with each instrument’s terms and that CLNGT has no obligations of any sort to Parallax Enterprises concerning the Potential Liquefaction Transactions. On March 11, 2016, Parallax Enterprises and the other defendants in the Texas Federal Suit moved to dismiss the suit for lack of subject matter jurisdiction. On August 2, 2016, the court denied the defendants’ motion to dismiss without prejudice and permitted the parties to pursue jurisdictional discovery.

On March 11, 2016, Parallax Enterprises filed a suit against us and CLNGT styled Civil Action No. 62-810, Parallax Enterprises LLP v. Cheniere Energy, Inc. and Cheniere LNG Terminals, LLC, in the 25th Judicial District Court of Plaquemines Parish, Louisiana (the “Louisiana Suit”), wherein Parallax Enterprises asserted claims for breach of contract, fraudulent inducement, negligent misrepresentation, detrimental reliance, unjust enrichment and violation of the Louisiana Unfair Trade Practices Act. Parallax Enterprises predicated its claims in the Louisiana Suit on an allegation that we and CLNGT breached a purported agreement to jointly develop the Potential Liquefaction Transactions. Parallax Enterprises sought $400 million in alleged economic damages and rescission of the Secured Note. On April 15, 2016, we and CLNGT removed the Louisiana Suit to the United States District Court for the Eastern District of Louisiana, which subsequently transferred the Louisiana Suit to the United States District Court for the Southern District of Texas, where it was assigned Civil Action No. 4:16-cv-01628 and transferred to the same judge presiding over the Texas Federal Suit for coordinated handling. On August 22, 2016, Parallax Enterprises voluntarily dismissed all claims asserted against CLNGT and us in the Louisiana Suit without prejudice to refiling.

On July 27, 2017, the Parallax entities named as defendants in the Texas Federal Suit reurged their motion to dismiss and simultaneously filed counterclaims against CLNGT and third party claims against us for breach of contract, breach of fiduciary duty, promissory estoppel, quantum meruit and fraudulent inducement of the Secured Note and Pledge Agreement, based on substantially the same factual allegations Parallax Enterprises made in the Louisiana Suit. These Parallax entities also simultaneously filed an action styled Cause No. 2017-49685, Parallax Enterprises, LLC, et al. v. Cheniere Energy, Inc., et al., in the 61st District Court of Harris County, Texas (the “Texas State Suit”), which asserts substantially the same claims these entities asserted in the Texas Federal Suit. On July 31, 2017, CLNGT withdrew its opposition to the dismissal of the Texas Federal Suit without prejudice on jurisdictional grounds and the federal court subsequently dismissed the Texas Federal Suit without prejudice. We and CLNGT simultaneously filed an answer and counterclaims in the Texas State Suit, asserting the same claims CLNGT had previously asserted in the Texas Federal Suit. Additionally, CLNGT filed third party claims against Parallax principals Martin Houston, Christopher Bowen Daniels, Howard Candelet and Mark Evans, as well as Tellurian Investments, Inc., Driftwood LNG, LLC, Driftwood LNG Pipeline LLC and Tellurian Services LLC, formerly known as Parallax Services LLC, including claims for tortious interference with CLNGT’s collateral rights under the Secured Note and Pledge Agreement, fraudulent transfer, conspiracy/aiding and abetting.
 
On February 15, 2019, we filed an action with CLNGT against Charif Souki, our former Chairman of the Board and Chief Executive Officer, styled, Cause No. 2019-11529, Cheniere Energy, Inc. and Cheniere LNG Terminals, LLC v. Charif Souki, in the 55th District Court of Harris County, Texas, which asserts claims of breach of fiduciary duties, fraudulent transfer, tortious interference with CLNGT’s collateral rights under the Secured Note and Pledge Agreement, and conspiracy/aiding and abetting. On April 29, 2019, the court consolidated the Souki matter with the earlier filed pending case against Parallax, Tellurian and the individual defendants in the Texas State Suit.

On January 30, 2020, the parties filed an Agreed Motion to Dismiss and all claims were dismissed with prejudice.

The resolution of the foregoing litigation did not have a material adverse impact on our financial results.

On January 10, 2020, a purported shareholder of Cheniere filed a shareholder derivative action in state court in Houston, Texas. The complaint names as defendants ten of our current directors. The plaintiff alleges that those directors breached their fiduciary duties by abandoning a proposed joint-development arrangement with Parallax in 2015, which later was the subject of a separate lawsuit by Parallax discussed above. According to the complaint, the directors’ alleged breach of their fiduciary duties caused us to incur legal fees in the Parallax action and also exposed us to a potential damages award in the Parallax lawsuit. On January 30, 2020, Parallax voluntarily dismissed with prejudice all claims against us. We do not expect that the resolution of the foregoing litigation will have a material adverse impact on our financial results.


35




ITEM 4.
MINE SAFETY DISCLOSURE

Not applicable.






PART II

ITEM 5.
MARKET FOR REGISTRANT’S COMMON EQUITY, RELATED STOCKHOLDER MATTERS AND ISSUER PURCHASES OF EQUITY SECURITIES

Market Information, Holders and Dividends
 
Our common stock has traded on the NYSE American under the symbol “LNG” since March 24, 2003. As of February 19, 2020, we had 254 million shares of common stock outstanding held by 96 record owners.
 
We have never paid a cash dividend on our common stock. Any future change in our dividend policy will be made at the discretion of our Board of Directors (our “Board”) in light of our financial condition, capital requirements, earnings, prospects and any restrictions under any financing agreements, as well as other factors our Board deems relevant.

Purchase of Equity Securities by the Issuer and Affiliated Purchasers

The following table summarizes stock repurchases for the three months ended December 31, 2019:
Period
 
Total Number of Shares Purchased (1)
 
Average Price Paid Per Share (2)
 
Total Number of Shares Purchased as a Part of Publicly Announced Plans
 
Approximate Dollar Value of Shares That May Yet Be Purchased Under the Plans (3)
October 1 - 31, 2019
 
324,138
 
$62.15
 
322,000
 
$820,860,569
November 1 - 30, 2019
 
372,766
 
$60.98
 
372,400
 
$798,153,446
December 1 - 31, 2019
 
784,815
 
$60.33
 
783,700
 
$750,875,707
Total
 
1,481,719
 
$60.89
 
1,478,100
 
 
 
(1)
Includes shares surrendered to us by participants in our share-based compensation plans for payment of applicable tax withholdings on the vesting of share-based compensation awards. Associated shares surrendered by participants are repurchased pursuant to terms of the plan and award agreements and not as part of the publicly announced share repurchase plan.
(2)
The price paid per share was based on the average trading price of our common stock on the dates on which we repurchased the shares.
(3)
On June 3, 2019, we announced that our Board authorized a 3-year, $1 billion share repurchase program. For additional information, see Note 18—Share Repurchase Program of our Notes to Consolidated Financial Statements under Item 8 of this Form 10-K.


37


Total Stockholder Return
 
The following is a customized peer group consisting of 27 companies (the “New Peer Group”) that were selected because they are publicly traded companies that have: (1) comparable Global Industries Classification Standards, (2) similar market capitalization, (3) similar enterprise values and (4) similar operating characteristics and capital intensity:
New Peer Group
Air Products and Chemicals, Inc. (APD)
 
LyondellBasell Industries N.V. (LYB)
Apache Corporation (APA)
 
Marathon Oil Corporation (MRO)
Baker Hughes Company (BKR)
 
Marathon Petroleum Corporation (MPC)
Concho Resources Inc. (CXO)
 
Noble Energy, Inc. (NBL)
ConocoPhillips (COP)
 
Occidental Petroleum Corporation (OXY)
Continental Resources, Inc. (CLR)
 
ONEOK, Inc. (OKE)
Devon Energy Corporation (DVN)
 
Phillips 66 (PSX)
Diamondback Energy, Inc. (FANG)
 
Pioneer Natural Resources Company (PXD)
Enterprise Products Partners L.P. (EPD)
 
Schlumberger Limited (SLB)
EOG Resources, Inc. (EOG)
 
Suncor Energy Inc. (SU)
Freeport-McMoRan Inc. (FCX)
 
Targa Resources Corp. (TRGP)
Halliburton Company (HAL)
 
Valero Energy Corporation (VLO)
Hess Corporation (HES)
 
The Williams Companies, Inc. (WMB)
Kinder Morgan, Inc. (KMI)
 
 

The New Peer Group companies were revised during 2019. Our previous peer group consisted of 29 companies (the “Old Peer Group”), which excluded Diamondback Energy, Inc. (FANG) and Targa Resources Corp. (TRGP) from the New Peer Group and included Anadarko Petroleum Corporation (APC), Andeavor (ANDV), EQT Corporation (EQT) and Praxair, Inc. (PX). Additionally, Baker Hughes, a GE company (BHGE) changed its name and ticker symbol to Baker Hughes Company (BKR) in October 2019.

The following graph compares the five-year total return on our common stock, the S&P 500 Index, the New Peer Group and the Old Peer Group. The graph was constructed on the assumption that $100 was invested in our common stock, the S&P 500 Index, the New Peer Group and the Old Peer Group on December 31, 2014 and that any dividends were fully reinvested.
Company / Index
 
2014
 
2015
 
2016
 
2017
 
2018
 
2019
Cheniere Energy, Inc.
 
100.00

 
52.91

 
58.85

 
76.48

 
84.08

 
86.75

S&P 500 Index
 
100.00

 
101.37

 
113.49

 
138.26

 
132.19

 
173.80

New Peer Group
 
100.00

 
79.05

 
110.62

 
115.91

 
91.57

 
107.19

Old Peer Group
 
100.00

 
79.89

 
108.84

 
113.88

 
89.89

 
103.49



38


chart-3977a579c119fd3c27ea06.jpg




39


ITEM 6.
SELECTED FINANCIAL DATA
 
Selected financial data set forth below are derived from our audited Consolidated Financial Statements for the periods indicated (in millions, except per share data). The financial data should be read in conjunction with Management’s Discussion and Analysis of Financial Condition and Results of Operations and our Consolidated Financial Statements and the accompanying notes thereto included elsewhere in this report.
 
 
Year Ended December 31,
 
 
2019
 
2018
 
2017
 
2016
 
2015
Consolidated Statement of Operations Data:
 
 
 
 
 
 
 
 
 
 
Revenues
 
$
9,730

 
$
7,987

 
$
5,601

 
$
1,283

 
$
271

Income (loss) from operations
 
2,361

 
2,024

 
1,388

 
(30
)
 
(449
)
Interest expense, net of capitalized interest
 
(1,432
)
 
(875
)
 
(747
)
 
(488
)
 
(322
)
Net income (loss) attributable to common stockholders
 
648

 
471

 
(393
)
 
(610
)
 
(975
)
Common Stock Data:
 
 
 
 
 
 
 
 
 
 
Net income (loss) per share attributable to common stockholders—basic
 
$
2.53

 
$
1.92

 
$
(1.68
)
 
$
(2.67
)
 
$
(4.30
)
Net income (loss) per share attributable to common stockholders—diluted
 
$
2.51

 
$
1.90

 
$
(1.68
)
 
$
(2.67
)
 
$
(4.30
)
Weighted average number of common shares outstanding—basic
 
256.2

 
245.6

 
233.1

 
228.8

 
226.9

Weighted average number of common shares outstanding—diluted
 
258.1

 
248.0

 
233.1

 
228.8

 
226.9


 
 
December 31,
 
 
2019
 
2018
 
2017
 
2016
 
2015
Consolidated Balance Sheet Data:
 
 
 
 
 
 
 
 
 
 
Property, plant and equipment, net
 
$
29,673

 
$
27,245

 
$
23,978

 
$
20,635

 
$
16,194

Total assets
 
35,492

 
31,987

 
27,906

 
23,703

 
18,809

Current debt, net
 

 
239

 

 
247

 
1,673

Long-term debt, net
 
30,774

 
28,179

 
25,336

 
21,688

 
14,920



40


ITEM 7.
MANAGEMENT’S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS
 
Introduction
 
The following discussion and analysis presents management’s view of our business, financial condition and overall performance and should be read in conjunction with our Consolidated Financial Statements and the accompanying notes. This information is intended to provide investors with an understanding of our past performance, current financial condition and outlook for the future. Our discussion and analysis includes the following subjects: 
Overview of Business 
Overview of Significant Events 
Liquidity and Capital Resources
Contractual Obligations
Results of Operations 
Off-Balance Sheet Arrangements  
Summary of Critical Accounting Estimates 
Recent Accounting Standards

Overview of Business
 
Cheniere, a Delaware corporation, is a Houston-based energy infrastructure company primarily engaged in LNG-related businesses. We provide clean, secure and affordable LNG to integrated energy companies, utilities and energy trading companies around the world. We aspire to conduct our business in a safe and responsible manner, delivering a reliable, competitive and integrated source of LNG to our customers. We own and operate the Sabine Pass LNG terminal in Louisiana, one of the largest LNG production facilities in the world, through our ownership interest in and management agreements with Cheniere Partners, which is a publicly traded limited partnership that we created in 2007. As of December 31, 2019, we owned 100% of the general partner interest and 48.6% of the limited partner interest in Cheniere Partners. We also own and operate the Corpus Christi LNG terminal in Texas, which is wholly owned by us.

The Sabine Pass LNG terminal is located in Cameron Parish, Louisiana, on the Sabine-Neches Waterway less than four miles from the Gulf Coast. Cheniere Partners, through its subsidiary SPL, is currently operating five natural gas liquefaction Trains and is constructing one additional Train for a total production capacity of approximately 30 mtpa of LNG (the “SPL Project”) at the Sabine Pass LNG terminal. The Sabine Pass LNG terminal has operational regasification facilities owned by Cheniere Partners’ subsidiary, SPLNG, that include pre-existing infrastructure of five LNG storage tanks with aggregate capacity of approximately 17 Bcfe, two marine berths that can each accommodate vessels with nominal capacity of up to 266,000 cubic meters and vaporizers with regasification capacity of approximately 4 Bcf/d. Cheniere Partners also owns a 94-mile pipeline through its subsidiary, CTPL, that interconnects the Sabine Pass LNG terminal with a number of large interstate pipelines.

We also own the Corpus Christi LNG terminal near Corpus Christi, Texas, and are currently operating two Trains and are constructing one additional Train for a total production capacity of approximately 15 mtpa of LNG. Additionally, we are operating a 23-mile natural gas supply pipeline that interconnects the Corpus Christi LNG terminal with several interstate and intrastate natural gas pipelines (the “Corpus Christi Pipeline” and together with the Trains, the “CCL Project”) through our subsidiaries CCL and CCP, respectively. The CCL Project, once fully constructed, will contain three LNG storage tanks with aggregate capacity of approximately 10 Bcfe and two marine berths that can each accommodate vessels with nominal capacity of up to 266,000 cubic meters.

We have contracted approximately 85% of the total production capacity from the SPL Project and the CCL Project (collectively, the “Liquefaction Projects”) on a term basis. This includes volumes contracted under SPAs in which the customers are required to pay a fixed fee with respect to the contracted volumes irrespective of their election to cancel or suspend deliveries of LNG cargoes, as well as volumes contracted under integrated production marketing (“IPM”) gas supply agreements.


41


Additionally, separate from the CCH Group, we are developing an expansion of the Corpus Christi LNG terminal adjacent to the CCL Project (“Corpus Christi Stage 3”) through our subsidiary CCL Stage III for up to seven midscale Trains with an expected total production capacity of approximately 10 mtpa of LNG. We received approval from FERC in November 2019 to site, construct and operate the expansion project.

We remain focused on operational excellence and customer satisfaction. Increasing demand of LNG has allowed us to expand our liquefaction infrastructure in a financially disciplined manner. We hold significant land positions at both the Sabine Pass LNG terminal and the Corpus Christi LNG terminal which provide opportunity for further liquefaction capacity expansion. The development of these sites or other projects, including infrastructure projects in support of natural gas supply and LNG demand, will require, among other things, acceptable commercial and financing arrangements before we can make a final investment decision (“FID”).

Overview of Significant Events

Our significant events since January 1, 2019 and through the filing date of this Form 10-K include the following:
Strategic
In November 2019, we received approval from the FERC to site, construct and operate the Corpus Christi Stage 3 expansion project, which is being developed for up to seven midscale Trains with an expected total production capacity of approximately 10 mtpa of LNG.
In September 2019, CCL and CCL Stage III entered into an IPM transaction with EOG Resources, Inc. (“EOG”) to purchase 140,000 MMBtu per day of natural gas, for a term of approximately 15 years beginning in early 2020, at a price based on the Platts Japan Korea Marker (“JKM”), net of a fixed liquefaction fee and certain costs incurred by Cheniere.
In May 2019, CCL Stage III entered into an IPM transaction with Apache Corporation to purchase 140,000 MMBtu per day of natural gas, for a term of approximately 15 years, at a price based on international LNG indices, net of a fixed liquefaction fee and certain costs incurred by Cheniere.
In May 2019, the board of directors of the general partner of Cheniere Partners made a positive FID with respect to Train 6 of the SPL Project and issued a full notice to proceed with construction to Bechtel Oil, Gas and Chemicals, Inc. (“Bechtel”) in June 2019.
In February 2019, Midship Pipeline Company, LLC (“Midship Pipeline”), in which we hold an equity interest, issued full notice to proceed to construct the Midship natural gas pipeline and related compression and interconnect facilities (the “Midship Project”) following receipt of final Notice to Proceed from the FERC and obtaining financing to construct the Midship Project.
Operational
As of February 21, 2020, over 1,000 cumulative LNG cargoes totaling over 70 million tonnes of LNG have been produced, loaded and exported from the Liquefaction Projects.
In March 2019, SPL achieved substantial completion of Train 5 of the SPL Project and commenced operating activities.
In February 2019 and August 2019, CCL achieved substantial completion of Trains 1 and 2 of the CCL Project, respectively, and commenced operating activities.
Financial
We completed the following debt transactions:
In November 2019, CCH issued an aggregate principal amount of $1.5 billion of 3.700% Senior Secured Notes due 2029 (the "2029 CCH Senior Notes"). Net proceeds of the offering were used to prepay a portion of the outstanding borrowings under the amended and restated CCH Credit Facility (the “CCH Credit Facility”).
In October 2019, CCH issued an aggregate principal amount of $475 million of 3.925% Senior Secured Notes due 2039 (the "3.925% CCH Senior Notes") pursuant to a note purchase agreement with certain accounts managed by BlackRock Real Assets and certain accounts managed by MetLife Investment Management, to prepay a portion of the outstanding indebtedness under the CCH Credit Facility.
In September 2019, CCH issued an aggregate principal amount of $727 million of 4.80% Senior Secured Notes due 2039 (the “4.80% CCH Senior Notes”) pursuant to a note purchase agreement originally entered into in June

42


2019 (“CCH Note Purchase Agreement”) with Allianz Global Investors GmbH, to prepay a portion of the outstanding indebtedness under the CCH Credit Facility.
In September 2019, Cheniere Partners issued an aggregate principal amount of $1.5 billion of 4.500% Senior Notes due 2029 (the “2029 CQP Senior Notes”) to prepay the outstanding balance under the $750 million term loan under Cheniere Partners’ credit facilities (the “2019 CQP Credit Facilities”), which were entered into in May 2019, and for general corporate purposes, including funding future capital expenditures in connection with the construction of Train 6 at the SPL Project. After applying the proceeds of the 2029 CQP Senior Notes, only a $750 million revolving credit facility, which is currently undrawn, remains as part of the 2019 CQP Credit Facilities.
In September 2019, Fitch Ratings (“Fitch”) and S&P Global Ratings each assigned an investment grade rating of BBB- to CCH’s senior secured debt, and Fitch assigned an investment grade issuer default rating of BBB- to CCH. In October 2019, Moody’s Investors Service upgraded its rating of CCH’s senior secured debt from Ba2 to Ba1 (Positive Outlook).
In June 2019, we announced a capital allocation framework which prioritizes investments in the growth of our liquefaction platform, improvement of consolidated leverage metrics, and a return of excess capital to shareholders under a three-year, $1.0 billion share repurchase program. We commenced share repurchase activity in the second quarter of 2019 and commenced prepayment of outstanding debt in the third quarter of 2019.
We reached the following contractual milestones:
In September 2019, the date of first commercial delivery was reached under the 20-year SPAs with Centrica plc and Total Gas & Power North America, Inc. (“Total”) relating to Train 5 of the SPL Project.
In June 2019, the date of first commercial delivery was reached under the 20-year SPAs with Endesa S.A. and PT Pertamina (Persero) relating to Train 1 of the CCL Project.
In March 2019, the date of first commercial delivery was reached under the 20-year SPA with BG Gulf Coast LNG, LLC relating to Train 4 of the SPL Project.

Liquidity and Capital Resources

Although results are consolidated for financial reporting, Cheniere, Cheniere Partners, SPL and the CCH Group operate with independent capital structures. Our capital requirements include capital and investment expenditures, repayment of long-term debt and repurchase of our shares. We expect the cash needs for at least the next twelve months will be met for each of these independent capital structures as follows:
SPL through project debt and borrowings, operating cash flows and equity contributions from Cheniere Partners;
Cheniere Partners through operating cash flows from SPLNG, SPL and CTPL and debt or equity offerings;
CCH Group through operating cash flows from CCL and CCP, project debt and borrowings and equity contributions from Cheniere; and
Cheniere through existing unrestricted cash, debt and equity offerings by us or our subsidiaries, operating cash flows, borrowings, services fees from our subsidiaries and distributions from our investment in Cheniere Partners.


43


The following table provides a summary of our liquidity position at December 31, 2019 and 2018 (in millions):
 
December 31,
 
2019
 
2018
Cash and cash equivalents (1)
$
2,474

 
$
981

Restricted cash designated for the following purposes:
 
 
 
SPL Project
181

 
756

Cheniere Partners and cash held by guarantor subsidiaries

 
785

CCL Project
80

 
289

Other
259

 
345

Available commitments under the following credit facilities:
 
 
 
$1.2 billion SPL Working Capital Facility (“SPL Working Capital Facility”)
786

 
775

2019 CQP Credit Facilities
750

 

$2.8 billion Cheniere Partners’ Credit Facilities (“2016 CQP Credit Facilities”)

 
115

CCH Credit Facility

 
982

$1.2 billion CCH Working Capital Facility (“CCH Working Capital Facility”)
729

 
716

$1.25 billion Cheniere Revolving Credit Facility (“Cheniere Revolving Credit Facility”)
665

 
1,250

 
(1)
Amounts presented include balances held by our consolidated variable interest entity (“VIE”), Cheniere Partners as discussed in Note 9—Non-controlling Interest and Variable Interest Entity of our Notes to Consolidated Financial Statements. As of December 31, 2019 and 2018, assets of Cheniere Partners, which are included in our Consolidated Balance Sheets, included $1.8 billion and zero, respectively, of cash and cash equivalents.
 
Sabine Pass LNG Terminal

Liquefaction Facilities

The SPL Project is one of the largest LNG production facilities in the world. Through Cheniere Partners, we are currently operating five Trains and two marine berths at the SPL Project and are constructing one additional Train. We have received authorization from the FERC to site, construct and operate Trains 1 through 6. We have achieved substantial completion of the first five Trains of the SPL Project and commenced commercial operating activities for each Train at various times starting in May 2016. The following table summarizes the project completion and construction status of Train 6 of the SPL Project as of December 31, 2019:
 
 
SPL Train 6
Overall project completion percentage
 
43.7%
Completion percentage of:
 

Engineering
 
91.5%
Procurement
 
60.9%
Subcontract work
 
37.4%
Construction
 
9.7%
Date of expected substantial completion
 
1H 2023

The following orders have been issued by the DOE authorizing the export of domestically produced LNG by vessel from the Sabine Pass LNG terminal:
Trains 1 through 4—FTA countries for a 30-year term, which commenced in May 2016, and non-FTA countries for a 20-year term, which commenced in June 2016, in an amount up to a combined total of the equivalent of 16 mtpa (approximately 803 Bcf/yr of natural gas).
Trains 1 through 4—FTA countries for a 25-year term and non-FTA countries for a 20-year term, both of which commenced in December 2018, in an amount up to a combined total of the equivalent of approximately 203 Bcf/yr of natural gas (approximately 4 mtpa).
Trains 5 and 6—FTA countries and non-FTA countries for a 20-year term, which partially commenced in June 2019 and the remainder commenced in September 2019, in an amount up to a combined total of 503.3 Bcf/yr of natural gas (approximately 10 mtpa).


44


In each case, the terms of these authorizations began on the earlier of the date of first export thereunder or the date specified in the particular order. In addition, SPL received an order providing for a three-year makeup period with respect to each of the non-FTA orders for LNG volumes SPL was authorized but unable to export during any portion of the initial 20-year export period of such order.

The DOE issued orders authorizing SPL to export domestically produced LNG by vessel from the Sabine Pass LNG terminal to FTA countries and non-FTA countries over a two-year period commencing January 2020, in an aggregate amount up to the equivalent of 600 Bcf of natural gas (however, exports under this order, when combined with exports under the orders above, may not exceed 1,509 Bcf/yr).

An application was filed in September 2019 to authorize additional exports from the SPL Project to FTA countries for a 25-year term and to non-FTA countries for a 20-year term in an amount up to the equivalent of approximately 153 Bcf/yr of natural gas, for a total SPL Project export of approximately 1,662 Bcf/yr. The terms of the authorizations are requested to commence on the date of first commercial export from the SPL Project of the volumes contemplated in the application. The application is currently pending before DOE.

Customers

SPL has entered into fixed price long-term SPAs generally with terms of 20 years (plus extension rights) with eight third parties for Trains 1 through 6 of the SPL Project. Under these SPAs, the customers will purchase LNG from SPL on a free on board (“FOB”) basis for a price consisting of a fixed fee per MMBtu of LNG (a portion of which is subject to annual adjustment for inflation) plus a variable fee per MMBtu of LNG equal to approximately 115% of Henry Hub. The customers may elect to cancel or suspend deliveries of LNG cargoes, with advance notice as governed by each respective SPA, in which case the customers would still be required to pay the fixed fee with respect to the contracted volumes that are not delivered as a result of such cancellation or suspension. We refer to the fee component that is applicable regardless of a cancellation or suspension of LNG cargo deliveries under the SPAs as the fixed fee component of the price under SPL’s SPAs. We refer to the fee component that is applicable only in connection with LNG cargo deliveries as the variable fee component of the price under SPL’s SPAs. The variable fees under SPL’s SPAs were generally sized at the time of entry into each SPA with the intent to cover the costs of gas purchases and transportation and liquefaction fuel to produce the LNG to be sold under each such SPA. The SPAs and contracted volumes to be made available under the SPAs are not tied to a specific Train; however, the term of each SPA generally commences upon the date of first commercial delivery of a specified Train.

In aggregate, the annual fixed fee portion to be paid by the third-party SPA customers is approximately $2.9 billion for Trains 1 through 5. After giving effect to an SPA that Cheniere has committed to provide to SPL by the end of 2020, the annual fixed fee portion to be paid by the third-party SPA customers would increase to at least $3.3 billion, which is expected to occur upon the date of first commercial delivery of Train 6.

In addition, Cheniere Marketing has agreements with SPL to purchase, at Cheniere Marketing’s option, any LNG produced by SPL in excess of that required for other customers. See Marketing section for additional information regarding agreements entered into by Cheniere Marketing.

Natural Gas Transportation, Storage and Supply

To ensure SPL is able to transport adequate natural gas feedstock to the Sabine Pass LNG terminal, it has entered into transportation precedent and other agreements to secure firm pipeline transportation capacity with CTPL and third-party pipeline companies. SPL has entered into firm storage services agreements with third parties to assist in managing variability in natural gas needs for the SPL Project. SPL has also entered into enabling agreements and long-term natural gas supply contracts with third parties in order to secure natural gas feedstock for the SPL Project. As of December 31, 2019, SPL had secured up to approximately 3,850 TBtu of natural gas feedstock through long-term and short-term natural gas supply contracts with remaining terms that range up to 10 years, a portion of which is subject to conditions precedent.

Construction

SPL entered into lump sum turnkey contracts with Bechtel for the engineering, procurement and construction of Trains 1 through 6 of the SPL Project, under which Bechtel charges a lump sum for all work performed and generally bears project cost,

45


schedule and performance risks unless certain specified events occur, in which case Bechtel may cause SPL to enter into a change order, or SPL agrees with Bechtel to a change order.

The total contract price of the EPC contract for Train 6 of the SPL Project is approximately $2.5 billion, including estimated costs for an optional third marine berth. As of December 31, 2019, we have incurred $1.1 billion under this contract.
Regasification Facilities
 
The Sabine Pass LNG terminal has operational regasification capacity of approximately 4 Bcf/d and aggregate LNG storage capacity of approximately 17 Bcfe. Approximately 2 Bcf/d of the regasification capacity at the Sabine Pass LNG terminal has been reserved under two long-term third-party TUAs, under which SPLNG’s customers are required to pay fixed monthly fees, whether or not they use the LNG terminal.  Each of Total and Chevron U.S.A. Inc. (“Chevron”) has reserved approximately 1 Bcf/d of regasification capacity and is obligated to make monthly capacity payments to SPLNG aggregating approximately $125 million annually, prior to inflation adjustments, for 20 years that commenced in 2009. Total S.A. has guaranteed Total’s obligations under its TUA up to $2.5 billion, subject to certain exceptions, and Chevron Corporation has guaranteed Chevron’s obligations under its TUA up to 80% of the fees payable by Chevron.

The remaining approximately 2 Bcf/d of capacity has been reserved under a TUA by SPL. SPL is obligated to make monthly capacity payments to SPLNG aggregating approximately $250 million annually, prior to inflation adjustments, continuing until at least May 2036. SPL entered into a partial TUA assignment agreement with Total, whereby upon substantial completion of Train 5 of the SPL Project, SPL gained access to substantially all of Total’s capacity and other services provided under Total’s TUA with SPLNG. This agreement provides SPL with additional berthing and storage capacity at the Sabine Pass LNG terminal that may be used to provide increased flexibility in managing LNG cargo loading and unloading activity, permit SPL to more flexibly manage its LNG storage capacity and accommodate the development of Train 6. Notwithstanding any arrangements between Total and SPL, payments required to be made by Total to SPLNG will continue to be made by Total to SPLNG in accordance with its TUA. During the years ended December 31, 2019, 2018 and 2017, SPL recorded $104 million, $30 million and $23 million, respectively, as operating and maintenance expense under this partial TUA assignment agreement.

Under each of these TUAs, SPLNG is entitled to retain 2% of the LNG delivered to the Sabine Pass LNG terminal.

Capital Resources

We currently expect that SPL’s capital resources requirements with respect to the SPL Project will be financed through project debt and borrowings, cash flows under the SPAs and equity contributions from Cheniere Partners. We believe that with the net proceeds of borrowings, available commitments under the SPL Working Capital Facility, 2019 CQP Credit Facilities, cash flows from operations and equity contributions from Cheniere Partners, SPL will have adequate financial resources available to meet its currently anticipated capital, operating and debt service requirements with respect to Trains 1 through 6 of the SPL Project. Additionally, SPLNG generates cash flows from the TUAs, as discussed above.
    
The following table provides a summary of our capital resources from borrowings and available commitments for the Sabine Pass LNG Terminal, excluding equity contributions to our subsidiaries and cash flows from operations (as described in Sources and Uses of Cash), at December 31, 2019 and 2018 (in millions):
 
 
December 31,
 
 
2019
 
2018
Senior notes (1)
 
$
17,750

 
$
16,250

Credit facilities outstanding balance (2)
 

 

Letters of credit issued (3)
 
414

 
425

Available commitments under credit facilities (3)
 
1,536

 
775

Total capital resources from borrowings and available commitments (4)
 
$
19,700

 
$
17,450

 
(1)
Includes SPL’s 5.625% Senior Secured Notes due 2021, 6.25% Senior Secured Notes due 2022, 5.625% Senior Secured Notes due 2023, 5.75% Senior Secured Notes due 2024, 5.625% Senior Secured Notes due 2025, 5.875% Senior Secured Notes due 2026 (the “2026 SPL Senior Notes”), 5.00% Senior Secured Notes due 2027 (the “2027 SPL Senior Notes”), 4.200% Senior Secured Notes due 2028 (the “2028 SPL Senior Notes”) and 5.00% Senior Secured Notes due 2037 (the “2037 SPL Senior Notes”) (collectively, the “SPL Senior Notes”), as well as CQP’s $1.5 billion of 5.250% Senior Notes

46


due 2025 (the “2025 CQP Senior Notes”), $1.1 billion of 5.625% Senior Notes due 2026 (the “2026 CQP Senior Notes”) and the 2029 CQP Senior Notes (collectively, the “CQP Senior Notes”).
(2)
Includes outstanding balances under the SPL Working Capital Facility and 2019 CQP Credit Facilities, inclusive of any portion of the 2019 CQP Credit Facilities that may be used for general corporate purposes.
(3)
Consists of SPL Working Capital Facility and 2019 CQP Credit Facilities. Balance at December 31, 2018 did not include the letters of credit issued or available commitments under the terminated 2016 CQP Credit Facilities, which were not specifically for the Sabine Pass LNG Terminal.
(4)
Does not include equity contributions that may be available from Cheniere’s borrowings under its convertible notes, which may be used for the Sabine Pass LNG Terminal.

SPL Senior Notes

The SPL Senior Notes are secured on a pari passu first-priority basis by a security interest in all of the membership interests in SPL and substantially all of SPL’s assets.

At any time prior to three months before the respective dates of maturity for each series of the SPL Senior Notes (except for the 2026 SPL Senior Notes, 2027 SPL Senior Notes, 2028 SPL Senior Notes and 2037 SPL Senior Notes, in which case the time period is six months before the respective dates of maturity), SPL may redeem all or part of such series of the SPL Senior Notes at a redemption price equal to the “make-whole” price (except for the 2037 SPL Senior Notes, in which case the redemption price is equal to the “optional redemption” price) set forth in the respective indentures governing the SPL Senior Notes, plus accrued and unpaid interest, if any, to the date of redemption. SPL may also, at any time within three months of the respective maturity dates for each series of the SPL Senior Notes (except for the 2026 SPL Senior Notes, 2027 SPL Senior Notes, 2028 SPL Senior Notes and 2037 SPL Senior Notes, in which case the time period is within six months of the respective dates of maturity), redeem all or part of such series of the SPL Senior Notes at a redemption price equal to 100% of the principal amount of such series of the SPL Senior Notes to be redeemed, plus accrued and unpaid interest, if any, to the date of redemption.

Both the indenture governing the 2037 SPL Senior Notes (the “2037 SPL Senior Notes Indenture”) and the common indenture governing the remainder of the SPL Senior Notes (the “SPL Indenture”) include restrictive covenants. SPL may incur additional indebtedness in the future, including by issuing additional notes, and such indebtedness could be at higher interest rates and have different maturity dates and more restrictive covenants than the current outstanding indebtedness of SPL, including the SPL Senior Notes and the SPL Working Capital Facility. Under the 2037 SPL Senior Notes Indenture and the SPL Indenture, SPL may not make any distributions until, among other requirements, deposits are made into debt service reserve accounts as required and a debt service coverage ratio test of 1.25:1.00 is satisfied. Semi-annual principal payments for the 2037 SPL Senior Notes are due on March 15 and September 15 of each year beginning September 15, 2025 and are fully amortizing according to a fixed sculpted amortization schedule.
    
SPL Working Capital Facility

In September 2015, SPL entered into the SPL Working Capital Facility with aggregate commitments of $1.2 billion, which was amended in May 2019 in connection with commercialization and financing of Train 6 of the SPL Project. The SPL Working Capital Facility is intended to be used for loans to SPL (“SPL Working Capital Loans”), the issuance of letters of credit on behalf of SPL, as well as for swing line loans to SPL (“SPL Swing Line Loans”), primarily for certain working capital requirements related to developing and placing into operation the SPL Project. SPL may, from time to time, request increases in the commitments under the SPL Working Capital Facility of up to $760 million and incremental increases in commitments of up to an additional $390 million. As of December 31, 2019 and 2018, SPL had $786 million and $775 million of available commitments and $414 million and $425 million aggregate amount of issued letters of credit under the SPL Working Capital Facility, respectively. SPL did not have any outstanding borrowings under the SPL Working Capital Facility as of both December 31, 2019 and 2018.

The SPL Working Capital Facility matures on December 31, 2020, and the outstanding balance may be repaid, in whole or in part, at any time without premium or penalty upon three business days’ notice. Loans deemed made in connection with a draw upon a letter of credit (“SPL LC Loans”) have a term of up to one year. SPL Swing Line Loans terminate upon the earliest of (1) the maturity date or earlier termination of the SPL Working Capital Facility, (2) the date 15 days after such SPL Swing Line Loan is made and (3) the first borrowing date for a SPL Working Capital Loan or SPL Swing Line Loan occurring at least three business days following the date the SPL Swing Line Loan is made. SPL is required to reduce the aggregate outstanding principal amount of all SPL Working Capital Loans to zero for a period of five consecutive business days at least once each year.

47


The SPL Working Capital Facility contains conditions precedent for extensions of credit, as well as customary affirmative and negative covenants. The obligations of SPL under the SPL Working Capital Facility are secured by substantially all of the assets of SPL as well as all of the membership interests in SPL on a pari passu basis with the SPL Senior Notes.

Cheniere Partners

CQP Senior Notes

The CQP Senior Notes are jointly and severally guaranteed by each of Cheniere Partners’ subsidiaries other than SPL and, subject to certain conditions governing its guarantee, Sabine Pass LP (the “CQP Guarantors”). The CQP Senior Notes are governed by the same base indenture (the “CQP Base Indenture”). The 2025 CQP Senior Notes are further governed by the First Supplemental Indenture, the 2026 CQP Senior Notes are further governed by the Second Supplemental Indenture and the 2029 CQP Senior Notes are further governed by the Third Supplemental Indenture. The indentures governing the CQP Senior Notes contain customary terms and events of default and certain covenants that, among other things, limit the ability of Cheniere Partners and the CQP Guarantors to incur liens and sell assets, enter into transactions with affiliates, enter into sale-leaseback transactions and consolidate, merge or sell, lease or otherwise dispose of all or substantially all of the applicable entity’s properties or assets.

At any time prior to October 1, 2020 for the 2025 CQP Senior Notes, October 1, 2021 for the 2026 CQP Senior Notes and October 1, 2024 for the 2029 CQP Senior Notes, Cheniere Partners may redeem all or a part of the applicable CQP Senior Notes at a redemption price equal to 100% of the aggregate principal amount of the CQP Senior Notes redeemed, plus the “applicable premium” set forth in the respective indentures governing the CQP Senior Notes, plus accrued and unpaid interest, if any, to the date of redemption. In addition, at any time prior to October 1, 2020 for the 2025 CQP Senior Notes, October 1, 2021 for the 2026 CQP Senior Notes and October 1, 2024 for the 2029 CQP Senior Notes, Cheniere Partners may redeem up to 35% of the aggregate principal amount of the CQP Senior Notes with an amount of cash not greater than the net cash proceeds from certain equity offerings at a redemption price equal to 105.250% of the aggregate principal amount of the 2025 CQP Senior Notes, 105.625% of the aggregate principal amount of the 2026 CQP Senior Notes and 104.5% of the aggregate principal amount of the 2029 CQP Senior Notes redeemed, plus accrued and unpaid interest, if any, to the date of redemption. Cheniere Partners also may at any time on or after October 1, 2020 through the maturity date of October 1, 2025 for the 2025 CQP Senior Notes, October 1, 2021 through the maturity date of October 1, 2026 for the 2026 CQP Senior Notes and October 1, 2024 through the maturity date of October 1, 2029 for the 2029 CQP Senior Notes, redeem the CQP Senior Notes, in whole or in part, at the redemption prices set forth in the respective indentures governing the CQP Senior Notes.

The CQP Senior Notes are Cheniere Partners’ senior obligations, ranking equally in right of payment with Cheniere Partners’ other existing and future unsubordinated debt and senior to any of its future subordinated debt. In the event that the aggregate amount of Cheniere Partners’ secured indebtedness and the secured indebtedness of the CQP Guarantors (other than the CQP Senior Notes or any other series of notes issued under the CQP Base Indenture) outstanding at any one time exceeds the greater of (1) $1.5 billion and (2) 10% of net tangible assets, the CQP Senior Notes will be secured to the same extent as such obligations under the 2019 CQP Credit Facilities. The obligations under the 2019 CQP Credit Facilities are secured on a first-priority basis (subject to permitted encumbrances) with liens on substantially all the existing and future tangible and intangible assets and rights of Cheniere Partners and the CQP Guarantors and equity interests in the CQP Guarantors (except, in each case, for certain excluded properties set forth in the 2019 CQP Credit Facilities). The liens securing the CQP Senior Notes, if applicable, will be shared equally and ratably (subject to permitted liens) with the holders of other senior secured obligations, which include the 2019 CQP Credit Facilities obligations and any future additional senior secured debt obligations.

2016 CQP Credit Facilities

In May 2019, Cheniere Partners terminated the remaining commitments under the 2016 CQP Credit Facilities. 

2019 CQP Credit Facilities

In May 2019, Cheniere Partners entered into the 2019 CQP Credit Facilities, which consisted of the $750 million term loan (“CQP Term Facility”), which was prepaid and terminated upon issuance of the 2029 CQP Senior Notes in September 2019, and the $750 million revolving credit facility (“CQP Revolving Facility”). Borrowings under the 2019 CQP Credit Facilities will be used to fund the development and construction of Train 6 of the SPL Project and for general corporate purposes, subject to a sublimit, and the 2019 CQP Credit Facilities are also available for the issuance of letters of credit.


48


Loans under the 2019 CQP Credit Facilities accrue interest at a variable rate per annum equal to LIBOR or the base rate (equal to the highest of the prime rate, the federal funds effective rate, as published by the Federal Reserve Bank of New York, plus 0.50%, and the adjusted one-month LIBOR plus 1.0%), plus the applicable margin. Under the CQP Revolving Facility, the applicable margin for LIBOR loans is 1.25% to 2.125% per annum, and the applicable margin for base rate loans is 0.25% to 1.125% per annum, in each case depending on the then-current rating of Cheniere Partners. Interest on LIBOR loans is due and payable at the end of each applicable LIBOR period (and at the end of every three-month period within the LIBOR period, if any), and interest on base rate loans is due and payable at the end of each calendar quarter.

Cheniere Partners pays a commitment fee equal to an annual rate of 30% of the margin for LIBOR loans multiplied by the average daily amount of the undrawn commitment, payable quarterly in arrears.

The 2019 CQP Credit Facilities mature on May 29, 2024. Any outstanding balance may be repaid, in whole or in part, at any time without premium or penalty, except for interest rate breakage costs. The 2019 CQP Credit Facilities contain conditions precedent for extensions of credit, as well as customary affirmative and negative covenants, and limit Cheniere Partners’ ability to make restricted payments, including distributions, to once per fiscal quarter and one true-up per fiscal quarter as long as certain conditions are satisfied.
The 2019 CQP Credit Facilities are unconditionally guaranteed and secured by a first priority lien (subject to permitted encumbrances) on substantially all of Cheniere Partners’ and the CQP Guarantors’ existing and future tangible and intangible assets and rights and equity interests in the CQP Guarantors (except, in each case, for certain excluded properties set forth in the 2019 CQP Credit Facilities).

Corpus Christi LNG Terminal

Liquefaction Facilities

We are currently operating two Trains and one marine berth at the CCL Project and are constructing one additional Train and marine berth. We have received authorization from the FERC to site, construct and operate Trains 1 through 3 of the CCL Project. We completed construction of Trains 1 and 2 of the CCL Project and commenced commercial operating activities in February 2019 and August 2019, respectively. The following table summarizes the project completion and construction status of Train 3 of the CCL Project, including the related infrastructure, as of December 31, 2019:
 
 
CCL Train 3
Overall project completion percentage
 
74.8%
Completion percentage of:
 
 
Engineering
 
98.7%
Procurement
 
99.5%
Subcontract work
 
28.3%
Construction
 
49.5%
Expected date of substantial completion
 
1H 2021

Separate from the CCH Group, we are also developing Corpus Christi Stage 3 through our subsidiary CCL Stage III, adjacent to the CCL Project. We received approval from FERC in November 2019 to site, construct and operate seven midscale Trains with an expected total production capacity of approximately 10 mtpa of LNG.

The following orders have been issued by the DOE authorizing the export of domestically produced LNG by vessel from the Corpus Christi LNG terminal:
CCL Project—FTA countries for a 25-year term and to non-FTA countries for a 20-year term, both of which commenced in June 2019, up to a combined total of the equivalent of 767 Bcf/yr (approximately 15 mtpa) of natural gas.
Corpus Christi Stage 3FTA countries for a 25-year term and to non-FTA countries for a 20-year term in an amount equivalent to 582.14 Bcf/yr (approximately 11 mtpa) of natural gas.

In each case, the terms of these authorizations begin on the earlier of the date of first export thereunder or the date specified in the particular order, which ranges from seven to 10 years from the date the order was issued.


49


An application was filed in September 2019 to authorize additional exports from the CCL Project to FTA countries for a 25-year term and to non-FTA countries for a 20-year term in an amount up to the equivalent of approximately 108 Bcf/yr of natural gas, for a total CCL Project export of 875.16 Bcf/yr. The terms of the authorizations are requested to commence on the date of first commercial export from the CCL Project of the volumes contemplated in the application. The application is currently pending before DOE.

Customers

CCL has entered into fixed price long-term SPAs generally with terms of 20 years (plus extension rights) with nine third parties for Trains 1 through 3 of the CCL Project. Under these SPAs, the customers will purchase LNG from CCL on a FOB basis for a price consisting of a fixed fee per MMBtu of LNG (a portion of which is subject to annual adjustment for inflation) plus a variable fee per MMBtu of LNG equal to approximately 115% of Henry Hub. The customers may elect to cancel or suspend deliveries of LNG cargoes, with advance notice as governed by each respective SPA, in which case the customers would still be required to pay the fixed fee with respect to the contracted volumes that are not delivered as a result of such cancellation or suspension. We refer to the fee component that is applicable regardless of a cancellation or suspension of LNG cargo deliveries under the SPAs as the fixed fee component of the price under our SPAs. We refer to the fee component that is applicable only in connection with LNG cargo deliveries as the variable fee component of the price under our SPAs. The variable fee under CCL’s SPAs entered into in connection with the development of the CCL Project was sized at the time of entry into each SPA with the intent to cover the costs of gas purchases and transportation and liquefaction fuel to produce the LNG to be sold under each such SPA. The SPAs and contracted volumes to be made available under the SPAs are not tied to a specific Train; however, the term of each SPA generally commences upon the date of first commercial delivery for the applicable Train, as specified in each SPA.

In aggregate, the minimum fixed fee portion to be paid by the third-party SPA customers is approximately $550 million for Train 1, increasing to approximately $1.4 billion upon the date of first commercial delivery for Train 2 and further increasing to approximately $1.8 billion following the substantial completion of Train 3 of the CCL Project.

In addition, Cheniere Marketing has agreements with CCL to purchase: (1) 15 TBtu per annum of LNG with an approximate term of 23 years, (2) any LNG produced by CCL in excess of that required for other customers at Cheniere Marketing’s option and (3) 0.85 mtpa of LNG with a term of up to seven years associated with the IPM gas supply agreement between CCL and EOG. See Marketing section for additional information regarding agreements entered into by Cheniere Marketing.

Natural Gas Transportation, Storage and Supply

To ensure CCL is able to transport adequate natural gas feedstock to the Corpus Christi LNG terminal, it has entered into transportation precedent agreements to secure firm pipeline transportation capacity with CCP and certain third-party pipeline companies. CCL has entered into a firm storage services agreement with a third party to assist in managing variability in natural gas needs for the CCL Project. CCL has also entered into enabling agreements and long-term natural gas supply contracts with third parties, and will continue to enter into such agreements, in order to secure natural gas feedstock for the CCL Project. As of December 31, 2019, CCL had secured up to approximately 2,999 TBtu of natural gas feedstock through long-term natural gas supply contracts with remaining terms that range up to eight years, a portion of which is subject to the achievement of certain project milestones and other conditions precedent.
CCL Stage III has also entered into long-term natural gas supply contracts with third parties, and anticipates continuing to enter into such agreements, in order to secure natural gas feedstock for Corpus Christi Stage 3. As of December 31, 2019, CCL Stage III had secured up to approximately 2,361 TBtu of natural gas feedstock through long-term natural gas supply contracts with remaining terms that range up to approximately 15 years, which is subject to the achievement of certain project milestones and other conditions precedent.

A portion of the natural gas feedstock transactions for CCL and CCL Stage III are IPM transactions, in which the natural gas producers are paid based on a global gas market price less a fixed liquefaction fee and certain costs incurred by us.

Construction

CCL entered into separate lump sum turnkey contracts with Bechtel for the engineering, procurement and construction of Trains 1 through 3 of the CCL Project under which Bechtel charges a lump sum for all work performed and generally bears project

50


cost, schedule and performance risks unless certain specified events occur, in which case Bechtel may cause CCL to enter into a change order, or CCL agrees with Bechtel to a change order.

The total contract price of the EPC contract for Train 3, which is currently under construction, is approximately $2.4 billion, reflecting amounts incurred under change orders through December 31, 2019. As of December 31, 2019, we have incurred $2.0 billion under this contract.

Final Investment Decision for Corpus Christi Stage 3

FID for Corpus Christi Stage 3 will be subject to, among other things, entering into an EPC contract, obtaining additional commercial support for the project and securing the necessary financing arrangements.
    
Pipeline Facilities

In December 2014, the FERC issued a certificate of public convenience and necessity under Section 7(c) of the Natural Gas Act of 1938, as amended, authorizing CCP to construct and operate the Corpus Christi Pipeline. The Corpus Christi Pipeline is designed to transport 2.25 Bcf/d of natural gas feedstock required by the CCL Project from the existing regional natural gas pipeline grid. The construction of the Corpus Christi Pipeline was completed in the second quarter of 2018.

In November 2019, the FERC authorized CCP to construct and operate the pipeline for Corpus Christi Stage 3. The pipeline will be designed to transport 1.5 Bcf/d of natural gas feedstock required by Corpus Christi Stage 3 from the existing regional natural gas pipeline grid.

Capital Resources

The CCH Group expects to finance the construction costs of the CCL Project from one or more of the following: operating cash flows from CCL and CCP, project debt and equity contributions from Cheniere. The following table provides a summary of the capital resources of the CCH Group from borrowings and available commitments for the CCL Project, excluding equity contributions from Cheniere, at December 31, 2019 and 2018 (in millions):
 
 
December 31,
 
 
2019
 
2018
Senior notes (1)
 
$
6,952

 
$
4,250

11.0% Convertible Senior Secured Notes due 2025 (2)
 
1,000

 
1,000

Credit facilities outstanding balance (3)
 
3,283

 
5,324

Letters of credit issued (3)
 
471

 
316

Available commitments under credit facilities (3)
 
729

 
1,698

Total capital resources from borrowings and available commitments (4)
 
$
12,435

 
$
12,588

 
(1)
Includes CCH’s 7.000% Senior Secured Notes due 2024 (the “2024 CCH Senior Notes”), 5.875% Senior Secured Notes due 2025 (the “2025 CCH Senior Notes”), 5.125% Senior Secured Notes due 2027 (the “2027 CCH Senior Notes”), 2029 CCH Senior Notes, 4.80% CCH Senior Notes and 3.925% CCH Senior Notes (collectively, the “CCH Senior Notes”).
(2)
Aggregate original principal amount before debt discount and debt issuance costs.
(3)
Includes CCH Credit Facility and CCH Working Capital Facility.
(4)
Does not include equity contributions that may be available from Cheniere’s borrowings under the 2021 Cheniere Convertible Unsecured Notes, 2045 Cheniere Convertible Senior Notes and Cheniere Revolving Credit Facility, which may be used for the CCL Project.

2025 CCH HoldCo II Convertible Senior Notes

In May 2015, CCH HoldCo II issued $1.0 billion aggregate principal amount of 11.0% Convertible Senior Secured Notes due 2025 (the “2025 CCH HoldCo II Convertible Senior Notes”) on a private placement basis. The 2025 CCH HoldCo II Convertible Senior Notes are convertible at the option of CCH HoldCo II or the holders on or after March 1, 2020 and September 1, 2020, respectively, provided the total market capitalization of Cheniere at that time is not less than $10.0 billion and certain other conditions are satisfied. CCH HoldCo II is restricted from making distributions to Cheniere under agreements governing its

51


indebtedness generally until, among other requirements, a historical debt service coverage ratio and a projected fixed debt service coverage ratio of 1.20:1.00 are achieved. The 2025 CCH HoldCo II Convertible Senior Notes are secured by a pledge by us of 100% of the equity interests in CCH HoldCo II, and a pledge by CCH HoldCo II of 100% of the equity interests in CCH HoldCo I. In addition, the 2025 CCH HoldCo II Convertible Senior Notes are secured by a security interest in the account into which all distributions from CCH HoldCo I to CCH HoldCo II must be deposited.

In May 2018, the amended and restated note purchase agreement under which the 2025 CCH HoldCo II Convertible Senior Notes were issued was subsequently amended in connection with commercialization and financing of Train 3 of the CCL Project and to provide the note holders with certain prepayment rights related thereto consistent with those under the CCH Credit Facility.  All terms of the 2025 CCH HoldCo II Convertible Senior Notes substantially remained unchanged.

CCH Senior Notes

The CCH Senior Notes are jointly and severally guaranteed by CCH’s subsidiaries, CCL, CCP and Corpus Christi Pipeline GP, LLC (each a “CCH Guarantor” and collectively, the “CCH Guarantors”). The indentures governing the CCH Senior Notes contain customary terms and events of default and certain covenants that, among other things, limit CCH’s ability and the ability of CCH’s restricted subsidiaries to: incur additional indebtedness or issue preferred stock; make certain investments or pay dividends or distributions on membership interests or subordinated indebtedness or purchase, redeem or retire membership interests; sell or transfer assets, including membership or partnership interests of CCH’s restricted subsidiaries; restrict dividends or other payments by restricted subsidiaries to CCH or any of CCH’s restricted subsidiaries; incur liens; enter into transactions with affiliates; dissolve, liquidate, consolidate, merge, sell or lease all or substantially all of the properties or assets of CCH and its restricted subsidiaries taken as a whole; or permit any CCH Guarantor to dissolve, liquidate, consolidate, merge, sell or lease all or substantially all of its properties and assets. The covenants included in the respective indentures that govern the CCH Senior Notes are subject to a number of important limitations and exceptions.

The CCH Senior Notes are CCH’s senior secured obligations, ranking senior in right of payment to any and all of CCH’s future indebtedness that is subordinated to the CCH Senior Notes and equal in right of payment with CCH’s other existing and future indebtedness that is senior and secured by the same collateral securing the CCH Senior Notes. The CCH Senior Notes are secured by a first-priority security interest in substantially all of CCH’s and the CCH Guarantors’ assets.

At any time prior to six months before the respective dates of maturity for each of the CCH Senior Notes, CCH may redeem all or part of such series of the CCH Senior Notes at a redemption price equal to the “make-whole” price set forth in the appropriate indenture, plus accrued and unpaid interest, if any, to the date of redemption. At any time within six months of the respective dates of maturity for each of the CCH Senior Notes, CCH may redeem all or part of such series of the CCH Senior Notes, in whole or in part, at a redemption price equal to 100% of the principal amount of the CCH Senior Notes to be redeemed, plus accrued and unpaid interest, if any, to the date of redemption.
CCH Credit Facility

In May 2018, CCH amended and restated the CCH Credit Facility to increase total commitments under the CCH Credit Facility from $4.6 billion to $6.1 billion. The obligations of CCH under the CCH Credit Facility are secured by a first priority lien on substantially all of the assets of CCH and its subsidiaries and by a pledge by CCH HoldCo I of its limited liability company interests in CCH. As of December 31, 2019 and 2018, CCH had zero and $1.0 billion of available commitments and $3.3 billion and $5.2 billion of loans outstanding under the CCH Credit Facility, respectively. As part of the capital allocation framework announced in June 2019, we prepaid $153 million of outstanding borrowings under the CCH Credit Facility during the year ended December 31, 2019.

The CCH Credit Facility matures on June 30, 2024, with principal payments due quarterly commencing on the earlier of (1) the first quarterly payment date occurring more than three calendar months following the completion of the CCL Project as defined in the common terms agreement and (2) a set date determined by reference to the date under which a certain LNG buyer linked to the last Train of the CCL Project to become operational is entitled to terminate its SPA for failure to achieve the date of first commercial delivery for that agreement. Scheduled repayments will be based upon a 19-year tailored amortization, commencing the first full quarter after the completion of Trains 1 through 3 and designed to achieve a minimum projected fixed debt service coverage ratio of 1.50:1.


52


Under the CCH Credit Facility, CCH is required to hedge not less than 65% of the variable interest rate exposure of its senior secured debt. CCH is restricted from making certain distributions under agreements governing its indebtedness generally until, among other requirements, the completion of the construction of Trains 1 through 3 of the CCL Project, funding of a debt service reserve account equal to six months of debt service and achieving a historical debt service coverage ratio and fixed projected debt service coverage ratio of at least 1.25:1.00.
CCH Working Capital Facility

In June 2018, CCH amended and restated the CCH Working Capital Facility to increase total commitments under the CCH Working Capital Facility from $350 million to $1.2 billion. The CCH Working Capital Facility is intended to be used for loans to CCH (“CCH Working Capital Loans”) and the issuance of letters of credit on behalf of CCH for certain working capital requirements related to developing and operating the CCL Project and for related business purposes. Loans under the CCH Working Capital Facility are guaranteed by the CCH Guarantors. CCH may, from time to time, request increases in the commitments under the CCH Working Capital Facility of up to the maximum allowed for working capital under the Common Terms Agreement that was entered into concurrently with the CCH Credit Facility. As of December 31, 2019 and 2018, CCH had $729 million and $716 million of available commitments, $471 million and $316 million aggregate amount of issued letters of credit and zero and $168 million of loans outstanding under the CCH Working Capital Facility, respectively.

The CCH Working Capital Facility matures on June 29, 2023, and CCH may prepay the CCH Working Capital Loans and loans made in connection with a draw upon any letter of credit (“CCH LC Loans”) at any time without premium or penalty upon three business days’ notice and may re-borrow at any time. CCH LC Loans have a term of up to one year. CCH is required to reduce the aggregate outstanding principal amount of all CCH Working Capital Loans to zero for a period of five consecutive business days at least once each year.

The CCH Working Capital Facility contains conditions precedent for extensions of credit, as well as customary affirmative and negative covenants. The obligations of CCH under the CCH Working Capital Facility are secured by substantially all of the assets of CCH and the CCH Guarantors as well as all of the membership interests in CCH and each of the CCH Guarantors on a pari passu basis with the CCH Senior Notes and the CCH Credit Facility.

Cheniere

Convertible Notes

In November 2014, we issued an aggregate principal amount of $1.0 billion of Convertible Unsecured Notes due 2021 (the “2021 Cheniere Convertible Unsecured Notes”). The 2021 Cheniere Convertible Unsecured Notes are convertible at the option of the holder into our common stock at the then applicable conversion rate, provided that the closing price of our common stock is greater than or equal to the conversion price on the date of conversion. In March 2015, we issued $625 million aggregate principal amount of unsecured 4.25% Convertible Senior Notes due 2045 (the “2045 Cheniere Convertible Senior Notes”). We have the right, at our option, at any time after March 15, 2020, to redeem all or any part of the 2045 Cheniere Convertible Senior Notes at a redemption price equal to the accreted amount of the 2045 Cheniere Convertible Senior Notes to be redeemed, plus accrued and unpaid interest, if any, to such redemption date. We have the option to satisfy the conversion obligation for the 2021 Cheniere Convertible Unsecured Notes and the 2045 Cheniere Convertible Senior Notes with cash, common stock or a combination thereof.

Cheniere Revolving Credit Facility

In December 2018, we amended and restated the Cheniere Revolving Credit Facility to increase total commitments under the Cheniere Revolving Credit Facility from $750 million to $1.25 billion. The Cheniere Revolving Credit Facility is intended to fund, through loans and letters of credit, equity capital contributions to CCH HoldCo II and its subsidiaries for the development of the CCL Project and, provided that certain conditions are met, for general corporate purposes.

The Cheniere Revolving Credit Facility matures on December 13, 2022 and contains representations, warranties and affirmative and negative covenants customary for companies like us with lenders of the type participating in the Cheniere Revolving Credit Facility that limit our ability to make restricted payments, including distributions, unless certain conditions are satisfied, as well as limitations on indebtedness, guarantees, hedging, liens, investments and affiliate transactions. Under the Cheniere Revolving Credit Facility, we are required to ensure that the sum of our unrestricted cash and the amount of undrawn commitments

53


under the Cheniere Revolving Credit Facility is at least equal to the lesser of (1) 20% of the commitments under the Cheniere Revolving Credit Facility and (2) $200 million (the “Liquidity Covenant”).

From and after the time at which certain specified conditions are met (the “Trigger Point”), we will have increased flexibility under the Cheniere Revolving Credit Facility to, among other things, (1) make restricted payments and (2) raise incremental commitments. The Trigger Point will occur once (1) completion has occurred for each of Train 1 of the CCL Project (as defined in the CCH Indenture) and Train 5 of the SPL Project (as defined in SPL’s common terms agreement), which has occurred in February 2019 and March 2019, respectively; (2) the aggregate principal amount of outstanding loans plus drawn and unreimbursed letters of credit under the Cheniere Revolving Credit Facility is less than or equal to 10% of aggregate commitments under the Cheniere Revolving Credit Facility and (3) we elect on a go-forward basis to be governed by a non-consolidated leverage ratio covenant not to exceed 5.75:1.00 (the “Springing Leverage Covenant”), which following such election will apply at any time that the aggregate principal amount of outstanding loans plus drawn and unreimbursed letters of credit under the Cheniere Revolving Credit Facility is greater than 30% of aggregate commitments under the Cheniere Revolving Credit Facility. Following the Trigger Point, at any time that the Springing Leverage Covenant is in effect, the Liquidity Covenant will not apply.

The Cheniere Revolving Credit Facility is secured by a first priority security interest (subject to permitted liens and other customary exceptions) in substantially all of our assets, including our interests in our direct subsidiaries (excluding CCH HoldCo II and certain other subsidiaries).

Cash Receipts from Subsidiaries

Our ownership interest in the Sabine Pass LNG terminal is held through Cheniere Partners. As of December 31, 2019, we owned a 48.6% limited partner interest in Cheniere Partners in the form of 104.5 million common units and 135.4 million subordinated units. We also own 100% of the general partner interest and the incentive distribution rights in Cheniere Partners. We are eligible to receive quarterly equity distributions from Cheniere Partners related to our ownership interests and our incentive distribution rights.

We also receive fees for providing management services to some of our subsidiaries. We received $103 million, $76 million and $106 million in total service fees from these subsidiaries during the years ended December 31, 2019, 2018 and 2017, respectively.

Share Repurchase Program

On June 3, 2019, we announced that our Board authorized a 3-year, $1.0 billion share repurchase program. During the year ended December 31, 2019, we repurchased an aggregate of 4.0 million shares of our common stock for $249 million, for a weighted average price per share of $62.27. As of December 31, 2019, we had up to $751 million of the share repurchase program available. Under the share repurchase program, repurchases can be made from time to time using a variety of methods, which may include open market purchases, privately negotiated transactions or otherwise, all in accordance with the rules of the SEC and other applicable legal requirements. The timing and amount of any shares of our common stock that are repurchased under the share repurchase program will be determined by our management based on market conditions and other factors.  The share repurchase program does not obligate us to acquire any particular amount of common stock, and may be modified, suspended or discontinued at any time or from time to time at our discretion.

Marketing

We market and sell LNG produced by the Liquefaction Projects that is not required for other customers through our integrated marketing function. We have, and continue to develop, a portfolio of long-, medium- and short-term SPAs to transport and unload commercial LNG cargoes to locations worldwide. These volumes are expected to be primarily sourced by LNG produced by the Liquefaction Projects but supplemented by volumes procured from other locations worldwide, as needed. As of December 31, 2019, we have sold or have options to sell approximately 4,935 TBtu of LNG to be delivered to customers between 2020 and 2045, excluding volumes for agreements anticipated to be assigned to SPL in the future.  The cargoes have been sold either on a FOB basis (delivered to the customer at the Sabine Pass LNG terminal or the Corpus Christi LNG terminal, as applicable) or a delivered at terminal (“DAT”) basis (delivered to the customer at their LNG receiving terminal). We have chartered LNG vessels to be utilized for cargoes sold on a DAT basis. In addition, we have entered into a long-term agreement to sell LNG cargoes on a DAT basis that is conditioned upon the buyer achieving certain milestones.


54


Cheniere Marketing entered into uncommitted trade finance facilities with available commitments of $420 million as of December 31, 2019, primarily to be used for the purchase and sale of LNG for ultimate resale in the course of its operations. The finance facilities are intended to be used for advances, guarantees or the issuance of letters of credit or standby letters of credit on behalf of Cheniere Marketing. As of December 31, 2019 and 2018, Cheniere Marketing had $41 million and $31 million, respectively, in standby letters of credit and guarantees outstanding under the finance facilities. As of December 31, 2018, Cheniere Marketing had $71 million in loans outstanding under the finance facilities. As of December 31, 2019, there were no loans outstanding under the finance facilities. Cheniere Marketing pays interest or fees on utilized commitments.

Corporate and Other Activities
 
We are required to maintain corporate and general and administrative functions to serve our business activities described above.  The development of our sites or other projects, including infrastructure projects in support of natural gas supply and LNG demand, will require, among other things, acceptable commercial and financing arrangements before we make an FID.
 
We have made an equity investment in Midship Holdings, LLC (“Midship Holdings”), which manages the business and affairs of Midship Pipeline. Midship Pipeline is constructing the Midship Project with expected capacity of up to 1.44 million Dekatherms per day that will connect new gas production in the Anadarko Basin to Gulf Coast markets, including markets serving the Liquefaction Projects. Construction of the Midship Project commenced in the first quarter of 2019 and is expected to be completed in the first half of 2020.

Restrictive Debt Covenants

As of December 31, 2019, each of our issuers was in compliance with all covenants related to their respective debt agreements.

LIBOR

The use of LIBOR is expected to be phased out by the end of 2021. It is currently unclear whether LIBOR will be utilized beyond that date or whether it will be replaced by a particular rate. We intend to continue to work with our lenders to pursue any amendments to our debt agreements that are currently subject to LIBOR and will continue to monitor, assess and plan for the phase out of LIBOR.

Sources and Uses of Cash

The following table summarizes the sources and uses of our cash, cash equivalents and restricted cash for the years ended December 31, 2019, 2018 and 2017 (in millions). The table presents capital expenditures on a cash basis; therefore, these amounts differ from the amounts of capital expenditures, including accruals, which are referred to elsewhere in this report. Additional discussion of these items follows the table. 
 
Year Ended December 31,
 
2019
 
2018
 
2017
Operating cash flows
$
1,833

 
$
1,990

 
$
1,231

Investing cash flows
(3,163
)
 
(3,654
)
 
(3,381
)
Financing cash flows
1,168

 
2,207

 
2,936

 
 
 
 
 
 
Net increase (decrease) in cash, cash equivalents and restricted cash
(162
)

543

 
786

Cash, cash equivalents and restricted cash—beginning of period
3,156

 
2,613

 
1,827

Cash, cash equivalents and restricted cash—end of period
$
2,994

 
$
3,156

 
$
2,613


Operating Cash Flows

Our operating cash net inflows during the years ended December 31, 2019, 2018 and 2017 were $1,833 million, $1,990 million and $1,231 million, respectively. The $157 million decrease in operating cash inflows in 2019 compared to 2018 was primarily related to increased operating costs and expenses, which were partially offset by increased cash receipts from the sale of LNG cargoes, as a result of the additional Trains that were operating at the Liquefaction Projects in 2019. The $759 million increase in operating cash inflows in 2018 compared to 2017 was primarily related to increased cash receipts from the sale of LNG cargoes, partially offset by increased operating costs and expenses as a result of the additional Trains that were operating at the SPL Project in 2018.

55


Investing Cash Flows

Investing cash net outflows during the years ended December 31, 2019, 2018 and 2017 were $3,163 million, $3,654 million and $3,381 million, respectively, and were primarily used to fund the construction costs for the Liquefaction Projects. These costs are capitalized as construction-in-process until achievement of substantial completion. Additionally, we invested $105 million in Midship Holdings, our equity method investment, during the year ended December 31, 2019. During the year ended December 31, 2018, we invested an additional $25 million in our equity method investment Midship Holdings, offset primarily by proceeds of $12 million from the sale of our other investments. During the year ended December 31, 2017, we invested an additional $41 million in Midship Holdings and made payments of $19 million, primarily for infrastructure to support the CCL Project and other capital projects. Partially offsetting these cash outflows during the year ended December 31, 2017 was a $36 million receipt from the return of collateral payments previously paid for the CCL Project.

Financing Cash Flows

Financing cash net inflows during the year ended December 31, 2019 were $1,168 million, primarily as a result of:
issuance of an aggregate principal amount of $1.5 billion of the 2029 CQP Senior Notes, which was used to prepay the outstanding balance of the term loan under the 2019 CQP Credit Facilities;
issuance of an aggregate principal amount of $1.5 billion of the 2029 CCH Senior Notes, $727 million of the 4.80% CCH Senior Notes and $475 million of the 3.925% CCH Senior Notes, which were used to prepay a portion of the outstanding balance of the CCH Credit Facility;
$51 million of debt issuance costs primarily related to up-front fees paid upon the closing of the above transactions;
$15 million of debt extinguishment cost related to the issuance of the 2029 CQP Senior Notes and the 2029 CCH Senior Notes;
$982 million of borrowings and $2,855 million of repayments under the CCH Credit Facility;
$730 million of borrowings and repayments under the 2019 CQP Credit Facilities;
$521 million of borrowings and $689 million in repayments under the CCH Working Capital Facility;
$72 million of net repayments related to our Cheniere Marketing trade financing facilities;
$590 million of distributions to non-controlling interest by Cheniere Partners;
$249 million paid to repurchase approximately 4 million shares of our common stock under the share repurchase program; and
$19 million paid for tax withholdings for share-based compensation.

Financing cash net inflows during the year ended December 31, 2018 were $2,207 million, primarily as a result of:
issuance of an aggregate principal amount of $1.1 billion of the 2026 CQP Senior Notes, which was used to prepay $1.1 billion of the outstanding borrowings under the 2016 CQP Credit Facilities;
$2.9 billion of borrowings and $281 million in repayments under the CCH Credit Facility;
$188 million of borrowings and $20 million in repayments under the CCH Working Capital Facility;
$71 million of net borrowings related to our Cheniere Marketing trade financing facilities;
$66 million of debt issuance costs related to up-front fees paid upon the closing of these transactions;
$17 million in debt extinguishment costs related to the prepayments of the 2016 CQP Credit Facilities and the CCH Credit Facility;
$576 million of distributions and dividends to non-controlling interest by Cheniere Partners and Cheniere Holdings;
$20 million paid for tax withholdings for share-based compensation; and
$7 million of transaction costs to acquire additional interest of Cheniere Holdings.


56


Financing cash net inflows during the year ended December 31, 2017 were $2,936 million, primarily as a result of:
issuances of SPL’s senior notes for an aggregate principal amount $2.15 billion;
$55 million of borrowings and $369 million of repayments made under the credit facilities SPL entered into in June 2015 (the “SPL Credit Facilities”);
$110 million of borrowings and $334 million of repayments made under the SPL Working Capital Facility;
$1.5 billion of borrowings under the CCH Credit Facility;
issuance of an aggregate principal amount of $1.5 billion of the 2027 CCH Senior Notes, which was used to prepay $1.4 billion of outstanding borrowings under the CCH Credit Facility;
$24 million of borrowings and $24 million of repayments made under the CCH Working Capital Facility;
issuance of an aggregate principal amount of $1.5 billion of the 2025 CQP Senior Notes, which was used to prepay $1.5 billion of the outstanding borrowings under the 2016 CQP Credit Facilities;
$24 million in net repayments made under the Cheniere Marketing trade finance facilities;
$89 million of debt issuance and deferred financing costs related to up-front fees paid upon the closing of these transactions;
$185 million of distributions and dividends to non-controlling interest by Cheniere Partners and Cheniere Holdings; and
$12 million paid for tax withholdings for share-based compensation.

Contractual Obligations
 
We are committed to make cash payments in the future pursuant to certain of our contracts. The following table summarizes certain contractual obligations in place as of December 31, 2019 (in millions):
 
 
Payments Due By Period (1)
 
 
Total
 
2020
 
2021 - 2022
 
2023 - 2024
 
Thereafter
Debt (2)
 
$
30,610

 
$

 
$
4,253

 
$
7,779

 
$
18,578

Interest payments (2)
 
11,315

 
1,633

 
3,419

 
2,612

 
3,651

Operating lease obligations (3)
 
530

 
250

 
78

 
42

 
160

Finance lease obligations (4)
 
187

 
11

 
20

 
20

 
136

Purchase obligations: (5)
 


 
 
 
 
 
 
 
 
Construction obligations (6)
 
1,301

 
726

 
534

 
41

 

Natural gas supply, transportation and storage service agreements (7)
 
13,468

 
3,503

 
3,943

 
2,035

 
3,987

Other purchase obligations (8)
 
1,658

 
224

 
299

 
298

 
837

Total
 
$
59,069


$
6,347


$
12,546


$
12,827


$
27,349

 
(1)
Agreements in force as of December 31, 2019 that have terms dependent on project milestone dates are based on the estimated dates as of December 31, 2019.
(2)
Based on the total debt balance, scheduled maturities and fixed or estimated forward interest rates in effect at December 31, 2019.  The repayment of paid in kind interest is included in interest payments. Interest payment obligations exclude adjustments for interest rate swap agreements. A discussion of our debt obligations can be found in Note 11—Debt of our Notes to Consolidated Financial Statements.
(3)
Operating lease obligations primarily relate to LNG vessel time charters, land sites related to the Liquefaction Projects and corporate office leases. Operating lease obligations do not include $2.0 billion of legally binding minimum lease payments for vessel charters which were executed as of December 31, 2019 but will commence between 2020 and 2022 and have fixed minimum lease terms of up to seven years. A discussion of our lease obligations can be found in Note 12—Leases of our Notes to Consolidated Financial Statements.
(4)
Finance lease obligations consist of tug leases related to the CCL Project, as further discussed in Note 12—Leases of our Notes to Consolidated Financial Statements.

57


(5)
Purchase obligations consist of agreements to purchase goods or services that are enforceable and legally binding that specify fixed or minimum quantities to be purchased. We include only contracts for which conditions precedent have been met. As project milestones and other conditions precedent are achieved, our obligations are expected to increase accordingly. We include contracts for which we have an early termination option if the option is not expected to be exercised.
(6)
Construction obligations primarily consist of the estimated remaining cost pursuant to our EPC contracts as of December 31, 2019 for Trains with respect to which we have made an FID to commence construction. A discussion of these obligations can be found at Note 19—Commitments and Contingencies of our Notes to Consolidated Financial Statements.
(7)
Pricing of natural gas supply agreements are based on estimated forward prices and basis spreads as of December 31, 2019.
(8)
Other purchase obligations primarily relate to payments under SPL’s partial TUA assignment agreement with Total as discussed in Note 13—Revenues from Contracts with Customers of our Notes to Consolidated Financial Statements.
In addition, as of December 31, 2019, we had $1,470 million aggregate amount of issued letters of credit under our credit facilities. We also had tax agreements with certain local taxing jurisdictions for an aggregate amount of $212 million to be paid through 2033, based on estimated tax obligations as of December 31, 2019.


58


Results of Operations

The following charts summarize the number of Trains that were in operation during the years ended December 31, 2019, 2018 and 2017 and total revenues and total LNG volumes loaded (including both operational and commissioning volumes) for the respective periods:
chart-6487a76e9c0ab3be367a07.jpg
chart-2a42d92e7759c23ef3ba07.jpgchart-62c08b85d09a6223e2aa07.jpg
The following table summarizes the volumes of operational and commissioning LNG cargoes that were loaded from the Liquefaction Projects, which were recognized on our Consolidated Financial Statements during the year ended December 31, 2019:
 
Year Ended December 31, 2019
(in TBtu)
Operational
 
Commissioning
Volumes loaded during the current period
1,466

 
48

Volumes loaded during the prior period but recognized during the current period
25

 
3

Less: volumes loaded during the current period and in transit at the end of the period
(33
)
 

Total volumes recognized in the current period
1,458

 
51


Our consolidated net income attributable to common stockholders was $648 million, or $2.53 per share—basic and $2.51 per share—diluted, in the year ended December 31, 2019, compared to net income attributable to common stockholders of $471 million, or $1.92 per share—basic and $1.90 per share—diluted, in the year ended December 31, 2018. This $177 million increase

59


in net income attributable to common stockholders in 2019 was primarily attributable to (1) increased gross margins due to increased volume of LNG sold partially offset by decreased pricing on LNG, (2) increased tax benefit from the release of a significant portion of the valuation allowance previously recorded against our deferred tax assets, (3) increased LNG revenues as a result of derivative gains on commodity derivatives and (4) decreased net income attributable to non-controlling interest, which were partially offset by an increase in (1) interest expense, net of amounts capitalized, (2) operating and maintenance expense, (3) derivative loss, net, associated with our interest rate derivatives, (4) depreciation and amortization expense and (5) loss on equity method investments.
Our consolidated net loss attributable to common stockholders was $393 million, or $1.68 per share (basic and diluted), in the year ended December 31, 2017. This $864 million increase in net income in 2018 compared to 2017 was primarily attributable to (1) increased income from operations due to additional Trains operating between the periods, (2) decreased loss on modification or extinguishment of debt and (3) increased derivative gain, net, which were partially offset by decreased net income attributable to non-controlling interest and increased interest expense, net of amounts capitalized.

We enter into derivative instruments to manage our exposure to (1) changing interest rates, (2) commodity-related marketing and price risks and (3) foreign exchange volatility. Derivative instruments are reported at fair value on our Consolidated Financial Statements. In some cases, the underlying transactions economically hedged receive accrual accounting treatment, whereby revenues and expenses are recognized only upon delivery, receipt or realization of the underlying transaction. Because the recognition of derivative instruments at fair value has the effect of recognizing gains or losses relating to future period exposure, use of derivative instruments may increase the volatility of our results of operations based on changes in market pricing, counterparty credit risk and other relevant factors.

Revenues
 
Year Ended December 31,
(in millions)
2019
 
2018
 
Change
 
2017
 
Change
LNG revenues
$
9,246

 
$
7,572

 
$
1,674

 
$
5,317

 
$
2,255

Regasification revenues
266

 
261

 
5

 
260

 
1

Other revenues
218

 
154

 
64

 
24

 
130

Total revenues
$
9,730


$
7,987


$
1,743

 
$
5,601

 
$
2,386


2019 vs. 2018 and 2018 vs. 2017

We begin recognizing LNG revenues from the Liquefaction Projects following the substantial completion and the commencement of operating activities of the respective Trains. The increase in revenues during each of the years was primarily attributable to the increased volume of LNG sold following the achievement of substantial completion of these Trains. The increase in revenue attributable to LNG volume sold during the year ended December 31, 2019 from the comparable period in 2018 was partially offset by decreased LNG revenues per MMBtu, which was primarily affected by market prices realized for volumes sold by our integrated marketing function. Additionally, the increase in other revenues during each of the years was due to an increase in sub-chartering income. We expect our LNG revenues to increase in the future upon Train 6 of the SPL Project and Train 3 of the CCL Project becoming operational, in addition to full year operation of the Trains that were completed during 2019.

Prior to substantial completion of a Train, amounts received from the sale of commissioning cargoes from that Train are offset against LNG terminal construction-in-process, because these amounts are earned or loaded during the testing phase for the construction of that Train. During the years ended December 31, 2019, 2018 and 2017, we realized offsets to LNG terminal costs of $301 million corresponding to 51 TBtu of LNG, $140 million corresponding to 17 TBtu and $320 million corresponding to 51 TBtu, respectively, that were related to the sale of commissioning cargoes from the Liquefaction Projects.

Also included in LNG revenues are gains and losses from derivative instruments and the sale of natural gas procured for the liquefaction process. We recognized revenues of $693 million, $163 million and a loss of $8 million during the years ended December 31, 2019, 2018 and 2017, respectively, related to derivative instruments and other revenues from these transactions.


60


The following table presents the components of LNG revenues and the corresponding LNG volumes sold:
 
Year Ended December 31,
 
2019
 
2018
 
2017
LNG revenues (in millions):
 
 
 
 
 
LNG from the Liquefaction Projects sold under third party long-term agreements (1)
$
6,342

 
$
4,762

 
$
2,588

LNG from the Liquefaction Projects sold by our integrated marketing function under short-term agreements
1,943

 
1,902

 
1,756

LNG procured from third parties
268

 
745

 
981

Other revenues and derivative gains (losses)
693

 
163

 
(8
)
Total LNG revenues
$
9,246

 
$
7,572

 
$
5,317

 
 
 
 
 
 
Volumes sold as LNG revenues (in TBtu):
 
 
 
 
 
LNG from the Liquefaction Projects sold under third party long-term agreements (1)
1,090

 
761

 
427

LNG from the Liquefaction Projects sold by our integrated marketing function under short-term agreements
368

 
212

 
233

LNG procured from third parties
40

 
84

 
98

Total volumes sold as LNG revenues
1,498

 
1,057

 
758

 
(1)     Long-term agreements include agreements with a tenure of 12 months or more.

Operating costs and expenses
 
Year Ended December 31,
(in millions)
2019
 
2018
 
Change
 
2017
 
Change
Cost of sales
$
5,079

 
$
4,597

 
$
482

 
$
3,120

 
$
1,477

Operating and maintenance expense
1,154

 
613

 
541

 
446

 
167

Development expense
9

 
7

 
2

 
10

 
(3
)
Selling, general and administrative expense
310

 
289

 
21

 
256

 
33

Depreciation and amortization expense
794

 
449

 
345

 
356

 
93

Restructuring expense

 

 

 
6

 
(6
)
Impairment expense and loss on disposal of assets
23

 
8

 
15

 
19

 
(11
)
Total operating costs and expenses
$
7,369

 
$
5,963

 
$
1,406

 
$
4,213

 
$
1,750


2019 vs. 2018 and 2018 vs. 2017

Our total operating costs and expenses increased during the year ended December 31, 2019 from the years ended December 31, 2018 and 2017, primarily as a result of the increase in operating Trains between each of the periods. During the year ended December 31, 2019, we further incurred increased third-party service and maintenance costs from turnaround and related activities at the SPL Project.

Cost of sales includes costs incurred directly for the production and delivery of LNG from the Liquefaction Projects, to the extent those costs are not utilized for the commissioning process. Cost of sales increased during the year ended December 31, 2019 from the comparable 2018 and 2017 periods, primarily as a result of the increase in operating Trains between each of the periods. Cost of sales increased during the year ended December 31, 2019 from the year ended December 31, 2018 due to increased volume of natural gas feedstock partially offset by its decreased pricing and increased vessel charter costs. Partially offsetting this increase was increased derivative gains from an increase in fair value of the derivatives associated with economic hedges to secure natural gas feedstock for the Liquefaction Projects, primarily due to a favorable shift in long-term forward prices. Cost of sales also includes port and canal fees, variable transportation and storage costs and the sale of natural gas procured for the liquefaction process and other costs to convert natural gas into LNG. The increase during the year ended December 31, 2018 from the comparable period in 2017 was primarily related to the increase in the volume of natural gas feedstock related to our LNG sales.

Operating and maintenance expense primarily includes costs associated with operating and maintaining the Liquefaction Projects. The increase in operating and maintenance expense during the year ended December 31, 2019 from the comparable 2018 and 2017 periods was primarily as a result of the increase in operating Trains between each of the periods. The increase during the year ended December 31, 2019 from the comparable period in 2018 was primarily related to: (1) increased natural gas transportation and storage capacity demand charges from operating Train 5 of the SPL Project and Trains 1 and 2 of the CCL

61


Project following the respective substantial completions, (2) increased cost of turnaround and related activities at the SPL Project, (3) increased TUA reservation charges paid to Total from payments under the partial TUA assignment agreement and (4) increased payroll and benefit costs from increased headcount to operate Train 5 of the SPL Project and Trains 1 and 2 of the CCL Project. The increase during the year ended December 31, 2018 from the comparable period in 2017 was primarily related to third-party service and maintenance contract costs, payroll and benefit costs of operations personnel and natural gas transportation and storage capacity demand charges. Operating and maintenance expense also includes insurance and regulatory costs and other operating costs.

Depreciation and amortization expense increased during each of the years ended December 31, 2019, 2018 and 2017 as a result of an increased number of operational Trains, as the related assets began depreciating upon reaching substantial completion.

Impairment expense and loss on disposal of assets increased during the year ended December 31, 2019 compared to the year ended December 31, 2018. The impairment expense and loss on disposal of assets recognized during the year ended December 31, 2019 was primarily related to the write down of assets used in non-core operations outside of our liquefaction activities, including losses from uncollectible notes receivable. Impairment expense and loss on disposal of assets decreased during the year ended December 31, 2018 from the comparable 2017 period. The impairment expense and loss on disposal of assets recognized during the year ended December 31, 2018 related to the write down of prepaid assets and related to write down of assets used in non-core operations outside of our liquefaction activities during the year ended December 31, 2017. The impairment expense and loss on disposal of assets recognized during the year ended December 31, 2017 also included $6 million related to damaged infrastructure as a result of Hurricane Harvey.

We expect our operating costs and expenses to generally increase in the future upon Train 6 of the SPL Project and Train 3 of the CCL Project achieving substantial completion, although we expect certain costs will not proportionally increase with the number of operational Trains as cost efficiencies will be realized.

Other expense (income)
 
Year Ended December 31,
(in millions)
2019
 
2018
 
Change
 
2017
 
Change
Interest expense, net of capitalized interest
$
1,432

 
$
875

 
$
557

 
$
747

 
$
128

Loss on modification or extinguishment of debt
55

 
27

 
28

 
100

 
(73
)
Derivative loss (gain), net
134

 
(57
)
 
191

 
(7
)
 
(50
)
Other expense (income)
25

 
(48
)
 
73

 
(18
)
 
(30
)
Total other expense
$
1,646

 
$
797

 
$
849

 
$
822

 
$
(25
)

2019 vs. 2018 and 2018 vs. 2017

Interest expense, net of capitalized interest, increased during the year ended December 31, 2019 from the comparable 2018 and 2017 periods primarily as a result of a decrease in the portion of total interest costs that could be capitalized as additional Trains of the Liquefaction Projects completed construction between the periods. During the years ended December 31, 2019, 2018 and 2017, we incurred $1.8 billion, $1.7 billion and $1.5 billion of total interest cost, respectively, of which we capitalized $414 million, $803 million and $779 million, respectively, which was primarily related to interest costs incurred for the construction of the Liquefaction Projects.

Loss on modification or extinguishment of debt increased during the year ended December 31, 2019 compared to the year ended December 31, 2018 and decreased between the year ended December 31, 2018 and the year ended December 31, 2017. The loss on modification or extinguishment of debt recognized in each of the years was related to the incurrence of third party fees and write off of unamortized debt issuance costs recognized upon refinancing our credit facilities with senior notes, paydown of our credit facilities as part of the capital allocation framework or upon amendment and restatement of our credit facilities.

Derivative loss, net increased during the year ended December 31, 2019 compared to the year ended December 31, 2018, primarily due to an unfavorable shift in the long-term forward LIBOR curve between the periods, but decreased compared to the derivative gain during the year ended December 31, 2017 primarily due to a favorable shift in the long-term forward LIBOR curve between the periods.


62


Other expense increased during the year ended December 31, 2019 compared to the years ended December 31, 2018 and 2017, primarily due to a loss on our equity method investments, which was partially offset by an increase in interest income earned on our cash and cash equivalents and restricted cash. During the year ended December 31, 2019, we recognized impairment losses of $87 million relating to our investments in certain equity method investees, including Midship Holdings. Impairments were precipitated primarily by cost overruns and extended construction timelines for operating infrastructure of our investees’ projects, resulting in a reduction of the expected fair value of our equity interests. Other income increased during the year ended December 31, 2018 compared to the year ended December 31, 2017, primarily due to an increase in interest income earned on our cash and cash equivalents.

Income tax provision
 
Year Ended December 31,
(in millions)
2019
 
2018
 
Change
 
2017
 
Change
Income before income taxes and non-controlling interest
$
715

 
$
1,227

 
$
(512
)
 
$
566

 
$
661

Income tax benefit (provision)
517

 
(27
)
 
544

 
(3
)
 
(24
)
Effective tax rate
(72.3
)%
 
2.2
%
 
 
 
0.5
%
 
 

2019 vs. 2018 and 2018 vs. 2017

The tax benefit of $517 million and effective tax rate of (72.3)% for the year ended December 31, 2019 is primarily attributable to releasing a significant portion of the valuation allowance previously recorded against our deferred tax assets.

We evaluate the recoverability of our deferred tax assets as of each reporting date, weighing all positive and negative evidence, and establish a valuation allowance if we determine that it is more likely than not that some or all of our deferred tax assets will not be realized. The assessment requires significant judgment and is performed in each of our applicable jurisdictions. In making such determination, we consider various factors such as historical profitability, future projections of sustained profitability, reversal of existing deferred tax liabilities, construction and operational milestones reached on our Liquefaction Projects and our long-term SPAs achieving date of first commercial delivery. We recorded a valuation allowance of $686 million in 2018 against our deferred tax assets due to being in a three-year cumulative loss position at the time, in addition to ongoing construction and performance risks related to our Liquefaction Projects. After weighing 2019 positive and negative evidence, we determined that sufficient positive evidence existed to support releasing the valuation allowance against significantly all of our federal deferred tax assets and a portion of our state deferred tax assets. The positive evidence supporting such conclusion included successful completion and subsequent operations of Trains 1 and 2 of the CCL Project and Train 5 of the SPL Project, our transitioning from a three-year cumulative loss position in 2018 to a three-year cumulative income position in 2019, achieving date of first commercial delivery on 12 of our long term customer SPAs and forecasts of sustained future profitability. As a result, we recorded a valuation allowance release of $490 million comprised of a $493 million federal valuation allowance release and a $49 million Louisiana valuation allowance release, partially offset by an increase to the valuation allowance of $52 million in various other state and foreign tax jurisdictions. We maintained a valuation allowance of $196 million at December 31, 2019 primarily against state net operating loss carryforward deferred tax assets, for which we continue to believe the more likely than not recognition threshold was not met.

The tax expense of $27 million and $3 million during the years ended December 31, 2018 and 2017 was primarily due to income earned in the UK related to our integrated marketing function. The effective tax rates during each of the years ended December 31, 2018 and 2017 were lower than the 21% and 35% federal statutory rates for the respective years, primarily as a result of maintaining a valuation allowance against our federal and state net deferred tax assets.

Net income attributable to non-controlling interest
 
Year Ended December 31,
(in millions)
2019
 
2018
 
Change
 
2017
 
Change
Net income attributable to non-controlling interest
$
584

 
$
729

 
$
(145
)
 
$
956

 
$
(227
)

2019 vs. 2018

Net income attributable to non-controlling interest decreased during the year ended December 31, 2019 from the year ended December 31, 2018 primarily due to the annualized decrease of non-controlling interest as a result of our merger with Cheniere

63


Holdings in September 2018, in which all publicly-held shares of Cheniere Holdings were canceled and the non-controlling interest in Cheniere Holdings was reduced to zero. The consolidated net income recognized by Cheniere Partners decreased from $1.3 billion in the year ended December 31, 2018 to $1.2 billion in the year ended December 31, 2019 primarily due a decrease in income from operations from higher operating and maintenance expense and an increase in interest expense, net of capitalized interest and increased depreciation and amortization expense, partially offset by increased margins due to higher volumes of LNG sold but decreased pricing on LNG.

2018 vs. 2017

Net income attributable to non-controlling interest decreased during the year ended December 31, 2018 from the year ended December 31, 2017 due to the nonrecurrence of non-cash amortization of the beneficial conversion feature on Cheniere Partners’ Class B units that occurred during the comparable period in 2017, which was partially offset by the increase in consolidated net income recognized by Cheniere Partners in which the non-controlling interests are held, adjusting for the increase in the share of Cheniere Partners’ net income that is attributed to non-controlling interest holders as a result of changes in ownership percentages between years. Net income attributable to non-controlling interest during the year ended December 31, 2017 included approximately $748 million due to amortization of the beneficial conversion feature on Cheniere Partners’ Class B units, which ceased upon the conversion of Cheniere Partners’ Class B units into common units. The consolidated net income recognized by Cheniere Partners increased from $490 million in the year ended December 31, 2017 to $1.3 billion in the year ended December 31, 2018, primarily as a result of the additional Trains that were operating at the SPL Project between the periods. Partially offsetting the decrease in net income attributable to non-controlling interest was an increase in ownership percentage by non-controlling interest holders between the periods as a result of the conversion of Cheniere Partners’ Class B units into common units on August 2, 2017.

Off-Balance Sheet Arrangements
 
As of December 31, 2019, we had no transactions that met the definition of off-balance sheet arrangements that may have a current or future material effect on our consolidated financial position or operating results.

Summary of Critical Accounting Estimates

The preparation of Consolidated Financial Statements in conformity with GAAP requires management to make certain estimates and assumptions that affect the amounts reported in the Consolidated Financial Statements and the accompanying notes. Management evaluates its estimates and related assumptions regularly, including those related to the valuation of derivative instruments. Changes in facts and circumstances or additional information may result in revised estimates, and actual results may differ from these estimates. Management considers the following to be its most critical accounting estimates that involve significant judgment.

Fair Value of Derivative Instruments

All derivative instruments, other than those that satisfy specific exceptions, are recorded at fair value. We record changes in the fair value of our derivative positions based on the value for which the derivative instrument could be exchanged between willing parties.  If market quotes are not available to estimate fair value, management’s best estimate of fair value is based on the quoted market price of derivatives with similar characteristics or determined through industry-standard valuation approaches. Such evaluations may involve significant judgment and the results are based on expected future events or conditions, particularly for those valuations using inputs unobservable in the market.

Our derivative instruments consist of interest rate swaps, financial commodity derivative contracts transacted in an over-the-counter market, physical commodity contracts and foreign currency exchange (“FX”) contracts. We value our interest rate swaps using observable inputs including interest rate curves, risk adjusted discount rates, credit spreads and other relevant data. Valuation of our financial commodity derivative contracts is determined using observable commodity price curves and other relevant data. We estimate the fair values of our FX derivative instruments using observable FX rates and other relevant data. 

Valuation of our physical commodity contracts is predominantly driven by observable and unobservable market commodity prices and, as applicable to our natural gas supply contracts, our assessment of the associated events deriving fair value, including evaluating whether the respective market is available as pipeline infrastructure is developed. The fair value of our physical commodity contracts incorporates risk premiums related to the satisfaction of conditions precedent, such as completion and placement into service of relevant pipeline infrastructure to accommodate marketable physical gas flow. A portion of our physical

64


commodity contracts require us to make critical accounting estimates that involve significant judgment, as the fair value is developed through the use of internal models which incorporate significant unobservable inputs. In instances where observable data is unavailable, consideration is given to the assumptions that market participants would use in valuing the asset or liability. This includes assumptions about market risks, such as future prices of energy units for unobservable periods, liquidity, volatility and contract duration.

Gains and losses on derivative instruments are recognized in earnings. The ultimate fair value of our derivative instruments is uncertain, and we believe that it is reasonably possible that a change in the estimated fair value could occur in the near future as interest rates, commodity prices and FX rates change.

Recent Accounting Standards

For descriptions of recently issued accounting standards, see Note 2—Summary of Significant Accounting Policies of our Notes to Consolidated Financial Statements.

ITEM 7A.    QUANTITATIVE AND QUALITATIVE DISCLOSURES ABOUT MARKET RISK
 
Marketing and Trading Commodity Price Risk

We have entered into commodity derivatives consisting of natural gas supply contracts for the commissioning and operation of the SPL Project, the CCL Project and potential future development of Corpus Christi Stage 3 (“Liquefaction Supply Derivatives”). We have also entered into financial derivatives to hedge the exposure to the commodity markets in which we have contractual arrangements to purchase or sell physical LNG (“LNG Trading Derivatives”). In order to test the sensitivity of the fair value of the Liquefaction Supply Derivatives and the LNG Trading Derivatives to changes in underlying commodity prices, management modeled a 10% change in the commodity price for natural gas for each delivery location and a 10% change in the commodity price for LNG, respectively, as follows (in millions):
 
December 31, 2019
 
December 31, 2018
 
Fair Value
 
Change in Fair Value
 
Fair Value
 
Change in Fair Value
Liquefaction Supply Derivatives
$
149

 
$
179

 
$
(42
)
 
$
6

LNG Trading Derivatives
165

 
22

 
(24
)
 
9


Interest Rate Risk

We are exposed to interest rate risk primarily when we incur debt related to project financing. Interest rate risk is managed in part by replacing outstanding floating-rate debt with fixed-rate debt with varying maturities. CCH has entered into interest rate swaps to hedge the exposure to volatility in a portion of the floating-rate interest payments under the CCH Credit Facility (“CCH Interest Rate Derivatives”) and to hedge against changes in interest rates that could impact anticipated future issuance of debt by CCH (“CCH Interest Rate Forward Start Derivatives”). In order to test the sensitivity of the fair value of the CCH Interest Rate Derivatives to changes in interest rates, management modeled a 10% change in the forward one-month LIBOR curve across the remaining terms of the CCH Interest Rate Derivatives and CCH Interest Rate Forward Start Derivatives as follows (in millions):
 
December 31, 2019
 
December 31, 2018
 
Fair Value
 
Change in Fair Value
 
Fair Value
 
Change in Fair Value
CCH Interest Rate Derivatives
$
(81
)
 
$
19

 
$
18

 
$
37

CCH Interest Rate Forward Start Derivatives
(8
)
 
15

 

 



65


Foreign Currency Exchange Risk

We have entered into foreign currency exchange (“FX”) contracts to hedge exposure to currency risk associated with operations in countries outside of the United States (“FX Derivatives”). In order to test the sensitivity of the fair value of the FX Derivatives to changes in FX rates, management modeled a 10% change in FX rate between the U.S. dollar and the applicable foreign currencies as follows (in millions):
 
December 31, 2019
 
December 31, 2018
 
Fair Value
 
Change in Fair Value
 
Fair Value
 
Change in Fair Value
FX Derivatives
$
4

 
$

 
$
15

 
$
1


See Note 7—Derivative Instruments for additional details about our derivative instruments.


66




ITEM 8.
FINANCIAL STATEMENTS AND SUPPLEMENTARY DATA
 
INDEX TO CONSOLIDATED FINANCIAL STATEMENTS
 
CHENIERE ENERGY, INC. AND SUBSIDIARIES
 
 
 


67


MANAGEMENT’S REPORT TO THE STOCKHOLDERS OF CHENIERE ENERGY, INC.
 
Management’s Report on Internal Control Over Financial Reporting
 
As management, we are responsible for establishing and maintaining adequate internal control over financial reporting for Cheniere Energy, Inc. and its subsidiaries (“Cheniere”). In order to evaluate the effectiveness of internal control over financial reporting, as required by Section 404 of the Sarbanes-Oxley Act of 2002, we have conducted an assessment, including testing using the criteria in Internal Control—Integrated Framework (2013) issued by the Committee of Sponsoring Organizations of the Treadway Commission (“COSO”). Cheniere’s system of internal control over financial reporting is designed to provide reasonable assurance regarding the reliability of financial reporting and the preparation of financial statements for external purposes in accordance with accounting principles generally accepted in the United States of America. Because of its inherent limitations, internal control over financial reporting may not prevent or detect misstatements and, even when determined to be effective, can only provide reasonable assurance with respect to financial statement preparation and presentation.
 
Based on our assessment, we have concluded that Cheniere maintained effective internal control over financial reporting as of December 31, 2019, based on criteria in Internal Control—Integrated Framework (2013) issued by the COSO.

Cheniere’s independent registered public accounting firm, KPMG LLP, has issued an audit report on Cheniere’s internal control over financial reporting as of December 31, 2019, which is contained in this Form 10-K.
 
Management’s Certifications
 
The certifications of Cheniere’s Chief Executive Officer and Chief Financial Officer required by the Sarbanes-Oxley Act of 2002 have been included as Exhibits 31 and 32 in Cheniere’s Form 10-K.
 
CHENIERE ENERGY, INC.
 
 
 
 
 
By:
/s/ Jack A. Fusco
 
By:
/s/ Michael J. Wortley
 
Jack A. Fusco
 
 
Michael J. Wortley
 
President and Chief Executive Officer
(Principal Executive Officer)
 
 
Executive Vice President and Chief Financial Officer
(Principal Financial Officer)


68


REPORT OF INDEPENDENT REGISTERED PUBLIC ACCOUNTING FIRM

To the Stockholders and Board of Directors
Cheniere Energy, Inc.:
Opinion on the Consolidated Financial Statements
We have audited the accompanying consolidated balance sheets of Cheniere Energy, Inc. and subsidiaries (the Company) as of December 31, 2019 and 2018, the related consolidated statements of operations, stockholders’ equity, and cash flows for each of the years in the three-year period ended December 31, 2019, and the related notes and financial statement schedule I (collectively, the consolidated financial statements). In our opinion, the consolidated financial statements present fairly, in all material respects, the financial position of the Company as of December 31, 2019 and 2018, and the results of its operations and its cash flows for each of the years in the three-year period ended December 31, 2019, in conformity with U.S. generally accepted accounting principles.
We also have audited, in accordance with the standards of the Public Company Accounting Oversight Board (United States) (PCAOB), the Company’s internal control over financial reporting as of December 31, 2019, based on criteria established in Internal Control—Integrated Framework (2013) issued by the Committee of Sponsoring Organizations of the Treadway Commission, and our report dated February 24, 2020 expressed an unqualified opinion on the effectiveness of the Company’s internal control over financial reporting.
Change in Accounting Principle
As discussed in Note 2 to the consolidated financial statements, the Company has changed its method of accounting for leases as of January 1, 2019 due to the adoption of ASU 2016-02, Leases (Topic 842), and subsequent amendments thereto.
Basis for Opinion
These consolidated financial statements are the responsibility of the Company’s management. Our responsibility is to express an opinion on these consolidated financial statements based on our audits. We are a public accounting firm registered with the PCAOB and are required to be independent with respect to the Company in accordance with the U.S. federal securities laws and the applicable rules and regulations of the Securities and Exchange Commission and the PCAOB.
We conducted our audits in accordance with the standards of the PCAOB. Those standards require that we plan and perform the audit to obtain reasonable assurance about whether the consolidated financial statements are free of material misstatement, whether due to error or fraud. Our audits included performing procedures to assess the risks of material misstatement of the consolidated financial statements, whether due to error or fraud, and performing procedures that respond to those risks. Such procedures included examining, on a test basis, evidence regarding the amounts and disclosures in the consolidated financial statements. Our audits also included evaluating the accounting principles used and significant estimates made by management, as well as evaluating the overall presentation of the consolidated financial statements. We believe that our audits provide a reasonable basis for our opinion.
Critical Audit Matter
The critical audit matter communicated below is a matter arising from the current period audit of the consolidated financial statements that was communicated or required to be communicated to the audit committee and that: (1) relates to accounts or disclosures that are material to the consolidated financial statements and (2) involved our especially challenging, subjective, or complex judgment. The communication of critical audit matter does not alter in any way our opinion on the consolidated financial statements, taken as a whole, and we are not, by communicating the critical audit matter below, providing a separate opinion on the critical audit matter or on the accounts or disclosures to which it relates.
Fair value of the level 3 physical liquefaction supply derivatives
As discussed in note 7 to the consolidated financial statements, the Company recorded fair value of level 3 physical liquefaction supply derivatives of $138 million, as of December 31, 2019. The physical liquefaction supply derivatives consist of natural gas supply contracts for the operation of the liquefied natural gas facilities. The fair value of the Company’s level 3 physical liquefaction supply derivatives is developed through the use of internal models, using observable and unobservable market commodity prices.
We identified the evaluation of the fair value of the Company’s level 3 physical liquefaction supply derivatives as a critical audit matter. Specifically, there is subjectivity in certain assumptions used to estimate the fair value, such as the use of liquidity assumptions and adjustments for unobservable commodity prices. Additionally, the fair value for certain of the liquefaction

69


supply derivatives is derived through the use of complex models, which include assumptions for unobservable commodity prices and volatility.
The primary procedures we performed to address this critical audit matter include the following. We tested certain internal controls over the valuation of the level 3 physical liquefaction supply derivatives. This included controls related to the assumptions for significant unobservable inputs and the fair value models. For the level 3 liquefaction supply derivatives selected, we involved valuation professionals with specialized skills who assisted in:
Assessing the models and volatility used by the Company in its valuation by developing independent fair value estimates and comparing the independently developed estimates to the Company’s fair value estimates, and
Testing the market unobservable forward price curve adjustments and liquidity assumptions by comparing to market data, such as quoted or published forward prices for similar commodities.
In addition, we evaluated the Company’s assumptions for unobservable commodity prices by comparing to market or third party data, such as adjustments for third party quoted transportation prices.




/s/    KPMG LLP
KPMG LLP
 



We have served as the Company’s auditor since 2014.

Houston, Texas
February 24, 2020

70


REPORT OF INDEPENDENT REGISTERED PUBLIC ACCOUNTING FIRM

To the Stockholders and Board of Directors
Cheniere Energy, Inc.:
Opinion on Internal Control Over Financial Reporting
We have audited Cheniere Energy, Inc. and subsidiaries’ (the Company) internal control over financial reporting as of December 31, 2019, based on criteria established in Internal Control—Integrated Framework (2013) issued by the Committee of Sponsoring Organizations of the Treadway Commission. In our opinion, the Company maintained, in all material respects, effective internal control over financial reporting as of December 31, 2019, based on criteria established in Internal Control—Integrated Framework (2013) issued by the Committee of Sponsoring Organizations of the Treadway Commission.
We also have audited, in accordance with the standards of the Public Company Accounting Oversight Board (United States) (PCAOB), the consolidated balance sheets of the Company as of December 31, 2019 and 2018, the related consolidated statements of operations, stockholders’ equity, and cash flows for each of the years in the three-year period ended December 31, 2019, and the related notes and financial statement schedule I (collectively, the consolidated financial statements), and our report dated February 24, 2020 expressed an unqualified opinion on those consolidated financial statements.
Basis for Opinion
The Company’s management is responsible for maintaining effective internal control over financial reporting and for its assessment of the effectiveness of internal control over financial reporting, included in the accompanying Management’s Report on Internal Control Over Financial Reporting. Our responsibility is to express an opinion on the Company’s internal control over financial reporting based on our audit. We are a public accounting firm registered with the PCAOB and are required to be independent with respect to the Company in accordance with the U.S. federal securities laws and the applicable rules and regulations of the Securities and Exchange Commission and the PCAOB.
We conducted our audit in accordance with the standards of the PCAOB. Those standards require that we plan and perform the audit to obtain reasonable assurance about whether effective internal control over financial reporting was maintained in all material respects. Our audit of internal control over financial reporting included obtaining an understanding of internal control over financial reporting, assessing the risk that a material weakness exists, and testing and evaluating the design and operating effectiveness of internal control based on the assessed risk. Our audit also included performing such other procedures as we considered necessary in the circumstances. We believe that our audit provides a reasonable basis for our opinion.
Definition and Limitations of Internal Control Over Financial Reporting
A company’s internal control over financial reporting is a process designed to provide reasonable assurance regarding the reliability of financial reporting and the preparation of financial statements for external purposes in accordance with generally accepted accounting principles. A company’s internal control over financial reporting includes those policies and procedures that (1) pertain to the maintenance of records that, in reasonable detail, accurately and fairly reflect the transactions and dispositions of the assets of the company; (2) provide reasonable assurance that transactions are recorded as necessary to permit preparation of financial statements in accordance with generally accepted accounting principles, and that receipts and expenditures of the company are being made only in accordance with authorizations of management and directors of the company; and (3) provide reasonable assurance regarding prevention or timely detection of unauthorized acquisition, use, or disposition of the company’s assets that could have a material effect on the financial statements.
Because of its inherent limitations, internal control over financial reporting may not prevent or detect misstatements. Also, projections of any evaluation of effectiveness to future periods are subject to the risk that controls may become inadequate because of changes in conditions, or that the degree of compliance with the policies or procedures may deteriorate.
/s/    KPMG LLP
KPMG LLP
 
Houston, Texas
February 24, 2020

71


CHENIERE ENERGY, INC. AND SUBSIDIARIES

CONSOLIDATED BALANCE SHEETS (1)
(in millions, except share data) 
 
December 31,
 
2019
 
2018
ASSETS

 
 
Current assets
 
 
 
Cash and cash equivalents
$
2,474

 
$
981

Restricted cash
520

 
2,175

Accounts and other receivables
491

 
585

Inventory
312

 
316

Derivative assets
323

 
63

Other current assets
92

 
114

Total current assets
4,212

 
4,234

 
 
 
 
Property, plant and equipment, net
29,673

 
27,245

Operating lease assets, net
439

 

Non-current derivative assets
174

 
54

Goodwill
77

 
77

Deferred tax assets
529

 
8

Other non-current assets, net
388

 
369

Total assets
$
35,492

 
$
31,987

 
 
 
 
LIABILITIES AND STOCKHOLDERS’ EQUITY
 

 
 

Current liabilities
 

 
 

Accounts payable
$
66

 
$
58

Accrued liabilities
1,281

 
1,169

Current debt

 
239

Deferred revenue
161

 
139

Current operating lease liabilities
236

 

Derivative liabilities
117

 
128

Other current liabilities
13

 
9

Total current liabilities
1,874

 
1,742

 
 
 
 
Long-term debt, net
30,774

 
28,179

Non-current operating lease liabilities
189

 

Non-current finance lease liabilities
58

 
57

Non-current derivative liabilities
151

 
22

Other non-current liabilities
11

 
58

 
 
 
 
Commitments and contingencies (see Note 19)


 


 
 
 
 
Stockholders’ equity
 

 
 

Preferred stock, $0.0001 par value, 5.0 million shares authorized, none issued

 

Common stock, $0.003 par value, 480.0 million shares authorized
 
 
 

Issued: 270.7 million shares and 269.8 million shares at December 31, 2019 and 2018, respectively


 


Outstanding: 253.6 million shares and 257.0 million shares at December 31, 2019 and 2018, respectively
1

 
1

Treasury stock: 17.1 million shares and 12.8 million shares at December 31, 2019 and 2018, respectively, at cost
(674
)
 
(406
)
Additional paid-in-capital
4,167

 
4,035

Accumulated deficit
(3,508
)
 
(4,156
)
Total stockholders’ deficit
(14
)
 
(526
)
Non-controlling interest
2,449

 
2,455

Total equity
2,435

 
1,929

Total liabilities and stockholders’ equity
$
35,492

 
$
31,987

 
(1)
Amounts presented include balances held by our consolidated variable interest entity (“VIE”), Cheniere Partners, as further discussed in Note 9— Non-controlling Interest and Variable Interest Entity. As of December 31, 2019, total assets and liabilities of Cheniere Partners, which are included in our Consolidated Balance Sheets, were $19.1 billion and $18.6 billion, respectively, including $1.8 billion of cash and cash equivalents and $0.2 billion of restricted cash.

The accompanying notes are an integral part of these consolidated financial statements.

72



CHENIERE ENERGY, INC. AND SUBSIDIARIES

CONSOLIDATED STATEMENTS OF OPERATIONS
(in millions, except per share data) 
 
Year Ended December 31,
 
2019
 
2018
 
2017
Revenues
 
 
 
 
 
LNG revenues
$
9,246

 
$
7,572

 
$
5,317

Regasification revenues
266

 
261

 
260

Other revenues
218

 
154

 
24

Total revenues
9,730

 
7,987

 
5,601

 
 
 
 
 
 
Operating costs and expenses
 
 
 
 
 
Cost of sales (excluding depreciation and amortization expense shown separately below)
5,079

 
4,597

 
3,120

Operating and maintenance expense
1,154

 
613

 
446

Development expense
9

 
7

 
10

Selling, general and administrative expense
310

 
289

 
256

Depreciation and amortization expense
794

 
449

 
356

Restructuring expense

 

 
6

Impairment expense and loss on disposal of assets
23

 
8

 
19

Total operating costs and expenses
7,369

 
5,963

 
4,213

 
 
 
 
 
 
Income from operations
2,361

 
2,024

 
1,388

 
 
 
 
 
 
Other income (expense)
 
 
 
 
 
Interest expense, net of capitalized interest
(1,432
)
 
(875
)
 
(747
)
Loss on modification or extinguishment of debt
(55
)
 
(27
)
 
(100
)
Derivative gain (loss), net
(134
)
 
57

 
7

Other income (expense)
(25
)
 
48

 
18

Total other expense
(1,646
)
 
(797
)
 
(822
)
 
 
 
 
 
 
Income before income taxes and non-controlling interest
715


1,227

 
566

Income tax benefit (provision)
517


(27
)
 
(3
)
Net income
1,232


1,200

 
563

Less: net income attributable to non-controlling interest
584


729

 
956

Net income (loss) attributable to common stockholders
$
648


$
471

 
$
(393
)






 
 
Net income (loss) per share attributable to common stockholders—basic (1)
$
2.53


$
1.92

 
$
(1.68
)
Net income (loss) per share attributable to common stockholders—diluted (1)
$
2.51

 
$
1.90

 
$
(1.68
)
 





 
 
Weighted average number of common shares outstanding—basic
256.2

 
245.6

 
233.1

Weighted average number of common shares outstanding—diluted
258.1

 
248.0

 
233.1


 
(1)
Earnings per share in the table may not recalculate exactly due to rounding because it is calculated based on whole numbers, not the rounded numbers presented.






The accompanying notes are an integral part of these consolidated financial statements.

73



CHENIERE ENERGY, INC. AND SUBSIDIARIES

CONSOLIDATED STATEMENTS OF STOCKHOLDERS’ EQUITY
(in millions)
 
Total Stockholders’ Equity
 
 
 
 
Common Stock
 
Treasury Stock
 
Additional Paid-in Capital
 
Accumulated Deficit
 
Non-controlling Interest
 
Total
Equity
 
Shares
 
Par Value Amount
 
Shares
 
Amount
 
 
 
 
Balance at December 31, 2016
238.0

 
$
1

 
12.2

 
$
(374
)
 
$
3,211

 
$
(4,234
)
 
$
2,235

 
$
839

Issuances of restricted stock
0.1

 

 

 

 

 

 

 

Issuance of stock to acquire additional interest in Cheniere Holdings

 

 

 

 
2

 

 
(2
)
 

Forfeitures of restricted stock
(0.2
)
 

 

 

 

 

 

 

Share-based compensation

 

 

 

 
34

 

 

 
34

Shares withheld from employees related to share-based compensation, at cost
(0.3
)
 

 
0.3

 
(12
)
 

 

 

 
(12
)
Net income attributable to non-controlling interest

 

 

 

 

 

 
956

 
956

Equity portion of convertible notes, net

 

 

 

 
1

 

 

 
1

Distributions and dividends to non-controlling interest

 

 

 

 

 

 
(185
)
 
(185
)
Net loss

 

 

 

 

 
(393
)
 

 
(393
)
Balance at December 31, 2017
237.6

 
1

 
12.5

 
(386
)
 
3,248

 
(4,627
)
 
3,004

 
1,240

Vesting of restricted stock units
0.5

 

 

 

 

 

 

 

Issuance of stock to acquire additional interest in Cheniere Holdings and other merger related adjustments
19.2

 

 

 

 
694

 

 
(702
)
 
(8
)
Share-based compensation

 

 

 

 
90

 

 

 
90

Shares withheld from employees related to share-based compensation, at cost
(0.3
)
 

 
0.3

 
(20
)
 

 

 

 
(20
)
Net income attributable to non-controlling interest

 

 

 

 

 

 
729

 
729

Equity portion of convertible notes, net

 

 

 

 
3

 

 

 
3

Distributions and dividends to non-controlling interest

 

 

 

 

 

 
(576
)
 
(576
)
Net income

 

 

 

 

 
471

 

 
471

Balance at December 31, 2018
257.0


1


12.8


(406
)

4,035


(4,156
)

2,455


1,929

Vesting of restricted stock units
0.9

 

 

 

 

 

 

 

Share-based compensation

 

 

 

 
131

 

 

 
131

Shares withheld from employees related to share-based compensation, at cost
(0.3
)
 

 
0.3

 
(19
)
 

 

 

 
(19
)
Shares repurchased, at cost
(4.0
)
 

 
4.0

 
(249
)
 

 

 

 
(249
)
Net income attributable to non-controlling interest

 

 

 

 

 

 
584

 
584

Equity portion of convertible notes, net

 

 

 

 
1

 

 

 
1

Distributions and dividends to non-controlling interest

 

 

 

 

 

 
(590
)
 
(590
)
Net income

 

 

 

 

 
648

 

 
648

Balance at December 31, 2019
253.6

 
$
1

 
17.1

 
$
(674
)
 
$
4,167

 
$
(3,508
)
 
$
2,449

 
$
2,435

    

The accompanying notes are an integral part of these consolidated financial statements.

74



CHENIERE ENERGY, INC. AND SUBSIDIARIES

CONSOLIDATED STATEMENTS OF CASH FLOWS
(in millions)
 
Year Ended December 31,
 
2019
 
2018
 
2017
Cash flows from operating activities
 
 
 
 
 
Net income
$
1,232

 
$
1,200

 
$
563

Adjustments to reconcile net income to net cash provided by operating activities:
 
 
 
 
 
Depreciation and amortization expense
794

 
449

 
356

Share-based compensation expense
131

 
113

 
91

Non-cash interest expense
143

 
74

 
75

Amortization of debt issuance costs, deferred commitment fees, premium and discount
103

 
69

 
69

Non-cash operating lease costs
350

 

 

Loss on modification or extinguishment of debt
55

 
27

 
100

Total losses (gains) on derivatives, net
(400
)
 
51

 
62

Net cash provided by (used for) settlement of derivative instruments
138

 
17

 
(106
)
Impairment expense and loss on disposal of assets
23

 
8

 
19

Impairment or loss on equity method investments
88

 

 

Deferred taxes
(521
)
 
(5
)
 
(3
)
Other

 
(5
)
 
(1
)
Changes in operating assets and liabilities:
 
 
 
 
 
Accounts and other receivables
1

 
(133
)
 
(141
)
Inventory
11

 
(73
)
 
(73
)
Other current assets
(18
)
 
(15
)
 
(34
)
Accounts payable and accrued liabilities
52

 
188

 
225

Deferred revenue
22

 
26

 
34

Operating lease liabilities
(366
)
 

 

Finance lease liabilities
1

 

 

Other, net
(6
)
 
(1
)
 
(5
)
Net cash provided by operating activities
1,833

 
1,990

 
1,231

 
 
 
 
 
 
Cash flows from investing activities
 
 
 
 
 
Property, plant and equipment, net
(3,056
)
 
(3,643
)
 
(3,357
)
Investment in equity method investment
(105
)
 
(25
)
 
(41
)
Other
(2
)
 
14

 
17

Net cash used in investing activities
(3,163
)
 
(3,654
)
 
(3,381
)
 
 
 
 
 
 
Cash flows from financing activities
 
 
 
 
 
Proceeds from issuances of debt
6,434

 
4,285

 
6,854

Repayments of debt
(4,346
)
 
(1,391
)
 
(3,632
)
Debt issuance and deferred financing costs
(51
)
 
(66
)
 
(89
)
Debt extinguishment costs
(15
)
 
(17
)
 

Distributions and dividends to non-controlling interest
(590
)
 
(576
)
 
(185
)
Payments related to tax withholdings for share-based compensation
(19
)
 
(20
)
 
(12
)
Repurchase of common stock
(249
)
 

 

Other
4

 
(8
)
 

Net cash provided by financing activities
1,168

 
2,207

 
2,936

 
 
 
 
 
 
Net increase (decrease) in cash, cash equivalents and restricted cash
(162
)
 
543

 
786

Cash, cash equivalents and restricted cash—beginning of period
3,156

 
2,613

 
1,827

Cash, cash equivalents and restricted cash—end of period
$
2,994

 
$
3,156

 
$
2,613

Balances per Consolidated Balance Sheets:
 
December 31,
 
2019
 
2018
Cash and cash equivalents
$
2,474

 
$
981

Restricted cash
520

 
2,175

Total cash, cash equivalents and restricted cash
$
2,994

 
$
3,156


The accompanying notes are an integral part of these consolidated financial statements.

75


  
CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS


NOTE 1—ORGANIZATION AND NATURE OF OPERATIONS

Cheniere, a Delaware corporation, is a Houston-based energy infrastructure company primarily engaged in LNG-related businesses. We are operating and constructing two natural gas liquefaction and export facilities at Sabine Pass and Corpus Christi.

The Sabine Pass LNG terminal is located in Cameron Parish, Louisiana, on the Sabine-Neches Waterway less than four miles from the Gulf Coast. Cheniere Partners, through its subsidiary SPL, is currently operating five natural gas liquefaction Trains and is constructing one additional Train for a total production capacity of approximately 30 mtpa of LNG (the “SPL Project”) at the Sabine Pass LNG terminal. The Sabine Pass LNG terminal has operational regasification facilities owned by Cheniere Partners’ subsidiary, SPLNG, that include pre-existing infrastructure of five LNG storage tanks, two marine berths and vaporizers. Cheniere Partners also owns a 94-mile pipeline that interconnects the Sabine Pass LNG terminal with a number of large interstate pipelines (the “Creole Trail Pipeline”) through its subsidiary, CTPL. As of December 31, 2019, we owned 100% of the general partner interest and 48.6% of the limited partner interest in Cheniere Partners.

The Corpus Christi LNG terminal is located near Corpus Christi, Texas and is operated and constructed by our subsidiary, CCL. We are currently operating two Trains and are constructing one additional Train for a total production capacity of approximately 15 mtpa of LNG. We also operate a 23-mile natural gas supply pipeline that interconnects the Corpus Christi LNG terminal with several interstate and intrastate natural gas pipelines (the “Corpus Christi Pipeline” and together with the Trains, the “CCL Project”) through our subsidiary, CCP. The CCL Project, once fully constructed, will contain three LNG storage tanks and two marine berths.

Additionally, separate from the CCH Group, we are developing an expansion of the Corpus Christi LNG terminal adjacent to the CCL Project (“Corpus Christi Stage 3”) through our subsidiary CCL Stage III, for up to seven midscale Trains with an expected total production capacity of approximately 10 mtpa of LNG. We received approval from FERC in November 2019 to site, construct and operate the expansion project.

We remain focused on operational excellence and customer satisfaction. Increasing demand of LNG has allowed us to expand our liquefaction infrastructure in a financially disciplined manner. We hold significant land positions at both the Sabine Pass LNG terminal and the Corpus Christi LNG terminal which provide opportunity for further liquefaction capacity expansion. The development of these sites or other projects, including infrastructure projects in support of natural gas supply and LNG demand, will require, among other things, acceptable commercial and financing arrangements before we make a final investment decision (“FID”).

NOTE 2—SUMMARY OF SIGNIFICANT ACCOUNTING POLICIES

Basis of Presentation

Our Consolidated Financial Statements have been prepared in accordance with GAAP. The Consolidated Financial Statements include the accounts of Cheniere, its majority owned subsidiaries and entities in which it holds a controlling interest, including the accounts of Cheniere Partners and its wholly owned subsidiaries. For those consolidated subsidiaries in which our ownership is less than 100%, the portion of the net income or loss attributable to the non-controlling interest is reported as net income (loss) attributable to non-controlling interest on our Consolidated Statement of Operations. All significant intercompany accounts and transactions have been eliminated in consolidation. Investments in non-controlled entities, over which Cheniere has the ability to exercise significant influence over operating and financial policies, are accounted for using the equity method of accounting, with our share of earnings or losses reported in other income (expense) on our Consolidated Statement of Operations. In applying the equity method of accounting, the investments are initially recognized at cost, and subsequently adjusted for our proportionate share of earnings, losses and distributions. Investments accounted for using the equity method of accounting are reported as a component of other noncurrent assets.

We make a determination at the inception of each arrangement whether an entity in which we have made an investment or in which we have other variable interests is considered a variable interest entity (“VIE”).  Generally, a VIE is an entity that does not have sufficient equity at risk to finance its activities without additional subordinated financial support from other parties, whose equity investors lack any characteristics of a controlling financial interest or which was established with non-substantive voting. We consolidate VIEs when we are deemed to be the primary beneficiary. The primary beneficiary of a VIE is generally the party that both: (1) has the power to make decisions that most significantly affect the economic performance of the VIE and (2) has the

76


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

obligation to absorb losses or the right to receive benefits that in either case could potentially be significant to the VIE. If we are not deemed to be the primary beneficiary of a VIE, we account for the investment or other variable interests in a VIE in accordance with applicable GAAP.

Certain reclassifications have been made to conform prior period information to the current presentation.  The reclassifications did not have a material effect on our consolidated financial position, results of operations or cash flows.

Recent Accounting Standards

We adopted Accounting Standards Update (“ASU”) 2016-02, Leases (Topic 842), and subsequent amendments thereto (“ASC 842”) on January 1, 2019 using the optional transition approach to apply the standard at the beginning of the first quarter of 2019 with no retrospective adjustments to prior periods. The adoption of the standard resulted in the recognition of right-of-use assets and lease liabilities for operating leases of approximately $550 million on our Consolidated Balance Sheets, with no material impact on our Consolidated Statements of Operations or Consolidated Statements of Cash Flows. We have elected the practical expedients to (1) carryforward prior conclusions related to lease identification and classification for existing leases, (2) combine lease and non-lease components of an arrangement for all classes of leased assets, (3) omit short-term leases with a term of 12 months or less from recognition on the balance sheet and (4) carryforward our existing accounting for land easements not previously accounted for as leases. See Note 12—Leases for additional information on our leases following the adoption of this standard.

In December 2019, the Financial Accounting Standards Board (“FASB”) issued ASU 2019-12, Income Taxes (Topic 740): Simplifying the Accounting for Income Taxes. The new guidance is designed to simplify the accounting for income taxes by removing certain exceptions related to the general principles in ASU 740, Income Taxes, and to clarify and simplify other aspects of the accounting for income taxes. This guidance changes the methodology for calculating income taxes in an interim period by prospectively requiring reflection of enacted changes in tax laws or rates in the interim period in which such change is enacted. We early adopted this guidance effective December 31, 2019. The adoption of this guidance did not have an impact on our Consolidated Financial Statements or related disclosures.

Use of Estimates

The preparation of Consolidated Financial Statements in conformity with GAAP requires management to make certain estimates and assumptions that affect the amounts reported in the Consolidated Financial Statements and the accompanying notes. Management evaluates its estimates and related assumptions regularly, including those related to fair value measurements, revenue recognition, property, plant and equipment, derivative instruments, leases, goodwill, asset retirement obligations (“AROs”), share-based compensation and income taxes including valuation allowances for deferred tax assets, as further discussed under the respective sections within this note. Changes in facts and circumstances or additional information may result in revised estimates, and actual results may differ from these estimates.

Fair Value Measurements

Fair value is the price that would be received to sell an asset or paid to transfer a liability in an orderly transaction between market participants. Hierarchy Levels 1, 2 and 3 are terms for the priority of inputs to valuation approaches used to measure fair value. Hierarchy Level 1 inputs are quoted prices in active markets for identical assets or liabilities. Hierarchy Level 2 inputs are inputs that are directly or indirectly observable for the asset or liability, other than quoted prices included within Level 1. Hierarchy Level 3 inputs are inputs that are not observable in the market.

In determining fair value, we use observable market data when available, or models that incorporate observable market data. In addition to market information, we incorporate transaction-specific details that, in management’s judgment, market participants would take into account in measuring fair value. We maximize the use of observable inputs and minimize our use of unobservable inputs in arriving at fair value estimates.

Recurring fair-value measurements are performed for derivative instruments as disclosed in Note 7—Derivative Instruments. The carrying amount of cash and cash equivalents, restricted cash, accounts receivable and accounts payable reported on the Consolidated Balance Sheets approximates fair value. The fair value of debt is the estimated amount we would have to pay to repurchase our debt in the open market, including any premium or discount attributable to the difference between the stated interest rate and market interest rate at each balance sheet date. Debt fair values, as disclosed in Note 11—Debt, are based on quoted

77


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

market prices for identical instruments, if available, or based on valuations of similar debt instruments using observable or unobservable inputs. Non-financial assets and liabilities initially measured at fair value include intangible assets, goodwill and AROs.

Revenue Recognition

We recognize revenues when we transfer control of promised goods or services to our customers in an amount that reflects the consideration to which we expect to be entitled to in exchange for those goods or services. Revenues from the sale of LNG are recognized as LNG revenues, including LNG revenues generated by our integrated marketing function which are reported on a gross or net basis based on an assessment of whether it is acting as the principal or the agent in the transaction. LNG regasification capacity payments are recognized as regasification revenues. See Note 13—Revenues from Contracts with Customers for further discussion of revenues.

Cash and Cash Equivalents

We consider all highly liquid investments with an original maturity of three months or less to be cash equivalents.

Restricted Cash

Restricted cash consists of funds that are contractually or legally restricted as to usage or withdrawal and have been presented separately from cash and cash equivalents on our Consolidated Balance Sheets.

Accounts and Notes Receivable

Accounts and notes receivable are reported net of any allowances for doubtful accounts. Notes receivable that are not classified as trade receivables are recorded within other current assets in our Consolidated Balance Sheets, net of any allowances for doubtful accounts. We periodically review the collectability on our accounts receivable and recognize an allowance if there is probability of non-collection, based on historical write-off and customer-specific factors. As of December 31, 2019 and 2018, we had an allowance on our accounts and notes receivable of zero and $30 million, respectively.

Inventory

LNG and natural gas inventory are recorded at the lower of weighted average cost and net realizable value. Materials and other inventory are recorded at the lower of cost and net realizable value and subsequently charged to expense when issued.

Accounting for LNG Activities

Generally, we begin capitalizing the costs of our LNG terminals once the individual project meets the following criteria: (1) regulatory approval has been received, (2) financing for the project is available and (3) management has committed to commence construction. Prior to meeting these criteria, most of the costs associated with a project are expensed as incurred. These costs primarily include professional fees associated with preliminary front-end engineering and design work, costs of securing necessary regulatory approvals and other preliminary investigation and development activities related to our LNG terminals.

Generally, costs that are capitalized prior to a project meeting the criteria otherwise necessary for capitalization include: land acquisition costs, detailed engineering design work and certain permits that are capitalized as other non-current assets. The costs of lease options are amortized over the life of the lease once obtained. If no land or lease is obtained, the costs are expensed.

Property, Plant and Equipment

Property, plant and equipment are recorded at cost. Expenditures for construction and commissioning activities, major renewals and betterments that extend the useful life of an asset are capitalized, while expenditures for maintenance and repairs (including those for planned major maintenance projects) to maintain property, plant and equipment in operating condition are generally expensed as incurred. We realize offsets to LNG terminal costs for sales of commissioning cargoes that were earned or loaded prior to the start of commercial operations of the respective Train during the testing phase for its construction. We depreciate our property, plant and equipment using the straight-line depreciation method. Upon retirement or other disposition of property,

78


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

plant and equipment, the cost and related accumulated depreciation are removed from the account, and the resulting gains or losses are recorded in impairment expense and loss (gain) on disposal of assets.

Management tests property, plant and equipment for impairment whenever events or changes in circumstances have indicated that the carrying amount of property, plant and equipment might not be recoverable. Assets are grouped at the lowest level for which there are identifiable cash flows that are largely independent of the cash flows of other groups of assets for purposes of assessing recoverability. Recoverability generally is determined by comparing the carrying value of the asset to the expected undiscounted future cash flows of the asset. If the carrying value of the asset is not recoverable, the amount of impairment loss is measured as the excess, if any, of the carrying value of the asset over its estimated fair value.

During the year ended December 31, 2017, we recognized $6 million of impairment expense related to damaged infrastructure as an effect of Hurricane Harvey and $6 million of impairment expense related to write down of assets used in non-core operations outside of our liquefaction activities.

Interest Capitalization

We capitalize interest costs during the construction period of our LNG terminals and related assets as construction-in-process. Upon commencement of operations, these costs are transferred out of construction-in-process into terminal and interconnecting pipeline facilities assets and are amortized over the estimated useful life of the asset.

Regulated Natural Gas Pipelines

The Creole Trail Pipeline and Corpus Christi Pipeline are subject to the jurisdiction of the FERC in accordance with the Natural Gas Act of 1938 and the Natural Gas Policy Act of 1978. The economic effects of regulation can result in a regulated company recording as assets those costs that have been or are expected to be approved for recovery from customers, or recording as liabilities those amounts that are expected to be required to be returned to customers, in a rate-setting process in a period different from the period in which the amounts would be recorded by an unregulated enterprise. Accordingly, we record assets and liabilities that result from the regulated rate-making process that may not be recorded under GAAP for non-regulated entities. We continually assess whether regulatory assets are probable of future recovery by considering factors such as applicable regulatory changes and recent rate orders applicable to other regulated entities. Based on this continual assessment, we believe the existing regulatory assets are probable of recovery. These regulatory assets and liabilities are primarily classified in our Consolidated Balance Sheets as other assets and other liabilities. We periodically evaluate their applicability under GAAP and consider factors such as regulatory changes and the effect of competition. If cost-based regulation ends or competition increases, we may have to reduce our asset balances to reflect a market basis less than cost and write off the associated regulatory assets and liabilities. 

Items that may influence our assessment are:
inability to recover cost increases due to rate caps and rate case moratoriums;  
inability to recover capitalized costs, including an adequate return on those costs through the rate-making process and the FERC proceedings;  
excess capacity;  
increased competition and discounting in the markets we serve; and  
impacts of ongoing regulatory initiatives in the natural gas industry.

Natural gas pipeline costs include amounts capitalized as an Allowance for Funds Used During Construction (“AFUDC”). The rates used in the calculation of AFUDC are determined in accordance with guidelines established by the FERC. AFUDC represents the cost of debt and equity funds used to finance our natural gas pipeline additions during construction. AFUDC is capitalized as a part of the cost of our natural gas pipelines. Under regulatory rate practices, we generally are permitted to recover AFUDC, and a fair return thereon, through our rate base after our natural gas pipelines are placed in service.

Derivative Instruments

We use derivative instruments to hedge our exposure to cash flow variability from interest rate, commodity price and foreign currency exchange (“FX”) rate risk. Derivative instruments are recorded at fair value and included in our Consolidated Balance Sheets as assets or liabilities depending on the derivative position and the expected timing of settlement, unless they satisfy criteria

79


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

for, and we elect, the normal purchases and sales exception. When we have the contractual right and intend to net settle, derivative assets and liabilities are reported on a net basis.

Changes in the fair value of our derivative instruments are recorded in earnings, unless we elect to apply hedge accounting and meet specified criteria. We did not have any derivative instruments designated as cash flow or fair value hedges during the years ended December 31, 2019, 2018 and 2017. See Note 7—Derivative Instruments for additional details about our derivative instruments.

Leases

Following the adoption of ASC 842, we determine if an arrangement is, or contains, a lease at inception of the arrangement. When we determine the arrangement is, or contains, a lease, we classify the lease as either an operating lease or a finance lease. Operating and finance leases are recognized on our Consolidated Balance Sheets by recording a lease liability representing the obligation to make future lease payments and a right-of-use asset representing the right to use the underlying asset for the lease term. Operating and finance lease right-of-use assets and liabilities are generally recognized based on the present value of lease payments over the lease term. In determining the present value of lease payments, we use the implicit interest rate in the lease if readily determinable. In the absence of a readily determinable implicitly interest rate, we discount our expected future lease payments using our relevant subsidiary’s incremental borrowing rate. The incremental borrowing rate is an estimate of the interest rate that a given subsidiary would have to pay to borrow on a collateralized basis over a similar term to that of the lease term. Options to renew a lease are included in the lease term and recognized as part of the right-of-use asset and lease liability, only to the extent they are reasonably certain to be exercised. We have elected practical expedients to (1) omit leases with an initial term of 12 months or less from recognition on our balance sheet and (2) to combine both the lease and non-lease components of an arrangement in calculating the right-of-use asset and lease liability for all classes of leased assets.

Lease expense for operating lease payments is recognized on a straight-line basis over the lease term. Lease expense for finance leases is recognized as the sum of the amortization of the right-of-use assets on a straight-line basis and the interest on lease liabilities using the effective interest method over the lease term.

Operating leases are included in operating lease assets, net, current operating lease liabilities and non-current operating lease liabilities on our Consolidated Balance Sheets. Finance leases are included in property, plant and equipment, net, other current liabilities and non-current finance lease liabilities on our Consolidated Balance Sheets. See Note 12—Leases for additional details about our leases.

Concentration of Credit Risk

Financial instruments that potentially subject us to a concentration of credit risk consist principally of cash and cash equivalents, restricted cash, derivative instruments and accounts receivable. We maintain cash balances at financial institutions, which may at times be in excess of federally insured levels. We have not incurred losses related to these balances to date.

The use of derivative instruments exposes us to counterparty credit risk, or the risk that a counterparty will be unable to meet its commitments. Certain of our commodity derivative transactions are executed through over-the-counter contracts which are subject to nominal credit risk as these transactions are settled on a daily margin basis with investment grade financial institutions. Collateral deposited for such contracts is recorded within other current assets. Our interest rate and FX derivative instruments are placed with investment grade financial institutions whom we believe are acceptable credit risks. We monitor counterparty creditworthiness on an ongoing basis; however, we cannot predict sudden changes in counterparties’ creditworthiness. In addition, even if such changes are not sudden, we may be limited in our ability to mitigate an increase in counterparty credit risk. Should one of these counterparties not perform, we may not realize the benefit of some of our derivative instruments.

SPL has entered into fixed price long-term SPAs generally with terms of 20 years with eight third parties, CCL has entered into fixed price long-term SPAs generally with terms of 20 years with nine third parties and our integrated marketing function has entered into a limited number of long-term SPAs with third parties. We are dependent on the respective customers’ creditworthiness and their willingness to perform under their respective SPAs. See Note 20—Customer Concentration for additional details about our customer concentration.

SPLNG has entered into two long-term TUAs with third parties for regasification capacity at the Sabine Pass LNG terminal. SPLNG is dependent on the respective customers’ creditworthiness and their willingness to perform under their respective TUAs.

80


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

SPLNG has mitigated this credit risk by securing TUAs for a significant portion of its regasification capacity with creditworthy third-party customers with a minimum Standard & Poor’s rating of A.
Goodwill
Goodwill is the excess of acquisition cost of a business over the estimated fair value of net assets acquired.  Goodwill is not amortized but is tested for impairment at least annually or more frequently if events or circumstances indicate goodwill is more likely than not impaired.  Goodwill impairment evaluation requires a comparison of the estimated fair value of a reporting unit to its carrying value.  Cheniere tests goodwill for impairment by either performing a qualitative assessment or a quantitative test.  The qualitative assessment is an assessment of historical information and relevant events and circumstances to determine whether it is more likely than not that the fair value of a reporting unit is less than its carrying amount, including goodwill.  Cheniere may elect not to perform the qualitative assessment and instead perform a quantitative impairment test.  Significant judgment is required in estimating the fair value of the reporting unit and performing quantitative goodwill impairment tests.
We completed our annual assessment of goodwill impairment as of October 1st by performing a qualitative assessment; the tests indicated it is more likely than not that there was no impairment. Our last quantitative assessment indicated that the reporting unit’s fair value substantially exceeded its carrying value. As discussed above regarding our use of estimates, our judgments and assumptions are inherent in our estimate of future cash flows used to determine the estimate of the reporting unit’s fair value. The use of alternate judgments and/or assumptions could result in the recognition of impairment charges in the Consolidated Financial Statements. A lower fair value estimate in the future for our reporting unit could result in an impairment of goodwill. Factors that could trigger a lower fair value estimate include significant negative industry or economic trends, cost increases, disruptions to our business, regulatory or political environment changes or other unanticipated events.

Debt

Our debt consists of current and long-term secured and unsecured debt securities, convertible debt securities and credit facilities with banks and other lenders.  Debt issuances are placed directly by us or through securities dealers or underwriters and are held by institutional and retail investors.

Debt is recorded on our Consolidated Balance Sheets at par value adjusted for unamortized discount or premium and net of unamortized debt issuance costs related to term notes. Debt issuance costs consist primarily of arrangement fees, professional fees, legal fees and printing costs. If debt issuance costs are incurred in connection with a line of credit arrangement or on undrawn funds, they are presented as an asset on our Consolidated Balance Sheets. Discounts, premiums and debt issuance costs directly related to the issuance of debt are amortized over the life of the debt and are recorded in interest expense, net of capitalized interest using the effective interest method. Gains and losses on the extinguishment or modification of debt are recorded in gain (loss) on modification or extinguishment of debt on our Consolidated Statements of Operations.

Asset Retirement Obligations

We recognize AROs for legal obligations associated with the retirement of long-lived assets that result from the acquisition, construction, development and/or normal use of the asset and for conditional AROs in which the timing or method of settlement are conditional on a future event that may or may not be within our control. The fair value of a liability for an ARO is recognized in the period in which it is incurred, if a reasonable estimate of fair value can be made. The fair value of the liability is added to the carrying amount of the associated asset. This additional carrying amount is depreciated over the estimated useful life of the asset.

We have not recorded an ARO associated with the Sabine Pass LNG terminal. Based on the real property lease agreements at the Sabine Pass LNG terminal, at the expiration of the term of the leases we are required to surrender the LNG terminal in good working order and repair, with normal wear and tear and casualty expected. Our property lease agreements at the Sabine Pass LNG terminal have terms of up to 90 years including renewal options. We have determined that the cost to surrender the Sabine Pass LNG terminal in good order and repair, with normal wear and tear and casualty expected, is immaterial.

We have not recorded an ARO associated with the Creole Trail Pipeline or the Corpus Christi Pipeline. We believe that it is not feasible to predict when the natural gas transportation services provided by the Creole Trail Pipeline or the Corpus Christi Pipeline will no longer be utilized. In addition, our right-of-way agreements associated with the Creole Trail Pipeline and the Corpus Christi Pipeline have no stipulated termination dates. We intend to operate the Creole Trail Pipeline and the Corpus Christi Pipeline as long as supply and demand for natural gas exists in the United States and intend to maintain it regularly.

81


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

Share-based Compensation

We have awarded share-based compensation in the form of stock, restricted stock, restricted stock units, performance stock units and phantom units that are more fully described in Note 15—Share-based Compensation. We recognize share-based compensation based upon the estimated fair value of awards. The recognition period for these costs begins at either the applicable service inception date or grant date and continues throughout the requisite service period. For equity-classified share-based compensation awards (which include stock, restricted stock, restricted stock units and performance stock units to employees and non-employee directors), compensation cost is recognized based on the grant-date fair value and not subsequently remeasured unless modified. The fair value is recognized as expense (net of any capitalization) using the straight-line basis for awards that vest based solely on service conditions and using the accelerated recognition method for awards that vest based on performance conditions. For awards with both time and performance-based conditions, we generally recognize compensation cost based on the probable outcome of the performance condition at each reporting period. For liability-classified share-based compensation awards (which include phantom units), compensation costs are remeasured at fair value through settlement or maturity. We account for forfeitures as they occur.

Non-controlling Interests

When we consolidate a subsidiary, we include 100% of the assets, liabilities, revenues and expenses of the subsidiary in our Consolidated Financial Statements, even if we own less than 100% of the subsidiary. Non-controlling interests represent third-party ownership in the net assets of our consolidated subsidiaries and are presented as a component of equity. Changes in our ownership interests in subsidiaries that do not result in deconsolidation are generally recognized within equity. See Note 9—Non-controlling Interest and Variable Interest Entities for additional details about our non-controlling interest.

Income Taxes

Provisions for income taxes are based on taxes payable or refundable for the current year and deferred taxes on temporary differences between the tax basis of assets and liabilities and their reported amounts in our Consolidated Financial Statements. Deferred tax assets and liabilities are included in our Consolidated Financial Statements at currently enacted income tax rates applicable to the period in which the deferred tax assets and liabilities are expected to be realized or settled. As changes in tax laws or rates are enacted, deferred tax assets and liabilities are adjusted through the current period’s provision for income taxes. A valuation allowance is recorded to reduce the carrying value of our deferred tax assets when it is more likely than not that a portion or all of the deferred tax assets will expire before realization of the benefit or future deductibility is not probable.

We recognize the tax benefit from an uncertain tax position only if it is more likely than not that the tax position will be sustained on examination by the taxing authorities, based on the technical merits of the tax position.

Net Income (Loss) Per Share

Net income (loss) per share attributable to common stockholders (“EPS”) is computed in accordance with GAAP. Basic EPS excludes dilution and is computed by dividing net income (loss) attributable to common stockholders by the weighted average number of common shares outstanding during the period. Diluted EPS reflects potential dilution and is computed by dividing net income (loss) attributable to common stockholders by the weighted average number of common shares outstanding during the period increased by the number of additional common shares that would have been outstanding if the potential common shares had been issued. The dilutive effect of unvested stock is calculated using the treasury-stock method and the dilutive effect of convertible securities is calculated using the if-converted method.

Business Segment

We have determined that we operate as a single operating and reportable segment. Our chief operating decision maker makes resource allocation decisions and assesses performance based on financial information presented on a consolidated basis in the delivery of an integrated source of LNG to our customers.


82


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

NOTE 3—RESTRICTED CASH
 
Restricted cash consists of funds that are contractually or legally restricted as to usage or withdrawal and have been presented separately from cash and cash equivalents on our Consolidated Balance Sheets. As of December 31, 2019 and 2018, restricted cash consisted of the following (in millions):
 
 
December 31,
 
 
2019
 
2018
Current restricted cash
 
 
 
 
SPL Project
 
$
181

 
$
756

Cheniere Partners and cash held by guarantor subsidiaries
 

 
785

CCL Project
 
80

 
289

Cash held by our subsidiaries restricted to Cheniere
 
259

 
345

Total current restricted cash
 
$
520

 
$
2,175


Pursuant to the accounts agreements entered into with the collateral trustees for the benefit of SPL’s debt holders and CCH’s debt holders, SPL and CCH are required to deposit all cash received into reserve accounts controlled by the collateral trustees.  The usage or withdrawal of such cash is restricted to the payment of liabilities related to the SPL Project and the CCL Project (collectively, the “Liquefaction Projects”) and other restricted payments.
The cash held by Cheniere Partners and its guarantor subsidiaries was restricted in use under the terms of the previous $2.8 billion credit facilities (the “2016 CQP Credit Facilities”) and the related depositary agreement governing the extension of credit to Cheniere Partners, but is no longer restricted following the termination of the 2016 CQP Credit Facilities in May 2019.

NOTE 4—ACCOUNTS AND OTHER RECEIVABLES

As of December 31, 2019 and 2018, accounts and other receivables consisted of the following (in millions):
 
 
December 31,
 
 
2019
 
2018
Trade receivables
 
 
 
 
SPL and CCL
 
$
328

 
$
330

Cheniere Marketing
 
113

 
205

Other accounts receivable
 
50

 
50

Total accounts and other receivables
 
$
491

 
$
585



NOTE 5—INVENTORY

As of December 31, 2019 and 2018, inventory consisted of the following (in millions):
 
 
December 31,
 
 
2019
 
2018
Natural gas
 
$
16

 
$
30

LNG
 
67

 
24

LNG in-transit
 
93

 
173

Materials and other
 
136

 
89

Total inventory
 
$
312

 
$
316




83


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

NOTE 6—PROPERTY, PLANT AND EQUIPMENT
 
As of December 31, 2019 and 2018, property, plant and equipment, net consisted of the following (in millions):
 
 
December 31,
 
 
2019
 
2018
LNG terminal costs
 
 
 
 
LNG terminal and interconnecting pipeline facilities
 
$
27,305

 
$
13,386

LNG site and related costs
 
322

 
86

LNG terminal construction-in-process
 
3,903

 
14,864

Accumulated depreciation
 
(2,049
)
 
(1,299
)
Total LNG terminal costs, net
 
29,481

 
27,037

Fixed assets and other
 
 

 
 

Computer and office equipment
 
23

 
17

Furniture and fixtures
 
22

 
22

Computer software
 
110

 
100

Leasehold improvements
 
42

 
41

Land
 
59

 
59

Other
 
21

 
21

Accumulated depreciation
 
(141
)
 
(111
)
Total fixed assets and other, net
 
136

 
149

Assets under finance lease
 
 
 
 
Tug vessels
 
60

 
60

Accumulated depreciation
 
(4
)
 
(1
)
Total assets under finance lease, net
 
56

 
59

Property, plant and equipment, net
 
$
29,673

 
$
27,245



Depreciation expense was $788 million, $445 million and $354 million during the years ended December 31, 2019, 2018 and 2017, respectively.
We realized offsets to LNG terminal costs of $301 million, $140 million and $320 million during the years ended December 31, 2019, 2018 and 2017, respectively, that were related to the sale of commissioning cargoes because these amounts were earned or loaded prior to the start of commercial operations of the respective Trains of the Liquefaction Projects, during the testing phase for its construction.

LNG Terminal Costs

Our LNG terminals are depreciated using the straight-line depreciation method applied to groups of LNG terminal assets with varying useful lives. The identifiable components of our LNG terminals have depreciable lives between 7 and 50 years, as follows:
Components
 
Useful life (yrs)
LNG storage tanks
 
50
Natural gas pipeline facilities
 
40
Marine berth, electrical, facility and roads
 
35
Water pipelines
 
30
Regasification processing equipment
 
30
Sendout pumps
 
20
Liquefaction processing equipment
 
7-50
Other
 
10-30

Fixed Assets and Other

Our fixed assets and other are recorded at cost and are depreciated on a straight-line method based on estimated lives of the individual assets or groups of assets.


84


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

NOTE 7—DERIVATIVE INSTRUMENTS
 
We have entered into the following derivative instruments that are reported at fair value:
interest rate swaps to hedge the exposure to volatility in a portion of the floating-rate interest payments under CCH’s credit facilities (“CCH Interest Rate Derivatives”) and to hedge against changes in interest rates that could impact anticipated future issuance of debt by CCH (“CCH Interest Rate Forward Start Derivatives”);
commodity derivatives consisting of natural gas supply contracts for the commissioning and operation of the Liquefaction Projects and potential future development of Corpus Christi Stage 3 (“Physical Liquefaction Supply Derivatives”) and associated economic hedges (collectively, the “Liquefaction Supply Derivatives”);
financial derivatives to hedge the exposure to the commodity markets in which we have contractual arrangements to purchase or sell physical LNG (“LNG Trading Derivatives”); and
foreign currency exchange (“FX”) contracts to hedge exposure to currency risk associated with both LNG Trading Derivatives and operations in countries outside of the United States (“FX Derivatives”).
We recognize our derivative instruments as either assets or liabilities and measure those instruments at fair value. None of our derivative instruments are designated as cash flow or fair value hedging instruments, and changes in fair value are recorded within our Consolidated Statements of Operations to the extent not utilized for the commissioning process.

The following table shows the fair value of our derivative instruments that are required to be measured at fair value on a recurring basis as of December 31, 2019 and 2018, which are classified as derivative assets, non-current derivative assets, derivative liabilities or non-current derivative liabilities in our Consolidated Balance Sheets (in millions):
 
Fair Value Measurements as of
 
December 31, 2019
 
December 31, 2018
 
Quoted Prices in Active Markets
(Level 1)
 
Significant Other Observable Inputs
(Level 2)
 
Significant Unobservable Inputs
(Level 3)
 
Total
 
Quoted Prices in Active Markets
(Level 1)
 
Significant Other Observable Inputs
(Level 2)
 
Significant Unobservable Inputs
(Level 3)
 
Total
CCH Interest Rate Derivatives asset (liability)
$

 
$
(81
)
 
$

 
$
(81
)
 
$

 
$
18

 
$

 
$
18

CCH Interest Rate Forward Start Derivatives liability

 
(8
)
 

 
(8
)
 

 

 

 

Liquefaction Supply Derivatives asset (liability)
5

 
6

 
138

 
149

 
6

 
(19
)
 
(29
)
 
(42
)
LNG Trading Derivatives asset (liability)

 
165

 

 
165

 
1

 
(25
)
 

 
(24
)
FX Derivatives asset

 
4

 

 
4

 

 
15

 

 
15



We value our CCH Interest Rate Derivatives and CCH Interest Rate Forward Start Derivatives using an income-based approach utilizing observable inputs to the valuation model including interest rate curves, risk adjusted discount rates, credit spreads and other relevant data. We value our LNG Trading Derivatives and our Liquefaction Supply Derivatives using a market or option-based approach incorporating present value techniques, as needed, using observable commodity price curves, when available, and other relevant data. We value our FX Derivatives with a market approach using observable FX rates and other relevant data.

The fair value of our Physical Liquefaction Supply Derivatives is predominantly driven by observable and unobservable market commodity prices and, as applicable to our natural gas supply contracts, our assessment of the associated events deriving fair value, including evaluating whether the respective market is available as pipeline infrastructure is developed. The fair value of our Physical Liquefaction Supply Derivatives incorporates risk premiums related to the satisfaction of conditions precedent, such as completion and placement into service of relevant pipeline infrastructure to accommodate marketable physical gas flow. As of December 31, 2019 and 2018, some of our Physical Liquefaction Supply Derivatives existed within markets for which the pipeline infrastructure was under development to accommodate marketable physical gas flow.

We include a portion of our Physical Liquefaction Supply Derivatives as Level 3 within the valuation hierarchy as the fair value is developed through the use of internal models which incorporate significant unobservable inputs. In instances where observable data is unavailable, consideration is given to the assumptions that market participants would use in valuing the asset

85


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

or liability. This includes assumptions about market risks, such as future prices of energy units for unobservable periods, liquidity, volatility and contract duration.

The Level 3 fair value measurements of natural gas positions within our Physical Liquefaction Supply Derivatives could be materially impacted by a significant change in certain natural gas and international LNG prices. The following table includes quantitative information for the unobservable inputs for our Level 3 Physical Liquefaction Supply Derivatives as of December 31, 2019:
 
 
Net Fair Value Asset
(in millions)
 
Valuation Approach
 
Significant Unobservable Input
 
Significant Unobservable Inputs Range
Physical Liquefaction Supply Derivatives
 
$138
 
Market approach incorporating present value techniques
 
Henry Hub basis spread
 
$(0.718) - $0.058
 
 
 
 
Option pricing model
 
International LNG pricing spread, relative to Henry Hub (1)
 
86% - 213%

 
(1)    Spread contemplates U.S. dollar-denominated pricing.

Increases or decreases in basis or pricing spreads, in isolation, would decrease or increase, respectively, the fair value of our Physical Liquefaction Supply Derivatives.
The following table shows the changes in the fair value of our Level 3 Physical Liquefaction Supply Derivatives during the years ended December 31, 2019, 2018 and 2017 (in millions):
 
 
Year Ended December 31,
 
 
2019
 
2018
 
2017
Balance, beginning of period
 
$
(29
)
 
$
43

 
$
79

Realized and mark-to-market gains (losses):
 
 
 
 
 
 
Included in cost of sales
 
(77
)
 
(13
)
 
(37
)
Purchases and settlements:
 
 
 
 
 
 
Purchases
 
199

 
(31
)
 
14

Settlements
 
44

 
(29
)
 
(12
)
Transfers out of Level 3 (1)
 
1

 
1

 
(1
)
Balance, end of period
 
$
138

 
$
(29
)
 
$
43

Change in unrealized losses relating to instruments still held at end of period
 
$
(77
)
 
$
(13
)
 
$
(37
)
 
(1)    Transferred to Level 2 as a result of observable market for the underlying natural gas purchase agreements.

Derivative assets and liabilities arising from our derivative contracts with the same counterparty are reported on a net basis, as all counterparty derivative contracts provide for the unconditional right of set-off in the event of default. The use of derivative instruments exposes us to counterparty credit risk, or the risk that a counterparty will be unable to meet its commitments in instances when our derivative instruments are in an asset position. Additionally, counterparties are at risk that we will be unable to meet our commitments in instances where our derivative instruments are in a liability position. We incorporate both our own nonperformance risk and the respective counterparty’s nonperformance risk in fair value measurements. In adjusting the fair value of our derivative contracts for the effect of nonperformance risk, we have considered the impact of any applicable credit enhancements, such as collateral postings, set-off rights and guarantees.

Interest Rate Derivatives

CCH has entered into interest rate swaps to protect against volatility of future cash flows and hedge a portion of the variable interest payments on its amended and restated credit facility (the “CCH Credit Facility”).

In June and July of 2019, we entered into CCH Interest Rate Forward Start Derivatives to hedge against changes in interest rates that could impact anticipated future issuance of debt by CCH, which is anticipated by the end of 2020. In November 2019, CCH settled a portion of the CCH Interest Rate Forward Start Derivatives in conjunction with the prepayment of $1.5 billion of

86


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

commitments under the CCH Credit Facility. In June 2018, CCH settled a portion of the CCH Interest Rate Derivatives in conjunction with the amendment of the CCH Credit Facility.

Cheniere Partners previously had interest rate swaps (“CQP Interest Rate Derivatives”) to hedge a portion of the variable interest payments on its credit facilities. In October 2018, Cheniere Partners terminated the CQP Interest Rate Derivatives related to the 2016 CQP Credit Facilities.

In March 2017, SPL previously had interest rate swaps (“SPL Interest Rate Derivatives” and, collectively with the CCH Interest Rate Derivatives, the CCH Interest Rate Forward Start Derivatives and the CQP Interest Rate Derivatives, the “Interest Rate Derivatives”) to protect against volatility of future cash flows and hedge a portion of the variable interest payments on the credit facilities it entered into in June 2015.

As of December 31, 2019, we had the following Interest Rate Derivatives outstanding:
 
 
Notional Amounts
 
 
 
 
 
 
 
 
 
 
December 31, 2019
 
December 31, 2018
 
Effective Date
 
Maturity Date
 
Weighted Average Fixed Interest Rate Paid
 
Variable Interest Rate Received
CCH Interest Rate Derivatives
 
$4.5 billion
 
$4.0 billion
 
May 20, 2015
 
May 31, 2022
 
2.30%
 
One-month LIBOR
CCH Interest Rate Forward Start Derivatives
 
$750 million
 
 
September 30, 2020
 
December 31, 2030
 
2.06%
 
Three-month LIBOR

The following table shows the fair value and location of the Interest Rate Derivatives on our Consolidated Balance Sheets (in millions):
 
December 31, 2019
 
December 31, 2018
 
CCH Interest Rate Derivatives
 
CCH Interest Rate Forward Start Derivatives
 
Total
 
CCH Interest Rate Derivatives
 
CCH Interest Rate Forward Start Derivatives
 
Total
Consolidated Balance Sheet Location
 
 
 
 
 
 
 
 
 
 
 
Derivative assets
$

 
$

 
$

 
$
10

 
$

 
$
10

Non-current derivative assets

 

 

 
8

 

 
8

Total derivative assets






18




18

 
 
 
 
 


 
 
 
 
 


Derivative liabilities
(32
)
 
(8
)
 
(40
)
 

 

 

Non-current derivative liabilities
(49
)
 

 
(49
)
 

 

 

Total derivative liabilities
(81
)

(8
)

(89
)






 
 
 
 
 


 
 
 
 
 


Derivative asset (liability), net
$
(81
)

$
(8
)

$
(89
)

$
18


$


$
18


The following table shows the changes in the fair value and settlements of our Interest Rate Derivatives recorded in derivative gain (loss), net on our Consolidated Statements of Operations during the years ended December 31, 2019, 2018 and 2017 (in millions):
 
 
Year Ended December 31,
 
 
2019
 
2018
 
2017
CCH Interest Rate Derivatives gain (loss)
 
$
(101
)
 
$
43

 
$
3

CCH Interest Rate Forward Start Derivatives loss
 
(33
)
 

 

CQP Interest Rate Derivatives gain
 

 
14

 
6

SPL Interest Rate Derivatives loss
 

 

 
(2
)


Commodity Derivatives
SPL, CCL and CCL Stage III have entered into physical natural gas supply contracts and associated economic hedges to purchase natural gas for the commissioning and operation of the Liquefaction Projects and potential future development of Corpus Christi Stage 3, respectively, which are primarily indexed to the natural gas market and international LNG indices. The remaining

87


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

terms of the index-based physical natural gas supply contracts range up to approximately 15 years, some of which commence upon the satisfaction of certain events or states of affairs.

We have entered into, and may from time to time enter into, financial LNG Trading Derivatives in the form of swaps, forwards, options or futures to economically hedge exposure to the commodity markets in which we have contractual arrangements to purchase or sell physical LNG. We have entered into LNG Trading Derivatives to secure a fixed price position to minimize future cash flow variability associated with LNG purchase and sale transactions.

The following table shows the fair value and location of our Liquefaction Supply Derivatives and LNG Trading Derivatives (collectively, “Commodity Derivatives”) on our Consolidated Balance Sheets (in millions, except notional amount):
 
December 31, 2019
 
December 31, 2018
 
Liquefaction Supply Derivatives (1)
 
LNG Trading Derivatives (2)
 
Total
 
Liquefaction Supply Derivatives (1)
 
LNG Trading Derivatives (2)
 
Total
Consolidated Balance Sheet Location
 
 
 
 
 
 
 
 
 
 
 
Derivative assets
$
93

 
$
225

 
$
318

 
$
13

 
$
24

 
$
37

Non-current derivative assets
174

 

 
174

 
46

 

 
46

Total derivative assets
267

 
225

 
492

 
59

 
24

 
83

 
 
 
 
 
 
 
 
 
 
 
 
Derivative liabilities
(16
)
 
(60
)
 
(76
)
 
(79
)
 
(48
)
 
(127
)
Non-current derivative liabilities
(102
)
 

 
(102
)
 
(22
)
 

 
(22
)
Total derivative liabilities
(118
)
 
(60
)
 
(178
)
 
(101
)
 
(48
)
 
(149
)
 
 
 
 
 
 
 
 
 
 
 
 
Derivative asset (liability), net
$
149

 
$
165

 
$
314

 
$
(42
)
 
$
(24
)
 
$
(66
)
 
 
 
 
 
 
 
 
 
 
 
 
Notional amount, net (in TBtu) (3)
9,177

 
4

 
 
 
5,832

 
12

 
 

 
    
(1)
Does not include collateral posted with counterparties by us of $7 million and $5 million for such contracts, which are included in other current assets in our Consolidated Balance Sheets as of December 31, 2019 and 2018, respectively. Includes derivative assets of $3 million and $2 million and non-current assets of $2 million and $3 million as of December 31, 2019 and 2018, respectively, for a natural gas supply contract CCL has with a related party.
(2)
Does not include collateral posted with counterparties by us of $5 million and $9 million deposited for such contracts, which are included in other current assets in our Consolidated Balance Sheets as of December 31, 2019 and 2018, respectively.
(3)
Includes 120 TBtu and 55 TBtu as of December 31, 2019 and 2018, respectively, for a natural gas supply contract CCL has with a related party.

The following table shows the changes in the fair value, settlements and location of our Commodity Derivatives recorded on our Consolidated Statements of Operations during the years ended December 31, 2019, 2018 and 2017 (in millions):
 
Consolidated Statements of Operations Location (1)
 
Year Ended December 31,
 
 
2019
 
2018
 
2017
LNG Trading Derivatives gain (loss)
LNG revenues
 
$
402

 
$
(25
)
 
$
(44
)
LNG Trading Derivatives loss
Cost of sales
 
(89
)
 

 

Liquefaction Supply Derivatives gain (loss) (2)
LNG revenues
 
2

 
(1
)
 

Liquefaction Supply Derivatives gain (loss) (2)(3)
Cost of sales
 
194

 
(100
)
 
(24
)
 
(1)
Fair value fluctuations associated with commodity derivative activities are classified and presented consistently with the item economically hedged and the nature and intent of the derivative instrument.
(2)
Does not include the realized value associated with derivative instruments that settle through physical delivery.
(3)
CCL recorded $85 million in cost of sales under a natural gas supply contract with a related party during the year ended December 31, 2019, including $1 million of Liquefaction Supply Derivatives loss. As of December 31, 2019, $3 million was included in accrued liabilities related to this contract. CCL did not have any transactions during the years ended December 31, 2018 and 2017 under this contract.


88


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

FX Derivatives

Cheniere Marketing has entered into FX Derivatives to protect against the volatility in future cash flows attributable to changes in international currency exchange rates. The FX Derivatives economically hedge the foreign currency exposure arising from cash flows expended for both physical and financial LNG transactions.

The following table shows the fair value and location of our FX Derivatives on our Consolidated Balance Sheets (in millions):
 
 
 
Fair Value Measurements as of
 
Consolidated Balance Sheet Location
 
December 31, 2019
 
December 31, 2018
FX Derivatives
Derivative assets
 
$
5

 
$
16

FX Derivatives
Derivative liabilities
 
(1
)
 
(1
)


The total notional amount of our FX Derivatives was $827 million and $379 million as of December 31, 2019 and 2018, respectively.
    
The following table shows the changes in the fair value, settlements and location of our FX Derivatives recorded on our Consolidated Statements of Operations during the years ended December 31, 2019, 2018 and 2017 (in millions):
 
 
 
Year Ended December 31,
 
Consolidated Statements of Operations Location
 
2019
 
2018
 
2017
FX Derivatives gain (loss)
LNG revenues
 
$
25

 
$
18

 
$
(1
)


Consolidated Balance Sheet Presentation

Our derivative instruments are presented on a net basis on our Consolidated Balance Sheets as described above. The following table shows the fair value of our derivatives outstanding on a gross and net basis (in millions):
 
 
Gross Amounts Recognized
 
Gross Amounts Offset in the Consolidated Balance Sheets
 
Net Amounts Presented in the Consolidated Balance Sheets
Offsetting Derivative Assets (Liabilities)
 
 
 
As of December 31, 2019
 
 
 
 
 
 
CCH Interest Rate Derivatives
 
$
(81
)
 
$

 
$
(81
)
CCH Interest Rate Forward Start Derivatives
 
(8
)
 

 
(8
)
Liquefaction Supply Derivatives
 
281

 
(14
)
 
267

Liquefaction Supply Derivatives
 
(126
)
 
8

 
(118
)
LNG Trading Derivatives
 
229

 
(4
)
 
225

LNG Trading Derivatives
 
(60
)
 

 
(60
)
FX Derivatives
 
9

 
(4
)
 
5

FX Derivatives
 
(6
)
 
5

 
(1
)
As of December 31, 2018
 
 
 
 
 


CCH Interest Rate Derivatives
 
$
19

 
$
(1
)
 
$
18

Liquefaction Supply Derivatives
 
95

 
(36
)
 
59

Liquefaction Supply Derivatives
 
(121
)
 
20

 
(101
)
LNG Trading Derivatives
 
112

 
(88
)
 
24

LNG Trading Derivatives
 
(92
)
 
44

 
(48
)
FX Derivatives
 
30

 
(14
)
 
16

FX Derivatives
 
(2
)
 
1

 
(1
)



89


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

NOTE 8—OTHER NON-CURRENT ASSETS

As of December 31, 2019 and 2018, other non-current assets, net consisted of the following (in millions):
 
 
December 31,
 
 
2019
 
2018
Advances made to municipalities for water system enhancements
 
$
87

 
$
90

Advances and other asset conveyances to third parties to support LNG terminals
 
55

 
54

Advances made under EPC and non-EPC contracts
 
29

 
14

Equity method investments
 
108

 
94

Debt issuance costs, net
 
45

 
72

Tax-related payments and receivables
 
20

 
21

Other
 
44

 
24

Total other non-current assets, net
 
$
388

 
$
369


Equity Method Investments

Our equity method investments consist of interests in privately-held companies. In 2017, we acquired an equity interest in Midship Holdings, LLC (“Midship Holdings”), which manages the business and affairs of Midship Pipeline Company, LLC (“Midship Pipeline”). Midship Pipeline is currently constructing an approximately 200-mile natural gas pipeline project (the “Midship Project”) that connects production in the Anadarko Basin to Gulf Coast markets. Midship Holdings entered into agreements with investment funds managed by EIG Global Energy Partners (“EIG”) under which EIG-managed funds committed to make an investment of up to $500 million (the “EIG Investment”) in the Midship Project, subject to the terms and conditions contained in the applicable agreements. The EIG Investment, when combined with equity contributed by us, is intended to ensure the Midship Project has the equity funding expected to be required to develop and construct the project. Construction of the Midship Project commenced in the first quarter of 2019.

Subsequent to Midship Project obtaining its financing in the form of credit facilities, in conjunction with existing equity, Midship Holdings was designed to finance its activities without additional subordinated financial support. As a result, Midship Holdings is no longer a variable interest entity. We continue to report Midship Holdings as an equity method investment due to our ability to exercise significant influence over the operating and financial policies of Midship Holdings through our non-controlling voting rights on its board of managers.

During the year ended December 31, 2019, we recognized impairment losses of $87 million relating to our investments in certain equity method investees, including Midship Holdings. Impairments were precipitated primarily by cost overruns and extended construction timelines for operating infrastructure of our investees’ projects, resulting in a reduction of the expected fair value of our equity interests. Impairment losses associated with our equity method investments are presented in other expense (income).

Our investment in Midship Holdings was $105 million, net of impairment losses, and $85 million at December 31, 2019 and 2018, respectively.

Cheniere LNG O&M Services, LLC (“O&M Services”), our wholly owned subsidiary provides the development, construction, operation and maintenance services associated with the Midship Project pursuant to agreements in which O&M Services receives an agreed upon fee and reimbursement of costs incurred. O&M Services recorded $12 million, $12 million and $3 million in the years ended December 31, 2019, 2018 and 2017, respectively, of other revenues and $3 million and $4 million of accounts receivable as of December 31, 2019 and 2018, respectively, for services provided to Midship Pipeline under these agreements. CCL has entered into a transportation precedent agreement and a negotiated rate agreement with Midship Pipeline to secure firm pipeline transportation capacity for a period of 10 years following commencement of the Midship Project. In May 2018, CCL issued a letter of credit to Midship Pipeline for drawings up to an aggregate maximum amount of $16 million. Midship Pipeline had not made any drawings on this letter of credit as of December 31, 2019.

NOTE 9—NON-CONTROLLING INTEREST AND VARIABLE INTEREST ENTITY

We own a 48.6% limited partner interest in Cheniere Partners in the form of 104.5 million common units and 135.4 million subordinated units, with the remaining non-controlling interest held by Blackstone CQP Holdco LP (“Blackstone CQP Holdco”)

90


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

and the public. We also own 100% of the general partner interest and the incentive distribution rights in Cheniere Partners. Cheniere Partners is accounted for as a consolidated variable interest entity.
Cheniere Partners is a limited partnership formed by us in 2006 to own and operate the Sabine Pass LNG terminal and related assets. Our subsidiary, Cheniere Partners GP, is the general partner of Cheniere Partners. In 2012, Cheniere Partners, Cheniere and Blackstone CQP Holdco entered into a unit purchase agreement whereby Cheniere Partners sold 100.0 million Class B units to Blackstone CQP Holdco in a private placement. The board of directors of Cheniere Partners GP was modified to include three directors appointed by Blackstone CQP Holdco, four directors appointed by us and four independent directors mutually agreed upon by Blackstone CQP Holdco and us and appointed by us. In addition, we provided Blackstone CQP Holdco with a right to maintain one board seat on our Board of Directors (our “Board”). A quorum of Cheniere Partners GP directors consists of a majority of all directors, including at least two directors appointed by Blackstone CQP Holdco, two directors appointed by us and two independent directors. Blackstone CQP Holdco will no longer be entitled to appoint Cheniere Partners GP directors in the event that Blackstone CQP Holdco’s ownership in Cheniere Partners is less than 20% of outstanding common units and subordinated units.

We have determined that Cheniere Partners GP is a VIE and that we, as the holder of the equity at risk, do not have a controlling financial interest due to the rights held by Blackstone CQP Holdco. However, we continue to consolidate Cheniere Partners as a result of Blackstone CQP Holdco’s right to maintain one board seat on our Board which creates a de facto agency relationship between Blackstone CQP Holdco and us. GAAP requires that when a de facto agency relationship exists, one of the members of the de facto agency relationship must consolidate the VIE based on certain criteria. As a result, we consolidate Cheniere Partners in our Consolidated Financial Statements.

The following table presents the summarized assets and liabilities (in millions) of Cheniere Partners, our consolidated VIE, which are included in our Consolidated Balance Sheets. The assets in the table below may only be used to settle obligations of Cheniere Partners. In addition, there is no recourse to us for the consolidated VIE’s liabilities. The assets and liabilities in the table below include third-party assets and liabilities of Cheniere Partners only and exclude intercompany balances that eliminate in consolidation.
 
 
December 31,
 
 
2019
 
2018
ASSETS
 
 
 
 
Current assets
 
 
 
 
Cash and cash equivalents
 
$
1,781

 
$

Restricted cash
 
181

 
1,541

Accounts and other receivables
 
297

 
348

Other current assets
 
184

 
125

Total current assets
 
2,443

 
2,014

 
 
 
 
 
Property, plant and equipment, net
 
16,368

 
15,390

Other non-current assets, net
 
309

 
228

Total assets
 
$
19,120

 
$
17,632

 
 
 
 
 
LIABILITIES
 
 
 
 
Current liabilities
 
 
 
 
Accrued liabilities
 
$
709

 
$
821

Other current liabilities
 
210

 
197

Total current liabilities
 
919

 
1,018

 
 
 
 
 
Long-term debt, net
 
17,579

 
16,066

Other non-current liabilities
 
104

 
18

Total liabilities
 
$
18,602

 
$
17,102




91


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

NOTE 10—ACCRUED LIABILITIES
  
As of December 31, 2019 and 2018, accrued liabilities consisted of the following (in millions): 
 
 
December 31,
 
 
2019
 
2018
Interest costs and related debt fees
 
$
293

 
$
233

Accrued natural gas purchases
 
460

 
610

LNG terminals and related pipeline costs
 
327

 
125

Compensation and benefits
 
115

 
117

Accrued LNG inventory
 
6

 
14

Other accrued liabilities
 
80

 
70

Total accrued liabilities
 
$
1,281

 
$
1,169


 

92


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

NOTE 11—DEBT
 
As of December 31, 2019 and 2018, our debt consisted of the following (in millions): 
 
 
December 31,
 
 
2019
 
2018
Long-term debt:
 
 
 
 
SPL
 
 
 


5.625% Senior Secured Notes due 2021 (“2021 SPL Senior Notes”)
 
$
2,000

 
$
2,000

6.25% Senior Secured Notes due 2022 (“2022 SPL Senior Notes”)
 
1,000

 
1,000

5.625% Senior Secured Notes due 2023 (“2023 SPL Senior Notes”)
 
1,500

 
1,500

5.75% Senior Secured Notes due 2024 (“2024 SPL Senior Notes”)
 
2,000

 
2,000

5.625% Senior Secured Notes due 2025 (“2025 SPL Senior Notes”)
 
2,000

 
2,000

5.875% Senior Secured Notes due 2026 (“2026 SPL Senior Notes”)
 
1,500

 
1,500

5.00% Senior Secured Notes due 2027 (“2027 SPL Senior Notes”)
 
1,500

 
1,500

4.200% Senior Secured Notes due 2028 (“2028 SPL Senior Notes”)
 
1,350

 
1,350

5.00% Senior Secured Notes due 2037 (“2037 SPL Senior Notes”)
 
800

 
800

Cheniere Partners
 
 
 
 
5.250% Senior Notes due 2025 (“2025 CQP Senior Notes”)
 
1,500

 
1,500

5.625% Senior Notes due 2026 (“2026 CQP Senior Notes”)
 
1,100

 
1,100

4.500% Senior Notes due 2029 (“2029 CQP Senior Notes”)
 
1,500

 

2016 CQP Credit Facilities
 

 

CQP Credit Facilities executed in 2019 (“2019 CQP Credit Facilities”)
 

 

CCH
 
 
 
 
7.000% Senior Secured Notes due 2024 (“2024 CCH Senior Notes”)
 
1,250

 
1,250

5.875% Senior Secured Notes due 2025 (“2025 CCH Senior Notes”)
 
1,500

 
1,500

5.125% Senior Secured Notes due 2027 (“2027 CCH Senior Notes”)
 
1,500

 
1,500

4.80% Senior Secured Notes due 2039 (“4.80% CCH Senior Notes”)
 
727

 

3.925% Senior Secured Notes due 2039 (“3.925% CCH Senior Notes”)
 
475

 

3.700% Senior Secured Notes due 2029 (“2029 CCH Senior Notes”)
 
1,500

 

CCH Credit Facility
 
3,283

 
5,156

CCH HoldCo II
 
 
 
 
11.0% Convertible Senior Secured Notes due 2025 (“2025 CCH HoldCo II Convertible Senior Notes”)
 
1,578

 
1,455

Cheniere
 
 
 
 
4.875% Convertible Unsecured Notes due 2021 (“2021 Cheniere Convertible Unsecured Notes”)
 
1,278

 
1,218

4.25% Convertible Senior Notes due 2045 (“2045 Cheniere Convertible Senior Notes”)
 
625

 
625

$1.25 billion Cheniere Revolving Credit Facility (“Cheniere Revolving Credit Facility”)
 

 

Unamortized premium, discount and debt issuance costs, net
 
(692
)
 
(775
)
Total long-term debt, net
 
30,774

 
28,179

 
 
 
 
 
Current debt:
 
 
 
 
$1.2 billion SPL Working Capital Facility (“SPL Working Capital Facility”)
 

 

$1.2 billion CCH Working Capital Facility (“CCH Working Capital Facility”)
 

 
168

Cheniere Marketing trade finance facilities
 

 
71

Total current debt
 

 
239

 
 
 
 
 
Total debt, net
 
$
30,774

 
$
28,418




93


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

Below is a schedule of future principal payments that we are obligated to make, based on current construction schedules, on our outstanding debt at December 31, 2019 (in millions): 
Years Ending December 31,
 
Principal Payments
2020
 
$

2021
 
3,413

2022
 
1,119

2023
 
1,633

2024
 
6,146

Thereafter
 
19,155

Total
 
$
31,466



Senior Notes

SPL Senior Notes

The terms of the 2021 SPL Senior Notes, 2022 SPL Senior Notes, 2023 SPL Senior Notes, 2024 SPL Senior Notes, 2025 SPL Senior Notes, 2026 SPL Senior Notes, 2027 SPL Senior Notes and 2028 SPL Senior Notes (collectively with the 2037 SPL Senior Notes, the “SPL Senior Notes”) are governed by a common indenture (the “SPL Indenture”) and the terms of the 2037 SPL Senior Notes are governed by a separate indenture (the “2037 SPL Senior Notes Indenture”). Both the SPL Indenture and the 2037 SPL Senior Notes Indenture contain customary terms and events of default and certain covenants that, among other things, limit SPL’s ability and the ability of SPL’s restricted subsidiaries to incur additional indebtedness or issue preferred stock, make certain investments or pay dividends or distributions on capital stock or subordinated indebtedness or purchase, redeem or retire capital stock, sell or transfer assets, including capital stock of SPL’s restricted subsidiaries, restrict dividends or other payments by restricted subsidiaries, incur liens, enter into transactions with affiliates, dissolve, liquidate, consolidate, merge, sell or lease all or substantially all of SPL’s assets and enter into certain LNG sales contracts. Subject to permitted liens, the SPL Senior Notes are secured on a pari passu first-priority basis by a security interest in all of the membership interests in SPL and substantially all of SPL’s assets. SPL may not make any distributions until, among other requirements, deposits are made into debt service reserve accounts as required and a debt service coverage ratio test of 1.25:1.00 is satisfied. Semi-annual principal payments for the 2037 SPL Senior Notes are due on March 15 and September 15 of each year beginning September 15, 2025 and are fully amortizing according to a fixed sculpted amortization schedule. Interest on the SPL Senior Notes is payable semi-annually in arrears.

At any time prior to three months before the respective dates of maturity for each series of the SPL Senior Notes (except for the 2026 SPL Senior Notes, 2027 SPL Senior Notes, 2028 SPL Senior Notes and 2037 SPL Senior Notes, in which case the time period is six months before the respective dates of maturity), SPL may redeem all or part of such series of the SPL Senior Notes at a redemption price equal to the “make-whole” price (except for the 2037 SPL Senior Notes, in which case the redemption price is equal to the “optional redemption” price) set forth in the respective indentures governing the SPL Senior Notes, plus accrued and unpaid interest, if any, to the date of redemption. SPL may also, at any time within three months of the respective maturity dates for each series of the SPL Senior Notes (except for the 2026 SPL Senior Notes, 2027 SPL Senior Notes, 2028 SPL Senior Notes and 2037 SPL Senior Notes, in which case the time period is within six months of the respective dates of maturity), redeem all or part of such series of the SPL Senior Notes at a redemption price equal to 100% of the principal amount of such series of the SPL Senior Notes to be redeemed, plus accrued and unpaid interest, if any, to the date of redemption.

CQP Senior Notes

In September 2019, Cheniere Partners issued an aggregate principal amount of $1.5 billion of the 2029 CQP Senior Notes. The proceeds of the offering were used to prepay the outstanding balance of the $750 million term loan under the 2019 CQP Credit Facilities (“CQP Term Facility”) and for general corporate purposes, including funding future capital expenditures in connection with the construction of Train 6 at the SPL Project, resulting in the recognition of debt modification and extinguishment costs of $13 million for the year ended December 31, 2019. Borrowings under the 2029 CQP Senior Notes accrue interest at a fixed rate of 4.500% per annum. As of December 31, 2019, only the $750 million revolving credit facility (“CQP Revolving Facility”), all of which is undrawn, remains as part of the 2019 CQP Credit Facilities.

The 2025 CQP Senior Notes, the 2026 CQP Senior Notes and the 2029 CQP Senior Notes (collectively, the “CQP Senior Notes”) are jointly and severally guaranteed by each of Cheniere Partners’ subsidiaries other than SPL and, subject to certain conditions governing its guarantee, Sabine Pass LP (the “CQP Guarantors”). The CQP Senior Notes are governed by the same

94


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

base indenture (the “CQP Base Indenture”). The 2025 CQP Senior Notes are further governed by the First Supplemental Indenture, the 2026 CQP Senior Notes are further governed by the Second Supplemental Indenture and the 2029 CQP Senior Notes are further governed by the Third Supplemental Indenture. The indentures governing the CQP Senior Notes contain customary terms and events of default and certain covenants that, among other things, limit the ability of Cheniere Partners and the CQP Guarantors to incur liens and sell assets, enter into transactions with affiliates, enter into sale-leaseback transactions and consolidate, merge or sell, lease or otherwise dispose of all or substantially all of the applicable entity’s properties or assets. Interest on the CQP Senior Notes is payable semi-annually in arrears.

At any time prior to October 1, 2020 for the 2025 CQP Senior Notes, October 1, 2021 for the 2026 CQP Senior Notes and October 1, 2024 for the 2029 CQP Senior Notes, Cheniere Partners may redeem all or a part of the applicable CQP Senior Notes at a redemption price equal to 100% of the aggregate principal amount of the CQP Senior Notes redeemed, plus the “applicable premium” set forth in the respective indentures governing the CQP Senior Notes, plus accrued and unpaid interest, if any, to the date of redemption. In addition, at any time prior to October 1, 2020 for the 2025 CQP Senior Notes, October 1, 2021 for the 2026 CQP Senior Notes and October 1, 2024 for the 2029 CQP Senior Notes, Cheniere Partners may redeem up to 35% of the aggregate principal amount of the CQP Senior Notes with an amount of cash not greater than the net cash proceeds from certain equity offerings at a redemption price equal to 105.250% of the aggregate principal amount of the 2025 CQP Senior Notes, 105.625% of the aggregate principal amount of the 2026 CQP Senior Notes and 104.5% of the aggregate principal amount of the 2029 CQP Senior Notes redeemed, plus accrued and unpaid interest, if any, to the date of redemption. Cheniere Partners also may at any time on or after October 1, 2020 through the maturity date of October 1, 2025 for the 2025 CQP Senior Notes, October 1, 2021 through the maturity date of October 1, 2026 for the 2026 CQP Senior Notes and October 1, 2024 through the maturity date of October 1, 2029 for the 2029 CQP Senior Notes, redeem the CQP Senior Notes, in whole or in part, at the redemption prices set forth in the respective indentures governing the CQP Senior Notes.

The CQP Senior Notes are Cheniere Partners’ senior obligations, ranking equally in right of payment with Cheniere Partners’ other existing and future unsubordinated debt and senior to any of its future subordinated debt. In the event that the aggregate amount of Cheniere Partners’ secured indebtedness and the secured indebtedness of the CQP Guarantors (other than the CQP Senior Notes or any other series of notes issued under the CQP Base Indenture) outstanding at any one time exceeds the greater of (1) $1.5 billion and (2) 10% of net tangible assets, the CQP Senior Notes will be secured to the same extent as such obligations under the 2019 CQP Credit Facilities. The obligations under the 2019 CQP Credit Facilities are secured on a first-priority basis (subject to permitted encumbrances) with liens on substantially all the existing and future tangible and intangible assets and rights of Cheniere Partners and the CQP Guarantors and equity interests in the CQP Guarantors (except, in each case, for certain excluded properties set forth in the 2019 CQP Credit Facilities). The liens securing the CQP Senior Notes, if applicable, will be shared equally and ratably (subject to permitted liens) with the holders of other senior secured obligations, which include the 2019 CQP Credit Facilities obligations and any future additional senior secured debt obligations.

CCH Senior Notes

In September 2019, CCH issued an aggregate principal amount of $727 million of the 4.80% CCH Senior Notes in a private placement conducted pursuant to Section 4(a)(2) of the Securities Act. The 4.80% CCH Senior Notes were issued under an indenture dated as of September 27, 2019 pursuant to a note purchase agreement with the purchasers party thereto and Allianz Global Investors GmbH, as noteholder consultant, originally entered into in June 2019. In October 2019, CCH issued an aggregate principal amount of $475 million of the 3.925% CCH Senior Notes in a private placement conducted pursuant to Section 4(a)(2) of the Securities Act. The 3.925% CCH Senior Notes were issued under an indenture dated October 17, 2019 pursuant to a note purchase agreement with the purchasers party thereto and certain accounts managed by BlackRock Real Assets and certain accounts managed by MetLife Investment Management. The 4.80% CCH Senior Notes and the 3.925% CCH Senior Notes accrue interest at a fixed rate of 4.80% and 3.925% per annum, respectively, and are fully amortizing according to a fixed sculpted amortization schedule with semi-annual payments of interest starting December 2019 and semi-annual payments of principal starting June 2027. The 4.80% CCH Senior Notes and the 3.925% CCH Senior Notes have a weighted average life of 15 years.

In November 2019, CCH issued an aggregate principal amount of $1.5 billion of the 2029 CCH Senior Notes. The 2029 CCH Senior Notes were issued pursuant to the same indenture governing the 2024 CCH Senior Notes, 2025 CCH Senior Notes and 2027 CCH Senior Notes (together with the 2029 CCH Senior Notes, the "144A CCH Senior Notes"). Borrowings under the 2029 CCH Senior Notes accrue interest at a fixed rate of 3.700% per annum.

The proceeds of the 4.80% CCH Senior Notes, 3.925% CCH Senior Notes and 2029 CCH Senior Notes were used to prepay a portion of the balance outstanding under the CCH Credit Facility, resulting in the recognition of debt modification and

95


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

extinguishment costs of $39 million for the year ended December 31, 2019 relating to the write off of unamortized debt discounts and issuance costs.
 
The 144A CCH Senior Notes, 4.80% CCH Senior Notes and 3.925% CCH Senior Notes (collectively, the “CCH Senior Notes”) are jointly and severally guaranteed by CCH’s subsidiaries, CCL, CCP and Corpus Christi Pipeline GP, LLC (the “CCH Guarantors”). The indentures governing the CCH Senior Notes contain customary terms and events of default and certain covenants that, among other things, limit CCH’s ability and the ability of CCH’s restricted subsidiaries to: incur additional indebtedness or issue preferred stock; make certain investments or pay dividends or distributions on membership interests or subordinated indebtedness or purchase, redeem or retire membership interests; sell or transfer assets, including membership or partnership interests of CCH’s restricted subsidiaries; restrict dividends or other payments by restricted subsidiaries to CCH or any of CCH’s restricted subsidiaries; incur liens; enter into transactions with affiliates; dissolve, liquidate, consolidate, merge, sell or lease all or substantially all of the properties or assets of CCH and its restricted subsidiaries taken as a whole; or permit any CCH Guarantor to dissolve, liquidate, consolidate, merge, sell or lease all or substantially all of its properties and assets. Interest on the CCH Senior Notes is payable semi-annually in arrears.

At any time prior to six months before the respective dates of maturity for each of the CCH Senior Notes, CCH may redeem all or part of such series of the CCH Senior Notes at a redemption price equal to the “make-whole” price set forth in the appropriate indenture, plus accrued and unpaid interest, if any, to the date of redemption. At any time within six months of the respective dates of maturity for each of the CCH Senior Notes, CCH may redeem all or part of such series of the CCH Senior Notes, in whole or in part, at a redemption price equal to 100% of the principal amount of the CCH Senior Notes to be redeemed, plus accrued and unpaid interest, if any, to the date of redemption.

Credit Facilities

Below is a summary of our credit facilities outstanding as of December 31, 2019 (in millions):
 
 
SPL Working Capital Facility
 
2019 CQP Credit Facilities
 
CCH Credit Facility
 
CCH Working Capital Facility
 
Cheniere Revolving Credit Facility
Original facility size
 
$
1,200

 
$
1,500

 
$
8,404

 
$
350

 
$
750

Incremental commitments
 

 

 
1,566

 
850

 
500

Less:
 
 
 
 
 
 
 
 
 
 
Outstanding balance
 

 

 
3,283

 

 

Commitments prepaid or terminated
 

 
750

 
6,687

 

 

Letters of credit issued
 
414

 

 

 
471

 
585

Available commitment
 
$
786


$
750

 
$


$
729


$
665

 
 
 
 
 
 
 
 
 
 
 
Interest rate on available balance
 
LIBOR plus 1.75% or base rate plus 0.75%
 
LIBOR plus 1.25% - 2.125% or base rate plus 0.25% - 1.125%
 
LIBOR plus 1.75% or base rate plus 0.75%
 
LIBOR plus 1.25% - 1.75% or base rate plus 0.25% - 0.75%
 
LIBOR plus 1.75% - 2.50% or base rate plus 0.75% - 1.50%
Weighted average interest rate of outstanding balance
 
n/a
 
n/a
 
3.55%
 
n/a
 
n/a
Maturity date
 
December 31, 2020
 
May 29, 2024
 
June 30, 2024
 
June 29, 2023
 
December 13, 2022


SPL Working Capital Facility

In September 2015, SPL entered into the SPL Working Capital Facility with aggregate commitments of $1.2 billion, which was amended in May 2019 in connection with commercialization and financing of Train 6 of the SPL Project. The SPL Working Capital Facility is intended to be used for loans to SPL (“SPL Working Capital Loans”), the issuance of letters of credit on behalf of SPL, as well as for swing line loans to SPL (“SPL Swing Line Loans”), primarily for certain working capital requirements related to developing and placing into operation the SPL Project. SPL may, from time to time, request increases in the commitments under the SPL Working Capital Facility of up to $760 million and incremental increases in commitments of up to an additional $390 million.
Loans under the SPL Working Capital Facility accrue interest at a variable rate per annum equal to LIBOR or the base rate (equal to the highest of the senior facility agent’s published prime rate, the federal funds effective rate, as published by the Federal Reserve Bank of New York, plus 0.50% and one month LIBOR plus 0.50%), plus the applicable margin. The applicable margin

96


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

for LIBOR loans under the SPL Working Capital Facility is 1.75% per annum, and the applicable margin for base rate loans under the SPL Working Capital Facility is 0.75% per annum. Interest on SPL Swing Line Loans and loans deemed made in connection with a draw upon a letter of credit (“SPL LC Loans”) is due and payable on the date the loan becomes due. Interest on LIBOR loans is due and payable at the end of each applicable LIBOR period, and interest on base rate loans is due and payable at the end of each fiscal quarter. However, if such base rate loan is converted into a LIBOR loan, interest is due and payable on that date. Additionally, if the loans become due prior to such periods, the interest also becomes due on that date.

SPL pays (1) a commitment fee equal to an annual rate of 0.70% on the average daily amount of the excess of the total commitment amount over the principal amount outstanding without giving effect to any outstanding SPL Swing Line Loans and (2) a letter of credit fee equal to an annual rate of 1.75% of the undrawn portion of all letters of credit issued under the SPL Working Capital Facility. If draws are made upon a letter of credit issued under the SPL Working Capital Facility and SPL does not elect for such draw (an “SPL LC Draw”) to be deemed an SPL LC Loan, SPL is required to pay the full amount of the SPL LC Draw on or prior to the business day following the notice of the SPL LC Draw. An SPL LC Draw accrues interest at an annual rate of 2.0% plus the base rate. As of December 31, 2019, no SPL LC Draws had been made upon any letters of credit issued under the SPL Working Capital Facility.

The SPL Working Capital Facility matures on December 31, 2020, and the outstanding balance may be repaid, in whole or in part, at any time without premium or penalty upon three business days’ notice. SPL LC Loans have a term of up to one year. SPL Swing Line Loans terminate upon the earliest of (1) the maturity date or earlier termination of the SPL Working Capital Facility, (2) the date 15 days after such SPL Swing Line Loan is made and (3) the first borrowing date for a SPL Working Capital Loan or SPL Swing Line Loan occurring at least three business days following the date the SPL Swing Line Loan is made. SPL is required to reduce the aggregate outstanding principal amount of all SPL Working Capital Loans to zero for a period of five consecutive business days at least once each year.

The SPL Working Capital Facility contains conditions precedent for extensions of credit, as well as customary affirmative and negative covenants. The obligations of SPL under the SPL Working Capital Facility are secured by substantially all of the assets of SPL as well as all of the membership interests in SPL on a pari passu basis with the SPL Senior Notes.

CQP Credit Facilities

In May 2019, Cheniere Partners terminated the remaining commitments under the 2016 CQP Credit Facilities and entered into the 2019 CQP Credit Facilities, which consisted of the $750 million CQP Term Facility, which was prepaid and terminated upon issuance of the 2029 CQP Senior Notes in September 2019, and the $750 million CQP Revolving Facility. Borrowings under the 2019 CQP Credit Facilities will be used to fund the development and construction of Train 6 of the SPL Project and for general corporate purposes, subject to a sublimit, and the 2019 CQP Credit Facilities are also available for the issuance of letters of credit.

Loans under the 2019 CQP Credit Facilities accrue interest at a variable rate per annum equal to LIBOR or the base rate (equal to the highest of the prime rate, the federal funds effective rate, as published by the Federal Reserve Bank of New York, plus 0.50%, and the adjusted one-month LIBOR plus 1.0%), plus the applicable margin. Under the CQP Term Facility, the applicable margin for LIBOR loans was 1.50% per annum, and the applicable margin for base rate loans was 0.50% per annum. Under the CQP Revolving Facility, the applicable margin for LIBOR loans is 1.25% to 2.125% per annum, and the applicable margin for base rate loans is 0.25% to 1.125% per annum, in each case depending on the then-current rating of Cheniere Partners. Interest on LIBOR loans is due and payable at the end of each applicable LIBOR period (and at the end of every three-month period within the LIBOR period, if any), and interest on base rate loans is due and payable at the end of each calendar quarter.

The 2019 CQP Credit Facilities mature on May 29, 2024. Any outstanding balance may be repaid, in whole or in part, at any time without premium or penalty, except for interest rate breakage costs. The 2019 CQP Credit Facilities contain conditions precedent for extensions of credit, as well as customary affirmative and negative covenants, and limit Cheniere Partners’ ability to make restricted payments, including distributions, to once per fiscal quarter and one true-up per fiscal quarter as long as certain conditions are satisfied.

The 2019 CQP Credit Facilities are unconditionally guaranteed and secured by a first priority lien (subject to permitted encumbrances) on substantially all of Cheniere Partners’ and the CQP Guarantors’ existing and future tangible and intangible assets and rights and equity interests in the CQP Guarantors (except, in each case, for certain excluded properties set forth in the 2019 CQP Credit Facilities).

97


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

CCH Credit Facility

In May 2018, CCH amended and restated the CCH Credit Facility to increase total commitments under the CCH Credit Facility from $4.6 billion to $6.1 billion. Borrowings are used to fund a portion of the costs of developing, constructing and placing into service the three Trains and the related facilities of the CCL Project and for related business purposes.

The CCH Credit Facility matures on June 30, 2024, with principal payments due quarterly commencing on the earlier of (1) the first quarterly payment date occurring more than three calendar months following the completion of the CCL Project as defined in the common terms agreement and (2) a set date determined by reference to the date under which a certain LNG buyer linked to the last Train of the CCL Project to become operational is entitled to terminate its SPA for failure to achieve the date of first commercial delivery for that agreement. Scheduled repayments will be based upon a 19-year tailored amortization, commencing the first full quarter after the completion of Trains 1 through 3 and designed to achieve a minimum projected fixed debt service coverage ratio of 1.50:1.

Loans under the CCH Credit Facility accrue interest at a variable rate per annum equal to, at CCH’s election, LIBOR or the base rate (determined by reference to the applicable agent’s prime rate), plus the applicable margin. The applicable margin for LIBOR loans is 1.75% and for base rate loans is 0.75%. Interest on LIBOR loans is due and payable at the end of each applicable interest period and interest on base rate loans is due and payable at the end of each quarter. The CCH Credit Facility also requires CCH to pay a commitment fee at a rate per annum equal to 40% of the margin for LIBOR loans, multiplied by the outstanding undrawn debt commitments.

The obligations of CCH under the CCH Credit Facility are secured by a first priority lien on substantially all of the assets of CCH and its subsidiaries and by a pledge by CCH HoldCo I of its limited liability company interests in CCH, on a pari passu basis with the CCH Senior Notes and the CCH Working Capital Facility.

Under the CCH Credit Facility, CCH is required to hedge not less than 65% of the variable interest rate exposure of its senior secured debt. CCH is restricted from making certain distributions under agreements governing its indebtedness generally until, among other requirements, the completion of the construction of Trains 1 through 3 of the CCL Project, funding of a debt service reserve account equal to six months of debt service and achieving a historical debt service coverage ratio and fixed projected debt service coverage ratio of at least 1.25:1.00.

The amendment and restatement of the CCH Credit Facility resulted in the recognition of $15 million of debt modification and extinguishment costs during the year ended December 31, 2018 relating to the incurrence of third party fees and write off of unamortized debt issuance costs. CCH was required to pay certain upfront fees to the agents and lenders under the CCH Credit Facility together with additional transaction fees and expenses in the aggregate amount of $53 million during the year ended December 31, 2018.

As part of the capital allocation framework announced in June 2019, we prepaid $153 million of outstanding borrowings under the CCH Credit Facility during the year ended December 31, 2019. The prepayment resulted in the recognition of debt extinguishment costs of $3 million for the year ended December 31, 2019.

CCH Working Capital Facility

In June 2018, CCH amended and restated the CCH Working Capital Facility to increase total commitments under the CCH Working Capital Facility from $350 million to $1.2 billion. The CCH Working Capital Facility is intended to be used for loans to CCH (“CCH Working Capital Loans”) and the issuance of letters of credit on behalf of CCH for certain working capital requirements related to developing and operating the CCL Project and for related business purposes. Loans under the CCH Working Capital Facility are guaranteed by the CCH Guarantors. CCH may, from time to time, request increases in the commitments under the CCH Working Capital Facility of up to the maximum allowed for working capital under the Common Terms Agreement that was entered into concurrently with the CCH Credit Facility.

Loans under the CCH Working Capital Facility, including CCH Working Capital Loans and loans made in connection with a draw upon any letter of credit (“CCH LC Loans” and collectively, the “Revolving Loans”) accrue interest at a variable rate per annum equal to LIBOR or the base rate (equal to the highest of (1) the prime rate, (2) the federal funds rate plus 0.50% and (3) one month LIBOR plus 0.50%) plus the applicable margin. The applicable margin for LIBOR Revolving Loans ranges from 1.25% to 1.75% per annum, and the applicable margin for base rate Revolving Loans ranges from 0.25% to 0.75% per annum. Interest

98


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

on Revolving Loans is due and payable on the date the loan becomes due. Interest on LIBOR Revolving Loans is due and payable at the end of each LIBOR period, and interest on base rate Revolving Loans is due and payable at the end of each quarter.

CCH pays (1) a commitment fee equal to an annual rate of 40% of the applicable margin for LIBOR Revolving Loans on the average daily amount of the excess of the total commitment amount over the principal amount outstanding, (2) a letter of credit fee equal to an annual rate equal to the applicable margin for LIBOR Revolving Loans on the undrawn portion of all letters of credit issued under the CCH Working Capital Facility and (3) a letter of credit fronting fee equal to an annual rate of 0.20% of the undrawn portion of all fronted letters of credit. Each of these fees is payable quarterly in arrears.
 
If draws are made upon a letter of credit issued under the CCH Working Capital Facility and CCH does not elect for such draw (a “CCH LC Draw”) to be deemed a CCH LC Loan, CCH is required to pay the full amount of the CCH LC Draw on or prior to the business day following the notice of the CCH LC Draw. A CCH LC Draw accrues interest at an annual rate of 2.00% plus the base rate.

CCH was required to pay certain upfront fees to the agents and lenders under the CCH Working Capital Facility together with additional transaction fees and expenses in the aggregate amount of $14 million during the year ended December 31, 2018.

The CCH Working Capital Facility matures on June 29, 2023 and CCH may prepay the Revolving Loans at any time without premium or penalty upon three business days’ notice and may re-borrow at any time. CCH LC Loans have a term of up to one year. CCH is required to reduce the aggregate outstanding principal amount of all CCH Working Capital Loans to zero for a period of five consecutive business days at least once each year.

The CCH Working Capital Facility contains conditions precedent for extensions of credit, as well as customary affirmative and negative covenants. The obligations of CCH under the CCH Working Capital Facility are secured by substantially all of the assets of CCH and the CCH Guarantors as well as all of the membership interests in CCH and each of the CCH Guarantors on a pari passu basis with the CCH Senior Notes and the CCH Credit Facility.

Cheniere Revolving Credit Facility

In December 2018, we amended and restated the Cheniere Revolving Credit Facility to increase total commitments under the Cheniere Revolving Credit Facility from $750 million to $1.25 billion. The Cheniere Revolving Credit Facility is intended to fund, through loans and letters of credit, equity capital contributions to CCH HoldCo II and its subsidiaries for the development of the CCL Project and, provided that certain conditions are met, for general corporate purposes.

The Cheniere Revolving Credit Facility matures on December 13, 2022 and contains representations, warranties and affirmative and negative covenants customary for companies like us with lenders of the type participating in the Cheniere Revolving Credit Facility that limit our ability to make restricted payments, including distributions, unless certain conditions are satisfied, as well as limitations on indebtedness, guarantees, hedging, liens, investments and affiliate transactions. Under the Cheniere Revolving Credit Facility, we are required to ensure that the sum of our unrestricted cash and the amount of undrawn commitments under the Cheniere Revolving Credit Facility is at least equal to the lesser of (1) 20% of the commitments under the Cheniere Revolving Credit Facility and (2) $200 million (the “Liquidity Covenant”).

From and after the time at which certain specified conditions are met (the “Trigger Point”), we will have increased flexibility under the Cheniere Revolving Credit Facility to, among other things, (1) make restricted payments and (2) raise incremental commitments. The Trigger Point will occur once (1) completion has occurred for each of Train 1 of the CCL Project (as defined in the CCH Indenture) and Train 5 of the SPL Project (as defined in SPL’s common terms agreement), which occurred in February 2019 and March 2019, respectively, (2) the aggregate principal amount of outstanding loans plus drawn and unreimbursed letters of credit under the Cheniere Revolving Credit Facility is less than or equal to 10% of aggregate commitments under the Cheniere Revolving Credit Facility and (3) we elect on a go-forward basis to be governed by a non-consolidated leverage ratio covenant not to exceed 5.75:1.00 (the “Springing Leverage Covenant”), which following such election will apply at any time that the aggregate principal amount of outstanding loans plus drawn and unreimbursed letters of credit under the Cheniere Revolving Credit Facility is greater than 30% of aggregate commitments under the Cheniere Revolving Credit Facility. Following the Trigger Point, at any time that the Springing Leverage Covenant is in effect, the Liquidity Covenant will not apply.

Loans under the Cheniere Revolving Credit Facility accrue interest at a variable rate per annum equal to LIBOR or the base rate (equal to the highest of (1) the prime rate, (2) the federal funds rate plus 0.50% and (3) one month LIBOR plus 1.00%), plus

99


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

the applicable margin. The applicable margin for LIBOR loans ranges from 1.75% to 2.50% per annum, and the applicable margin for base rate loans ranges from 0.75% to 1.50% per annum, in each case, based on the credit ratings then in effect assigned to loans under the Cheniere Revolving Credit Facility. Interest on LIBOR loans is due and payable at the end of each LIBOR period, and interest on base rate loans is due and payable at the end of each calendar quarter. We will also pay (1) prior to the Trigger Point, a commitment fee on the average daily amount of undrawn commitments at an annual rate of 0.75%, payable quarterly in arrears and (2) from and after the Trigger Point, a commitment fee on the average daily amount of undrawn commitments at a rate equal to 30% multiplied by the applicable margin for LIBOR loans then in effect. We will also pay a letter of credit fee at an annual rate equal to the applicable margin for LIBOR loans on the undrawn portion of all letters of credit issued under the Cheniere Revolving Credit Facility. Draws on any letters of credit will accrue interest at an annual rate equal to the base rate plus 2.0%.

The Cheniere Revolving Credit Facility is secured by a first priority security interest (subject to permitted liens and other customary exceptions) in substantially all of our assets, including our interests in our direct subsidiaries (excluding CCH HoldCo II and certain other subsidiaries).

Convertible Notes

Below is a summary of our convertible notes outstanding as of December 31, 2019 (in millions):
 
 
2021 Cheniere Convertible Unsecured Notes
 
2025 CCH HoldCo II Convertible Senior Notes
 
2045 Cheniere Convertible Senior Notes
Aggregate original principal
 
$
1,000

 
$
1,000

 
$
625

Debt component, net of discount and debt issuance costs
 
$
1,221

 
$
1,567

 
$
314

Equity component
 
$
211

 
$

 
$
194

Maturity date
 
May 28, 2021

 
May 13, 2025

 
March 15, 2045

Contractual interest rate
 
4.875
%
 
11.0
%
 
4.25
%
Effective interest rate (1)
 
8.2
%
 
12.0
%
 
9.4
%
Remaining debt discount and debt issuance costs amortization period (2)
 
1.4 years

 
0.8 years

 
25.2 years

 

(1)
Rate to accrete the discounted carrying value of the convertible notes to the face value over the remaining amortization period.
(2)
We amortize any debt discount and debt issuance costs using the effective interest over the period through contractual maturity except for the 2025 CCH HoldCo II Convertible Senior Notes, which are amortized through the date they are first convertible by holders into our common stock.
2021 Cheniere Convertible Unsecured Notes
In November 2014, we issued the 2021 Cheniere Convertible Unsecured Notes on a private placement basis in reliance on the exemption from registration provided for under section 4(a)(2) of the Securities Act and Regulation S promulgated thereunder. The 2021 Cheniere Convertible Unsecured Notes accrue interest at a rate of 4.875% per annum, which is payable in kind semi-annually in arrears by increasing the principal amount of the 2021 Cheniere Convertible Unsecured Notes outstanding. Beginning one year after the closing date, the 2021 Cheniere Convertible Unsecured Notes will be convertible at the option of the holder into our common stock at the then applicable conversion rate, provided that the closing price of our common stock is greater than or equal to the conversion price on the conversion date. The initial conversion price was $93.64 and is subject to adjustment upon the occurrence of certain specified events. We have the option to satisfy the conversion obligation with cash, common stock or a combination thereof.
Under GAAP, certain convertible debt instruments that may be settled in cash upon conversion are required to be separately accounted for as liability (debt) and equity (conversion option) components of the instrument in a manner that reflects the issuer’s non-convertible debt borrowing rate. We determined that the fair value of the debt component was $809 million and the residual value of the equity component was $191 million as of the issuance date. As of December 31, 2019 and 2018, the carrying value of the equity component was $211 million and $209 million, respectively. The debt component is accreted to the total principal amount due at maturity by amortizing the debt discount. The effective rate of interest to amortize the debt discount and debt

100


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

issuance costs was approximately 8.2% and 8.4% as of December 31, 2019 and 2018, respectively. As of December 31, 2019, the if-converted value of the 2021 Cheniere Convertible Unsecured Notes did not exceed the principal balance.
2025 CCH HoldCo II Convertible Senior Notes

In May 2015, CCH HoldCo II issued the 2025 CCH HoldCo II Convertible Senior Notes on a private placement basis in reliance on the exemption from registration provided for under section 4(a)(2) of the Securities Act. The 2025 CCH HoldCo II Convertible Senior Notes were issued pursuant to the amended and restated note purchase agreement entered into among CCH HoldCo II, EIG Management Company, LLC, The Bank of New York Mellon, us and the note purchasers. The $1.0 billion principal of the 2025 CCH HoldCo II Convertible Senior Notes are being used to partially fund costs associated with Trains 1 through 3 of the CCL Project. The 2025 CCH HoldCo II Convertible Senior Notes bear interest at a rate of 11.0% per annum, which is payable quarterly in arrears. Prior to the substantial completion of Train 2 of the CCL Project, interest on the 2025 CCH HoldCo II Convertible Senior Notes was paid entirely in kind. Following this date, the interest generally must be paid in cash; however, a portion of the interest may be paid in kind under certain specified circumstances. The 2025 CCH HoldCo II Convertible Senior Notes are secured by a pledge by us of 100% of the equity interests in CCH HoldCo II, and a pledge by CCH HoldCo II of 100% of the equity interests in CCH HoldCo I. In addition, the 2025 CCH HoldCo II Convertible Senior Notes are secured by a security interest in the account into which all distributions from CCH HoldCo I to CCH HoldCo II must be deposited.
At CCH HoldCo II’s option, the outstanding 2025 CCH HoldCo II Convertible Senior Notes are convertible into our common stock on or after March 1, 2020, provided the total market capitalization of Cheniere at that time is not less than $10.0 billion and certain other conditions are satisfied (the “Eligible Conversion Date”). The conversion price for 2025 CCH HoldCo II Convertible Senior Notes converted at CCH HoldCo II’s option is the lower of (1) a 10% discount to the average of the daily volume-weighted average price (“VWAP”) of our common stock for the 90 trading day period prior to the date on which notice of conversion is provided and (2) a 10% discount to the closing price of our common stock on the trading day preceding the date on which notice of conversion is provided. At the option of the holders, the 2025 CCH HoldCo II Convertible Senior Notes are convertible on or after the six-month anniversary of the Eligible Conversion Date, provided the total market capitalization of Cheniere at that time is not less than $10.0 billion and certain other conditions are satisfied, at a conversion price equal to the average of the daily VWAP of our common stock for the 90 trading day period prior to the date on which notice of conversion is provided. Conversions are also subject to various limitations and conditions.
CCH HoldCo II is restricted from making distributions to Cheniere under agreements governing its indebtedness generally until, among other requirements, a historical debt service coverage ratio and a projected fixed debt service coverage ratio of 1.20:1.00 are achieved.

In May 2018, the amended and restated note purchase agreement under which the 2025 CCH HoldCo II Convertible Senior Notes were issued was subsequently amended in connection with commercialization and financing of Train 3 of the CCL Project and to provide the note holders with certain prepayment rights related thereto.
2045 Cheniere Convertible Senior Notes

In March 2015, we issued the unsecured 2045 Cheniere Convertible Senior Notes to certain investors through a registered direct offering. The 2045 Cheniere Convertible Senior Notes were issued with an original issue discount of 20% and accrue interest at a rate of 4.25% per annum, which is payable semi-annually in arrears. We have the right, at our option, at any time after March 15, 2020, to redeem all or any part of the 2045 Cheniere Convertible Senior Notes at a redemption price payable in cash equal to the accreted amount of the 2045 Cheniere Convertible Senior Notes to be redeemed, plus accrued and unpaid interest, if any, to such redemption date. The conversion rate will initially equal 7.2265 shares of our common stock per $1,000 principal amount of the 2045 Cheniere Convertible Senior Notes, which corresponds to an initial conversion price of approximately $138.38 per share of our common stock. The conversion rate is subject to adjustment upon the occurrence of certain specified events. We have the option to satisfy the conversion obligation with cash, common stock or a combination thereof.

We determined that the fair value of the debt component of the 2045 Cheniere Convertible Senior Notes was $304 million and the residual value of the equity component was $196 million as of the issuance date, excluding debt issuance costs and original issue discount. As of both December 31, 2019 and 2018, the carrying value of the equity component was $194 million. The debt component is accreted to the total principal amount due at maturity by amortizing the debt discount and debt issuance costs. The effective rate of interest to amortize the debt discount and debt issuance costs was approximately 9.4% as of both December 31,

101


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

2019 and 2018. As of December 31, 2019, the if-converted value of the 2045 Cheniere Convertible Senior Notes did not exceed the principal balance.
Restrictive Debt Covenants

As of December 31, 2019, each of our issuers was in compliance with all covenants related to their respective debt agreements.

Interest Expense

Total interest expense, including interest expense related to our convertible notes, consisted of the following (in millions):
 
 
Year Ended December 31,
 
 
2019
 
2018
 
2017
Interest cost on convertible notes:
 
 
 
 
 
 
Interest per contractual rate
 
$
256

 
$
237

 
$
219

Amortization of debt discount
 
40

 
35

 
29

Amortization of debt issuance costs
 
12

 
9

 
7

Total interest cost related to convertible notes
 
308

 
281

 
255

Interest cost on debt and finance leases excluding convertible notes
 
1,538


1,397


1,271

Total interest cost
 
1,846

 
1,678

 
1,526

Capitalized interest
 
(414
)
 
(803
)
 
(779
)
Total interest expense, net
 
$
1,432

 
$
875

 
$
747



Fair Value Disclosures

The following table shows the carrying amount and estimated fair value of our debt (in millions):
 
 
December 31, 2019
 
December 31, 2018
 
 
Carrying
Amount
 
Estimated
Fair Value
 
Carrying
Amount
 
Estimated
Fair Value
Senior notes (1)
 
$
22,700

 
$
24,650

 
$
19,700

 
$
19,901

2037 SPL Senior Notes (2)
 
800

 
934

 
800

 
817

4.80% CCH Senior Notes (2)
 
727

 
830

 

 

3.925% CCH Senior Notes (2)
 
475

 
495

 

 

Credit facilities (3)
 
3,283

 
3,283

 
5,395

 
5,395

2021 Cheniere Convertible Unsecured Notes (2)
 
1,278

 
1,312

 
1,218

 
1,236

2025 CCH HoldCo II Convertible Senior Notes (2)
 
1,578

 
1,807

 
1,455

 
1,612

2045 Cheniere Convertible Senior Notes (4)
 
625

 
498

 
625

 
431

 
(1)
Includes the SPL Senior Notes except the 2037 SPL Senior Notes, the CQP Senior Notes and the 144A CCH Senior Notes. The Level 2 estimated fair value was based on quotes obtained from broker-dealers or market makers of these senior notes and other similar instruments.
(2)
The Level 3 estimated fair value was calculated based on inputs that are observable in the market or that could be derived from, or corroborated with, observable market data, including our stock price and interest rates based on debt issued by parties with comparable credit ratings to us and inputs that are not observable in the market. 
(3)
Includes SPL Working Capital Facility, 2016 CQP Credit Facilities, 2019 CQP Credit Facilities, CCH Credit Facility, CCH Working Capital Facility, Cheniere Revolving Credit Facility and Cheniere Marketing trade finance facilities. The Level 3 estimated fair value approximates the principal amount because the interest rates are variable and reflective of market rates and the debt may be repaid, in full or in part, at any time without penalty. 
(4)
The Level 1 estimated fair value was based on unadjusted quoted prices in active markets for identical liabilities that we had the ability to access at the measurement date.


102


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

NOTE 12—LEASES

Our leased assets consist primarily of (1) LNG vessel time charters (“vessel charters”), (2) tug vessels, (3) office space and facilities and (4) land sites, all of which are classified as operating leases except for our tug vessels at the Corpus Christi LNG terminal, which are classified as finance leases.
ASC 842 requires a lessee to recognize leases on its balance sheet by recording a lease liability representing the obligation to make future lease payments and a right-of-use asset representing the right to use the underlying asset for the lease term. As our leases generally do not provide an implicit rate, in order to calculate the lease liability, we discounted our expected future lease payments using our relevant subsidiary’s incremental borrowing rate at the later of January 1, 2019 or the commencement date of the lease. The incremental borrowing rate is an estimate of the rate of interest that a given subsidiary would have to pay to borrow on a collateralized basis over a similar term to that of the lease term.

Many of our leases contain renewal options exercisable at our sole discretion. Options to renew a lease are included in the lease term and recognized as part of the right-of-use asset and lease liability only to the extent they are reasonably certain to be exercised, such as when necessary to satisfy obligations that existed at the execution of the lease or when the non-renewal would otherwise result in a significant economic penalty.

We have elected the practical expedient to omit leases with an initial term of 12 months or less (“short-term lease”) from recognition on the balance sheet. We recognize short-term lease payments on a straight-line basis over the lease term and variable payments under short-term leases in the period in which the obligation is incurred.

Certain of our leases contain non-lease components which are not separated from the lease components when calculating the right-of-use asset and lease liability per our use of the practical expedient to combine both components of an arrangement for all classes of leased assets.

Certain of our leases also contain variable payments, such as inflation, that are not included when calculating the right-of-use asset and lease liability unless the payments are in-substance fixed.

We recognize lease expense for operating leases on a straight-line basis over the lease term. We recognize lease expense for finance leases as the sum of the amortization of the right-of-use assets on a straight-line basis and the interest on lease liabilities using the effective interest method over the lease term.

The following table shows the classification and location of our right-of-use assets and lease liabilities on our Consolidated Balance Sheets (in millions):
 
Consolidated Balance Sheet Location
 
December 31, 2019
Right-of-use assets—Operating
Operating lease assets, net
 
$
439

Right-of-use assets—Financing
Property, plant and equipment, net
 
56

Total right-of-use assets
 
 
$
495

 
 
 
 
Current operating lease liabilities
Current operating lease liabilities
 
$
236

Current finance lease liabilities
Other current liabilities
 
1

Non-current operating lease liabilities
Non-current operating lease liabilities
 
189

Non-current finance lease liabilities
Non-current finance lease liabilities
 
58

Total lease liabilities
 
 
$
484




103


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

The following table shows the classification and location of our lease cost on our Consolidated Statements of Operations (in millions):
 
Consolidated Statement of Operations Location
 
Year Ended December 31, 2019
Operating lease cost (1)
Operating costs and expenses (2)
 
$
612

Finance lease cost:
 
 


Amortization of right-of-use assets
Depreciation and amortization expense
 
3

Interest on lease liabilities
Interest expense, net of capitalized interest
 
10

Total lease cost
 
 
$
625

 
(1)
Includes $230 million of short-term lease costs and $7 million of variable lease costs paid to the lessor.
(2)
Presented in cost of sales, operating and maintenance expense or selling, general and administrative expense consistent with the nature of the asset under lease.

During the years ended December 31, 2018 and 2017, we recognized rental expense for all operating leases of $335 million and $199 million, respectively.

Future annual minimum lease payments for operating and finance leases as of December 31, 2019 are as follows (in millions): 
Years Ending December 31,
Operating Leases (1)
 
Finance Leases
2020
$
250

 
$
11

2021
56

 
10

2022
22

 
10

2023
21

 
10

2024
21

 
10

Thereafter
160

 
136

Total lease payments
530

 
187

Less: Interest
(105
)
 
(128
)
Present value of lease liabilities
$
425

 
$
59

 
(1)
Does not include $2.0 billion of legally binding minimum lease payments primarily for vessel charters which were executed as of December 31, 2019 but will commence primarily between 2020 and 2022 and have fixed minimum lease terms of up to seven years.

Future annual minimum lease payments for operating and capital leases as of December 31, 2018, prepared in accordance with accounting standards prior to the adoption of ASC 842, were as follows (in millions):
Years Ending December 31,
Operating Leases (1)
 
Capital Leases (2)
2019 (3)
$
380

 
$
5

2020
184

 
5

2021
238

 
5

2022
264

 
5

2023
264

 
5

Thereafter
999

 
73

Total lease payments
2,329

 
98

Less: Interest

 
(39
)
Present value of lease liabilities
$
2,329

 
$
59

 
(1)
Includes certain lease option renewals that are reasonably assured and payments for certain non-lease components. Also includes $79 million in payments for short-term leases and $1.6 billion in payments for LNG vessel charters which were previously executed but will commence primarily between 2020 and 2021.
(2)
Does not include payments for non-lease components of $98 million.
(3)
Does not include $43 million in aggregate payments we will receive from our LNG vessel subcharters.


104


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

The following table shows the weighted-average remaining lease term (in years) and the weighted-average discount rate for our operating leases and finance leases:
 
December 31, 2019
 
Operating Leases
 
Finance Leases
Weighted-average remaining lease term (in years)
8.4
 
18.7
Weighted-average discount rate (1)
5.2%
 
16.2%
 
(1)
The finance leases commenced prior to the adoption of ASC 842. In accordance with previous accounting guidance, the implied rate is based on the fair value of the underlying assets.

The following table includes other quantitative information for our operating and finance leases (in millions):
 
Year Ended December 31, 2019
Cash paid for amounts included in the measurement of lease liabilities:
 
Operating cash flows from operating leases
$
389

Operating cash flows from finance leases
9

Financing cash flows from finance leases

Right-of-use assets obtained in exchange for new operating lease liabilities
235



LNG Vessel Subcharters

From time to time, we sublease certain LNG vessels under charter to third parties while retaining our existing obligation to the original lessor. We have elected the practical expedient for lessors to combine lease and non-lease components and since the lease component is the predominant component of each arrangement, these subleases are accounted for as operating leases. The subleases have lease terms of up to one year and many contain short-term renewal options exercisable at the discretion of the third party. As of December 31, 2019, we had $9 million in future minimum sublease payments to be received from LNG vessel subcharters, which will be recognized entirely within 2020. We recognize fixed sublease income on a straight-line basis over the lease term of the sublease while variable sublease income is recognized when earned. We recognized $144 million of sublease income, including $22 million of variable lease payments, during the year ended December 31, 2019 in other revenues on our Consolidated Statements of Operations.

NOTE 13—REVENUES FROM CONTRACTS WITH CUSTOMERS

The following table represents a disaggregation of revenue earned from contracts with customers during the years ended December 31, 2019, 2018 and 2017 (in millions):
 
 
Year Ended December 31,
 
 
2019
 
2018
 
2017
LNG revenues
 
$
8,817

 
$
7,581

 
$
5,361

Regasification revenues
 
266

 
261

 
260

Other revenues
 
74

 
54

 
24

Total revenues from customers
 
9,157

 
7,896

 
5,645

Net derivative gains (losses) (1)
 
429

 
(9
)
 
(44
)
Other (2)
 
144

 
100

 

Total revenues
 
$
9,730

 
$
7,987

 
$
5,601

 
(1)
See Note 7—Derivative Instruments for additional information about our derivatives.
(2)
Includes revenues from LNG vessel subcharters. See Note 12—Leases for additional information about our subleases.

LNG Revenues

We have entered into numerous SPAs with third party customers for the sale of LNG on a free on board (“FOB”) (delivered to the customer at either the Sabine Pass or Corpus Christi LNG terminal) or delivered at terminal (“DAT”) (delivered to the customer at their LNG receiving terminal) basis. Our customers generally purchase LNG for a price consisting of a fixed fee per MMBtu of LNG (a portion of which is subject to annual adjustment for inflation) plus a variable fee per MMBtu of LNG equal

105


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

to approximately 115% of Henry Hub. The fixed fee component is the amount payable to us regardless of a cancellation or suspension of LNG cargo deliveries by the customers. The variable fee component is the amount generally payable to us only upon delivery of LNG plus all future adjustments to the fixed fee for inflation. The SPAs and contracted volumes to be made available under the SPAs are not tied to a specific Train; however, the term of each SPA generally commences upon the date of first commercial delivery of a specified Train.

We intend to primarily use LNG sourced from our Sabine Pass or Corpus Christi terminals to provide contracted volumes to our customers. However, we supplement this LNG with volumes procured from third parties. LNG revenues recognized from LNG that was procured from third parties was $268 million, $745 million and $981 million for the years ended December 31, 2019, 2018 and 2017, respectively.

Revenues from the sale of LNG are recognized at a point in time when the LNG is delivered to the customer, either at the Sabine Pass or Corpus Christi LNG terminal or at the customer’s LNG receiving terminal, based on the terms of the contract, which is the point legal title, physical possession and the risks and rewards of ownership transfer to the customer. Each individual molecule of LNG is viewed as a separate performance obligation. The stated contract price (including both fixed and variable fees) per MMBtu in each LNG sales arrangement is representative of the stand-alone selling price for LNG at the time the contract was negotiated. We have concluded that the variable fees meet the exception for allocating variable consideration to specific parts of the contract. As such, the variable consideration for these contracts is allocated to each distinct molecule of LNG and recognized when that distinct molecule of LNG is delivered to the customer. Because of the use of the exception, variable consideration related to the sale of LNG is also not included in the transaction price.

When we sell LNG on a DAT basis, we consider all transportation costs, including vessel chartering, loading/unloading and canal fees, as fulfillment costs and not as separate services provided to the customer within the arrangement, regardless of whether or not such activities occur prior to or after the customer obtains control of the LNG. We expense fulfillment costs as incurred unless otherwise dictated by GAAP.

Fees received pursuant to SPAs are recognized as LNG revenues only after substantial completion of the respective Train. Prior to substantial completion, sales generated during the commissioning phase are offset against the cost of construction for the respective Train, as the production and removal of LNG from storage is necessary to test the facility and bring the asset to the condition necessary for its intended use.

Regasification Revenues

The Sabine Pass LNG terminal has operational regasification capacity of approximately 4 Bcf/d. Approximately 2 Bcf/d of the regasification capacity at the Sabine Pass LNG terminal has been reserved under two long-term TUAs with unaffiliated third-party customers, under which they are required to pay fixed monthly fees regardless of their use of the LNG terminal. Each of the customers has reserved approximately 1 Bcf/d of regasification capacity. The customers are each obligated to make monthly capacity payments to SPLNG aggregating approximately $125 million annually for 20 years that commenced in 2009, which is representative of fixed consideration in the contract. A portion of this fee is adjusted annually for inflation which is considered variable consideration. The remaining capacity of the Sabine Pass LNG terminal has been reserved by SPL, for which the associated revenues are eliminated in consolidation.

Because SPLNG is continuously available to provide regasification service on a daily basis with the same pattern of transfer, we have concluded that SPLNG provides a single performance obligation to its customers on a continuous basis over time. We have determined that an output method of recognition based on elapsed time best reflects the benefits of this service to the customer and accordingly, LNG regasification capacity reservation fees are recognized as regasification revenues on a straight-line basis over the term of the respective TUAs.

In 2012, SPL entered into a partial TUA assignment agreement with Total Gas & Power North America, Inc. (“Total”), whereby upon substantial completion of Train 5 of the SPL Project, SPL gained access to substantially all of Total’s capacity and other services provided under Total’s TUA with SPLNG. This agreement provides SPL with additional berthing and storage capacity at the Sabine Pass LNG terminal that may be used to provide increased flexibility in managing LNG cargo loading and unloading activity, permit SPL to more flexibly manage its LNG storage capacity and accommodate the development of Train 6. Notwithstanding any arrangements between Total and SPL, payments required to be made by Total to SPLNG will continue to be made by Total to SPLNG in accordance with its TUA and we continue to recognize the payments received from Total as revenue.

106


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

During the years ended December 31, 2019, 2018 and 2017, SPL recorded $104 million, $30 million and $23 million, respectively, as operating and maintenance expense under this partial TUA assignment agreement.

Contract Assets and Liabilities
The following table shows our contract assets, which we classify as other non-current assets, net on our Consolidated Balance Sheets (in millions):
 
 
December 31,
 
 
2019
 
2018
Contract assets
 
$
18

 
$



Contract assets represent our right to consideration for transferring goods or services to the customer under the terms of a sales contract when the associated consideration is not yet due. Changes in contract assets during the year ended December 31, 2019 were primarily attributable to revenue recognized due to the delivery of LNG under certain SPAs for which the associated consideration was not yet due.

The following table reflects the changes in our contract liabilities, which we classify as deferred revenue on our Consolidated Balance Sheets (in millions):
 
 
Year Ended December 31,
 
 
2019
 
2018
Deferred revenues, beginning of period
 
$
139

 
$
111

Cash received but not yet recognized
 
161

 
139

Revenue recognized from prior period deferral
 
(139
)
 
(111
)
Deferred revenues, end of period
 
$
161

 
$
139



We record deferred revenue when we receive consideration, or such consideration is unconditionally due from a customer, prior to transferring goods or services to the customer under the terms of a sales contract. Changes in deferred revenue during the years ended December 31, 2019 and 2018 are primarily attributable to differences between the timing of revenue recognition and the receipt of advance payments related to delivery of LNG under certain SPAs.

Transaction Price Allocated to Future Performance Obligations

Because many of our sales contracts have long-term durations, we are contractually entitled to significant future consideration which we have not yet recognized as revenue. The following table discloses the aggregate amount of the transaction price that is allocated to performance obligations that have not yet been satisfied as of December 31, 2019 and 2018:
 
 
December 31, 2019
 
December 31, 2018
 
 
Unsatisfied Transaction Price (in billions)
 
Weighted Average Recognition Timing (years) (1)
 
Unsatisfied Transaction Price (in billions)
 
Weighted Average Recognition Timing (years) (1)
LNG revenues
 
$
106.4

 
11
 
$
106.6

 
11
Regasification revenues
 
2.4

 
5
 
2.6

 
6
Total revenues
 
$
108.8

 

 
$
109.2

 
 
 
    
(1)
The weighted average recognition timing represents an estimate of the number of years during which we shall have recognized half of the unsatisfied transaction price.

We have elected the following exemptions which omit certain potential future sources of revenue from the table above:
(1)
We omit from the table above all performance obligations that are part of a contract that has an original expected duration of one year or less.
(2)
The table above excludes substantially all variable consideration under our SPAs and TUAs. We omit from the table above all variable consideration that is allocated entirely to a wholly unsatisfied performance obligation or to a wholly unsatisfied promise to transfer a distinct good or service that forms part of a single performance obligation when that performance obligation qualifies as a series. The amount of revenue from variable fees that is not included in the transaction price will vary based on the future prices of Henry Hub throughout the contract terms, to the extent

107


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

customers elect to take delivery of their LNG, and adjustments to the consumer price index. Certain of our contracts contain additional variable consideration based on the outcome of contingent events and the movement of various indexes. We have not included such variable consideration in the transaction price to the extent the consideration is considered constrained due to the uncertainty of ultimate pricing and receipt. Approximately 52% and 56% of our LNG revenues from contracts with a duration of over one year during the years ended December 31, 2019 and 2018, respectively, were related to variable consideration received from customers. During each of the years ended December 31, 2019 and 2018, approximately 3% of our regasification revenues were related to variable consideration received from customers.

We have entered into contracts to sell LNG that are conditioned upon one or both of the parties achieving certain milestones such as reaching FID on a certain liquefaction Train, obtaining financing or achieving substantial completion of a Train and any related facilities. These contracts are considered completed contracts for revenue recognition purposes and are included in the transaction price above when the conditions are considered probable of being met.

NOTE 14—INCOME TAXES

Components of income before income taxes and non-controlling interest on our Consolidated Statements of Operations for the years ended December 31, 2019, 2018 and 2017 are as follows (in millions): 
 
 
Year Ended December 31,
 
 
2019
 
2018
 
2017
U.S.
 
$
289

 
$
997

 
$
30

International
 
426

 
230

 
536

Total income before income taxes and non-controlling interest
 
$
715

 
$
1,227

 
$
566


Income tax provision (benefit) included in our reported net income consisted of the following (in millions): 
 
 
Year Ended December 31,
 
 
2019
 
2018
 
2017
Current:
 
 
 
 
 
 
Federal
 
$

 
$

 
$

State
 

 
2

 

Foreign
 
4

 
30

 
6

Total current
 
4

 
32

 
6

 
 
 
 
 
 
 
Deferred:
 
 
 
 
 
 
Federal
 
(475
)
 

 

State
 
(46
)
 

 

Foreign
 

 
(5
)
 
(3
)
Total deferred
 
(521
)
 
(5
)
 
(3
)
Total income tax provision (benefit)
 
$
(517
)
 
$
27

 
$
3


 

108


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

The reconciliation of the federal statutory income tax rate to our effective income tax rate is as follows: 
 
 
Year Ended December 31,
 
 
2019
 
2018
 
2017
U.S. federal statutory tax rate
 
21.0
 %
 
21.0
 %
 
35.0
 %
Non-controlling interest
 
(17.2
)%
 
(11.4
)%
 
2.9
 %
State tax rate
 
(5.4
)%
 
(0.4
)%
 
(0.2
)%
U.S. tax reform rate change
 
 %
 
 %
 
71.4
 %
Executive compensation
 
1.3
 %
 
0.5
 %
 
0.9
 %
Share-based compensation
 
(0.3
)%
 
(0.5
)%
 
(6.2
)%
Nondeductible interest expense
 
5.0
 %
 
2.6
 %
 
8.5
 %
Foreign earnings taxed in the U.S.
 
6.7
 %
 
1.4
 %
 
 %
Foreign rate differential
 
(11.4
)%
 
(1.1
)%
 
(0.7
)%
Tax credits
 
(5.2
)%
 
(0.6
)%
 
(1.0
)%
Other
 
1.7
 %
 
0.5
 %
 
(0.4
)%
Valuation allowance
 
(68.5
)%
 
(9.8
)%
 
(109.7
)%
Effective tax rate
 
(72.3
)%
 
2.2
 %
 
0.5
 %


Significant components of our deferred tax assets and liabilities at December 31, 2019 and 2018 are as follows (millions): 
 
 
December 31,
 
 
2019
 
2018
Deferred tax assets
 
 
 
 
Net operating loss carryforwards and credits
 
 
 
 
Federal
 
$
2,860

 
$
848

Foreign
 
5

 
7

State
 
249

 
189

Federal and state tax credits
 
64

 
28

Disallowed business interest expense carryforward
 
154

 
19

Deferred gain
 
46

 
46

Other
 
97

 
50

Less: valuation allowance
 
(196
)
 
(686
)
Total deferred tax assets
 
3,279

 
501

 
 
 
 
 
Deferred tax liabilities
 
 

 
 

Investment in limited partnership
 
(554
)
 
(375
)
Convertible debt
 
(51
)
 
(59
)
Property, plant and equipment
 
(2,110
)
 
(48
)
Other
 
(35
)
 
(11
)
Total deferred tax liabilities
 
(2,750
)
 
(493
)
 
 
 
 
 
Net deferred tax assets
 
$
529

 
$
8


We recognize deferred tax assets and liabilities for future tax consequences arising from differences between the carrying amounts of existing assets and liabilities under GAAP and their respective tax bases, and for net operating loss (“NOL”) carryforwards and tax credit carryforwards. We evaluate the recoverability of our deferred tax assets as of each reporting date, weighing all positive and negative evidence, and establish a valuation allowance if we determine that it is more likely than not that some or all of our deferred tax assets will not be realized. The assessment requires significant judgment and is performed in each of our applicable jurisdictions. In making such determination, we consider various factors such as historical profitability, future projections of sustained profitability, reversal of existing deferred tax liabilities, construction and operational milestones reached on our Liquefaction Projects and our long-term SPAs achieving date of first commercial delivery. We recorded a valuation allowance of $686 million in 2018 against our deferred tax assets due to being in a three-year cumulative loss position at the time, in addition to ongoing construction and performance risks related to our Liquefaction Projects. After weighing 2019 positive and negative evidence, we determined that sufficient positive evidence existed to support releasing the valuation allowance against significantly all of our federal deferred tax assets and a portion of our state deferred tax assets. The positive evidence supporting such conclusion included successful completion and subsequent operations of Trains 1 and 2 of the CCL Project and Train 5 of the SPL Project, our transitioning from a three-year cumulative loss position in 2018 to a three-year cumulative income position

109


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

in 2019, commencing commercial delivery on 13 of our long term customer SPAs and forecasts of sustained future profitability. As a result, we recorded a decrease in valuation allowance of $490 million comprised of a $493 million federal valuation allowance release and a $49 million state valuation allowance release, partially offset by an increase in the valuation allowance of $52 million in various other state and foreign tax jurisdictions. We maintained a valuation allowance of $196 million at December 31, 2019 primarily against state NOL carryforward deferred tax assets, for which we continue to believe the more likely than not recognition threshold was not met.

At December 31, 2019, we had federal and state NOL carryforwards of approximately $13.6 billion and $3.1 billion, respectively. These NOL carryforwards will expire between 2021 and 2039. At December 31, 2019, we had federal and state tax credit carryforwards of $61 million and $3 million, respectively. The federal tax credit carryforwards include investment tax credit carryforwards of $52 million related to capital equipment placed in service for our Liquefaction Projects. We account for our federal investment tax credits under the flow-through method. The federal and state tax credit carryforwards will expire between 2027 and 2039.

Changes in the balance of unrecognized tax benefits are as follows (in millions): 
 
Year Ended December 31,
 
2019
 
2018
Balance at beginning of the year
$
61

 
$
62

Additions based on tax positions related to current year

 

Additions for tax positions of prior years

 

Reductions for tax positions of prior years

 
(1
)
Settlements

 

U.S. tax reform rate change

 

Balance at end of the year
$
61

 
$
61

 

If recognized, $52 million of unrecognized tax benefits would affect our effective tax rate in future periods. Currently, we do not recognize any accrued liabilities, interest and penalties associated with the unrecognized tax benefits provided above in our Consolidated Statements of Operations or our Consolidated Balance Sheets because any settlement of uncertain tax positions would result in an adjustment to our NOL carryforward. We recognize interest and penalties related to income tax matters as part of income tax expense.

We experienced an ownership change within the provisions of U.S. Internal Revenue Code (“IRC”) Section 382 in 2008, 2010 and 2012. An analysis of the annual limitation on the utilization of our NOLs was performed in accordance with IRC Section 382. It was determined that IRC Section 382 will not limit the use of our NOLs over the carryover period. We continue to monitor trading activity in our shares which may cause an additional ownership change which could ultimately affect our ability to fully utilize our existing NOL carryforwards.

We are subject to tax in the U.S. and various state and foreign jurisdictions and we remain subject to periodic audits and reviews by taxing authorities. Federal and state tax returns for the years after 2015 remain open for examination. Tax authorities may have the ability to review and adjust carryover attributes that were generated prior to these periods if utilized in an open tax year.

NOTE 15—SHARE-BASED COMPENSATION
  
We have granted restricted stock shares, restricted stock units, performance stock units and phantom units to employees and non-employee directors under the 2011 Incentive Plan, as amended (the “2011 Plan”) and the 2015 Employee Inducement Incentive Plan (“Inducement Plan”).


110


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

Total share-based compensation consisted of the following (in millions):
 
 
Year Ended December 31,
 
 
2019
 
2018
 
2017
Share-based compensation costs, pre-tax:
 
 
 
 
 
 
Equity awards
 
$
131

 
$
89

 
$
34

Liability awards
 
9

 
48

 
80

Total share-based compensation
 
140


137

 
114

Capitalized share-based compensation
 
(9
)
 
(24
)
 
(23
)
Total share-based compensation expense
 
$
131


$
113

 
$
91

Tax benefit associated with share-based compensation expense
 
$
14

 
$
6

 
$
5


The total unrecognized compensation cost at December 31, 2019 relating to non-vested share-based compensation arrangements consisted of the following:
 
Unrecognized Compensation Cost
(in millions)
 
Recognized over a weighted average period
(years)
Restricted Stock Share Awards
$
1

 
0.4
Restricted Share Unit and Performance Stock Unit Awards
$
145

 
1.8
Phantom Units Awards
$
3

 
0.7


Restricted Stock Share Awards

Restricted stock share awards are awards of common stock that are subject to restrictions on transfer and to a risk of forfeiture if the recipient terminates employment with us prior to the lapse of the restrictions. These awards vest based on service conditions (one, two, three or four-year service periods) and performance conditions. All performance conditions of the awards have been achieved as of December 31, 2019.

The Amended and Restated 2003 Stock Incentive Plan, as amended and 2011 Plan provide for the issuance of 21.0 million shares and 35.0 million shares, respectively, of our common stock that may be in the form of various share-based performance awards deemed by the Compensation Committee of our Board (the “Compensation Committee”).

The Inducement Plan initially provided for the issuance of up to 1.0 million shares of our common stock in the form of stock-based awards deemed by the Compensation Committee to provide us with an opportunity to attract employees. As of December 31, 2019, 0.2 million shares of restricted stock have been granted under the Inducement Plan. In December 2016, the Compensation Committee recommended, and our Board approved, reducing the remaining shares available for issuance under the Inducement Plan to zero.

The table below provides a summary of our restricted stock outstanding (in millions, except for per share information):
 
 

Shares
 
Weighted Average Grant Date Fair Value Per Share
Non-vested at January 1, 2019
 
0.1

 
$
45.77

Granted
 
0.0

 
67.79

Vested
 
(0.1
)
 
46.95

Forfeited
 

 

Non-vested at December 31, 2019
 
0.0

 
$
67.79



The fair value of restricted stock share awards vested for the years ended December 31, 2019, 2018 and 2017 were $3 million, $53 million and $78 million, respectively.

Restricted Share Unit and Performance Stock Unit Awards

Restricted stock units are stock awards that vest over a service period of three years and entitle the holder to receive shares of our common stock upon vesting, subject to restrictions on transfer and to a risk of forfeiture if the recipient terminates employment with us prior to the lapse of the restrictions. Performance stock units provide for cliff vesting after a period of three years with payouts based on metrics dependent upon market and performance achieved over the defined performance period compared to

111


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

pre-established performance targets. The settlement amounts of the awards are based on market and performance metrics which include cumulative distributable cash flow per share, and in certain circumstances, total shareholder return (“TSR”) of our common stock. Where applicable, the compensation for performance stock units is based on fair value assigned to the market metric of TSR using a Monte Carlo model upon grant, which remains constant through the vesting period, and a performance metric, which will vary due to changing estimates regarding the expected achievement of the performance metric of cumulative distributable cash flow per share. The number of shares that may be earned at the end of the vesting period ranges from 25% up to 300% of the target award amount if the threshold performance is met. Both restricted stock units and performance stock units will be settled in Cheniere common stock (on a one-for-one basis) and are classified as equity awards.

In January 2017, the issuance of awards with respect to 7.8 million shares of common stock available for issuance under the 2011 Plan was approved at a special meeting of our shareholders.
The table below provides a summary of our restricted share unit and performance stock unit awards outstanding assuming payout at target for awards containing performance conditions (in millions, except for per unit information):
 
 
Units
 
Weighted Average Grant Date Fair Value Per Unit
Non-vested at January 1, 2019
 
3.4

 
$
56.29

Granted
 
1.9

 
67.47

Vested
 
(0.8
)
 
52.87

Forfeited
 
(0.1
)
 
60.23

Non-vested at December 31, 2019 (1)
 
4.4

 
$
61.68

 
    
(1)
This number excludes 0.8 million performance stock units, which represent the incremental number of common units that would be issued if the maximum level of performance under the target awards amount is achieved.
The table below provides a summary of restricted share unit and performance stock unit awards issued and fair value of units vested:
 
 
Year Ended December 31,
 
 
2019
 
2018
 
2017
Units issued (in millions)
 
1.9

 
2.6

 
1.4

Weighted average grant date fair value per unit
 
$
67.47

 
$
59.50

 
$
47.16

Fair value of units vested (in millions)
 
$
45

 
$
22

 
$
1



Phantom Units Awards
 
Phantom units are share-based awards granted to employees over a vesting period that entitle the grantee to receive the cash equivalent to the value of a share of our common stock upon each vesting. We did not issue any phantom units to our employees and non-employee directors during the years ended December 31, 2019, 2018 and 2017. Phantom units are not eligible to receive quarterly distributions. These awards vest based on service conditions (two, three or four-year service periods).

The table below provides a summary of our phantom units outstanding (in millions):
 
 
Units
Non-vested at January 1, 2019
 
0.3

Granted
 

Vested
 
(0.2
)
Forfeited
 

Non-vested at December 31, 2019
 
0.1



The value of phantom units vested during the years ended December 31, 2019, 2018 and 2017 was $11 million$91 million and $86 million, respectively.


112


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

NOTE 16—EMPLOYEE BENEFIT PLAN

We have a defined contribution plan (“401(k) Plan”) which allows eligible employees to contribute up to 75% of their compensation up to the IRS maximum. We match each employee’s deferrals (contributions) up to 6% of compensation and may make additional contributions at our discretion. Employees are immediately vested in the contributions made by us. Our contributions to the 401(k) Plan were $15 million, $9 million and $7 million for the years ended December 31, 2019, 2018 and 2017, respectively. We have made no discretionary contributions to the 401(k) Plan to date.

NOTE 17—NET INCOME (LOSS) PER SHARE ATTRIBUTABLE TO COMMON STOCKHOLDERS

The following table reconciles basic and diluted weighted average common shares outstanding for the years ended December 31, 2019, 2018 and 2017 (in millions, except per share data):
 
 
Year Ended December 31,
 
 
2019
 
2018
 
2017
Weighted average common shares outstanding:
 
 
 
 
 
 
Basic
 
256.2

 
245.6

 
233.1

Dilutive unvested stock
 
1.9

 
2.4

 

Diluted
 
258.1

 
248.0

 
233.1

 
 
 
 
 
 
 
Basic net income (loss) per share attributable to common stockholders
 
$
2.53

 
$
1.92

 
$
(1.68
)
Diluted net income (loss) per share attributable to common stockholders
 
$
2.51

 
$
1.90

 
$
(1.68
)


Potentially dilutive securities that were not included in the diluted net income (loss) per share computations because their effects would have been anti-dilutive were as follows (in millions):
 
 
Year Ended December 31,
 
 
2019
 
2018
 
2017
Unvested stock (1)
 
2.3

 
0.8

 
3.4

Convertible notes (2)
 
43.7

 
17.5

 
16.9

Total potentially dilutive common shares
 
46.0

 
18.3

 
20.3

 
(1)
Does not include 0.5 million shares, 0.4 million shares and 0.2 million shares for the years ended December 31, 2019, 2018 and 2017, respectively, of unvested stock because the performance conditions had not yet been satisfied as of the respective dates.
(2)
Includes number of shares in aggregate issuable upon conversion of the 2021 Cheniere Convertible Unsecured Notes and the 2045 Cheniere Convertible Senior Notes for all periods presented and the 2025 CCH HoldCo II Convertible Senior Notes upon the substantial completion of Train 2 of the CCL Project during the year ended December 31, 2019.

NOTE 18—SHARE REPURCHASE PROGRAM

On June 3, 2019, we announced that our Board authorized a 3-year, $1.0 billion share repurchase program. During the year ended December 31, 2019, we repurchased an aggregate of 4.0 million shares of our common stock for $249 million, for a weighted average price per share of $62.27.
As of December 31, 2019, we had up to $751 million of the share repurchase program available. Under the share repurchase program, repurchases can be made from time to time using a variety of methods, which may include open market purchases, privately negotiated transactions or otherwise, all in accordance with the rules of the SEC and other applicable legal requirements. The timing and amount of any shares of our common stock that are repurchased under the share repurchase program will be determined by our management based on market conditions and other factors.  The share repurchase program does not obligate us to acquire any particular amount of common stock, and may be modified, suspended or discontinued at any time or from time to time at our discretion.


113


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

NOTE 19—COMMITMENTS AND CONTINGENCIES

We have various contractual obligations which are recorded as liabilities in our Consolidated Financial Statements. Other items, such as certain purchase commitments and other executed contracts which do not meet the definition of a liability as of December 31, 2019, are not recognized as liabilities but require disclosures in our Consolidated Financial Statements.

LNG Terminal Commitments and Contingencies
 
Obligations under EPC Contracts

SPL has a lump sum turnkey contract with Bechtel Oil, Gas and Chemicals, Inc. (“Bechtel”) for the engineering, procurement and construction of Train 6 of the SPL Project. The EPC contract price for Train 6 of the SPL Project is approximately $2.5 billion, reflecting amounts incurred under change orders through December 31, 2019, and including estimated costs for an optional third marine berth. As of December 31, 2019, we have incurred $1.1 billion under this contract.

CCL has a lump sum turnkey contract with Bechtel for the engineering, procurement and construction of Train 3 of the CCL Project. The EPC contract price for Train 3 of the CCL Project is approximately $2.4 billion, reflecting amounts incurred under change orders through December 31, 2019. As of December 31, 2019, we have incurred $2.0 billion under this contract.

SPL and CCL have the right to terminate its respective EPC contracts for its convenience, in which case Bechtel will be paid (1) the portion of the contract price for the work performed, (2) costs reasonably incurred by Bechtel on account of such termination and demobilization and (3) a lump sum of up to $30 million depending on the termination date.

Obligations under SPAs

SPL and CCL have third-party SPAs which obligate SPL and CCL, respectively, to purchase and liquefy sufficient quantities of natural gas to deliver contracted volumes of LNG to the customers’ vessels, subject to completion of construction of applicable specified Trains of the SPL Project or the CCL Project. In addition, our integrated marketing function has third-party SPAs which obligate us to deliver contracted volumes of LNG to the customers’ vessels or to the customers at their LNG receiving terminals.
 
Obligations under LNG TUAs
 
SPLNG has third-party TUAs with Total and Chevron U.S.A. Inc. to provide berthing for LNG vessels and for the unloading, storage and regasification of LNG at the Sabine Pass LNG terminal.

Obligations under Natural Gas Supply, Transportation and Storage Service Agreements

SPL, CCL and CCL Stage III have physical natural gas supply contracts to secure natural gas feedstock for the SPL Project, the CCL Project and potential future development of Corpus Christi Stage 3, respectively. The remaining terms of these contracts range up to 15 years, some of which commence upon the satisfaction of certain events or states of affairs. As of December 31, 2019, SPL, CCL and CCL Stage III have secured up to approximately 3,850 TBtu, 2,999 TBtu and 2,361 TBtu, respectively, of natural gas feedstock through natural gas supply contracts, a portion of which are considered purchase obligations if the certain events or states of affairs are satisfied.

Additionally, SPL and CCL have natural gas transportation and storage service agreements for the SPL Project and the CCL Project, respectively. The initial terms of the natural gas transportation agreements range up to 20 years for the SPL Project and the CCL Project, with renewal options for certain contracts, and commence upon the occurrence of conditions precedent. The initial term of the natural gas storage service agreements for the SPL Project ranges up to 10 years and the initial term of the natural gas storage service agreements for the CCL Project ranges up to five years.


114


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

As of December 31, 2019, the obligations of SPL, CCL and CCL Stage III under natural gas supply, transportation and storage service agreements for contracts in which conditions precedent were met were as follows (in millions): 
Years Ending December 31,
Payments Due (1)
2020
$
3,503

2021
2,382

2022
1,561

2023
1,231

2024
804

Thereafter
3,987

Total
$
13,468

 
(1)
Pricing of natural gas supply contracts are variable based on market commodity basis prices adjusted for basis spread. Amounts included are based on estimated forward prices and basis spreads as of December 31, 2019. Some of our contracts may not have been negotiated as part of arranging financing for the underlying assets providing the natural gas supply, transportation and storage services.
    
Restricted Net Assets
 
At December 31, 2019, our restricted net assets of consolidated subsidiaries were approximately $1.3 billion.

Other Commitments
 
In the ordinary course of business, we have entered into certain multi-year licensing and service agreements, none of which are considered material to our financial position.

Environmental and Regulatory Matters

Our LNG terminals and pipelines are subject to extensive regulation under federal, state and local statutes, rules, regulations and laws. These laws require that we engage in consultations with appropriate federal and state agencies and that we obtain and maintain applicable permits and other authorizations. Failure to comply with such laws could result in legal proceedings, which may include substantial penalties. We believe that, based on currently known information, compliance with these laws and regulations will not have a material adverse effect on our results of operations, financial condition or cash flows.

Legal Proceedings

We may in the future be involved as a party to various legal proceedings, which are incidental to the ordinary course of business. We regularly analyze current information and, as necessary, provide accruals for probable liabilities on the eventual disposition of these matters.

Parallax and Related Litigation

In 2015, our wholly owned subsidiary, Cheniere LNG Terminals, LLC (“CLNGT”), entered into discussions with Parallax Enterprises, LLC (“Parallax Enterprises”) regarding the potential joint development of two liquefaction plants in Louisiana (the “Potential Liquefaction Transactions”). While the parties negotiated regarding the Potential Liquefaction Transactions, CLNGT loaned Parallax Enterprises approximately $46 million, as reflected in a secured note dated April 23, 2015, as amended on June 30, 2015, September 30, 2015 and November 4, 2015 (the “Secured Note”). The Secured Note was secured by all assets of Parallax Enterprises and its subsidiary entities. On June 30, 2015, Parallax Enterprises’ parent entity, Parallax Energy LLC (“Parallax Energy”), executed a Pledge and Guarantee Agreement further securing repayment of the Secured Note by providing a parent guaranty and a pledge of all of the equity of Parallax Enterprises in satisfaction of the Secured Note (the “Pledge Agreement”). CLNGT and Parallax Enterprises never executed a definitive agreement to pursue the Potential Liquefaction Transactions. The Secured Note matured on December 11, 2015, and Parallax Enterprises failed to make payment. On February 3, 2016, CLNGT filed an action against Parallax Energy, Parallax Enterprises and certain of Parallax Enterprises’ subsidiary entities, styled Cause No. 4:16-cv-00286, Cheniere LNG Terminals, LLC v. Parallax Energy LLC, et al., in the United States District Court for the Southern District of Texas (the “Texas Federal Suit”). CLNGT asserted claims in the Texas Federal Suit for (1) recovery of all amounts due under the Secured Note and (2) declaratory relief establishing that CLNGT is entitled to enforce its rights under the

115


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

Secured Note and Pledge Agreement in accordance with each instrument’s terms and that CLNGT has no obligations of any sort to Parallax Enterprises concerning the Potential Liquefaction Transactions. On March 11, 2016, Parallax Enterprises and the other defendants in the Texas Federal Suit moved to dismiss the suit for lack of subject matter jurisdiction. On August 2, 2016, the court denied the defendants’ motion to dismiss without prejudice and permitted the parties to pursue jurisdictional discovery.

On March 11, 2016, Parallax Enterprises filed a suit against us and CLNGT styled Civil Action No. 62-810, Parallax Enterprises LLP v. Cheniere Energy, Inc. and Cheniere LNG Terminals, LLC, in the 25th Judicial District Court of Plaquemines Parish, Louisiana (the “Louisiana Suit”), wherein Parallax Enterprises asserted claims for breach of contract, fraudulent inducement, negligent misrepresentation, detrimental reliance, unjust enrichment and violation of the Louisiana Unfair Trade Practices Act. Parallax Enterprises predicated its claims in the Louisiana Suit on an allegation that we and CLNGT breached a purported agreement to jointly develop the Potential Liquefaction Transactions. Parallax Enterprises sought $400 million in alleged economic damages and rescission of the Secured Note. On April 15, 2016, we and CLNGT removed the Louisiana Suit to the United States District Court for the Eastern District of Louisiana, which subsequently transferred the Louisiana Suit to the United States District Court for the Southern District of Texas, where it was assigned Civil Action No. 4:16-cv-01628 and transferred to the same judge presiding over the Texas Federal Suit for coordinated handling. On August 22, 2016, Parallax Enterprises voluntarily dismissed all claims asserted against CLNGT and us in the Louisiana Suit without prejudice to refiling.

On July 27, 2017, the Parallax entities named as defendants in the Texas Federal Suit reurged their motion to dismiss and simultaneously filed counterclaims against CLNGT and third party claims against us for breach of contract, breach of fiduciary duty, promissory estoppel, quantum meruit and fraudulent inducement of the Secured Note and Pledge Agreement, based on substantially the same factual allegations Parallax Enterprises made in the Louisiana Suit. These Parallax entities also simultaneously filed an action styled Cause No. 2017-49685, Parallax Enterprises, LLC, et al. v. Cheniere Energy, Inc., et al., in the 61st District Court of Harris County, Texas (the “Texas State Suit”), which asserts substantially the same claims these entities asserted in the Texas Federal Suit. On July 31, 2017, CLNGT withdrew its opposition to the dismissal of the Texas Federal Suit without prejudice on jurisdictional grounds and the federal court subsequently dismissed the Texas Federal Suit without prejudice. We and CLNGT simultaneously filed an answer and counterclaims in the Texas State Suit, asserting the same claims CLNGT had previously asserted in the Texas Federal Suit. Additionally, CLNGT filed third party claims against Parallax principals Martin Houston, Christopher Bowen Daniels, Howard Candelet and Mark Evans, as well as Tellurian Investments, Inc., Driftwood LNG, LLC, Driftwood LNG Pipeline LLC and Tellurian Services LLC, formerly known as Parallax Services LLC, including claims for tortious interference with CLNGT’s collateral rights under the Secured Note and Pledge Agreement, fraudulent transfer, conspiracy/aiding and abetting.
 
On February 15, 2019, we filed an action with CLNGT against Charif Souki, our former Chairman of the Board and Chief Executive Officer, styled, Cause No. 2019-11529, Cheniere Energy, Inc. and Cheniere LNG Terminals, LLC v. Charif Souki, in the 55th District Court of Harris County, Texas, which asserts claims of breach of fiduciary duties, fraudulent transfer, tortious interference with CLNGT’s collateral rights under the Secured Note and Pledge Agreement and conspiracy/aiding and abetting. On April 29, 2019, the court consolidated the Souki matter with the earlier filed pending case against Parallax, Tellurian and the individual defendants in the Texas State Suit.
On January 30, 2020, the parties filed an Agreed Motion to Dismiss and all claims were dismissed with prejudice.
The resolution of the foregoing litigation did not have a material adverse impact on our financial results.

On January 10, 2020, a purported shareholder of Cheniere filed a shareholder derivative action in state court in Houston, Texas. The complaint names as defendants ten of our current directors. The plaintiff alleges that those directors breached their fiduciary duties by abandoning a proposed joint-development arrangement with Parallax in 2015, which later was the subject of a separate lawsuit by Parallax discussed above. According to the complaint, the directors’ alleged breach of their fiduciary duties caused us to incur legal fees in the Parallax action and also exposed us to a potential damages award in the Parallax lawsuit. On January 30, 2020, Parallax voluntarily dismissed with prejudice all claims against us. We do not expect that the resolution of the foregoing litigation will have a material adverse impact on our financial results.


116


CHENIERE ENERGY, INC. AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS—CONTINUED

NOTE 20—CUSTOMER CONCENTRATION
  
The following table shows customers with revenues of 10% or greater of total revenues from external customers and customers with accounts receivable balances of 10% or greater of total accounts receivable from external customers:
 
Percentage of Total Revenues from External Customers
 
Percentage of Accounts Receivable from External Customers
 
Year Ended December 31,
 
December 31,
 
2019
 
2018
 
2017
 
2019
 
2018
Customer A
16%
 
18%
 
24%
 
13%
 
21%
Customer B
10%
 
14%
 
14%
 
*
 
14%
Customer C
11%
 
19%
 
14%
 
13%
 
18%
Customer D
11%
 
13%
 
*
 
*
 
*
Customer E
*
 
*
 
17%
 
%
 
%
Customer F
*
 
*
 
*
 
%
 
10%

 
* Less than 10%

The following table shows revenues from external customers attributable to the country in which the revenues were derived (in millions). We attribute revenues from external customers to the country in which the party to the applicable agreement has its principal place of business. Substantially all of our long-lived assets are located in the United States.
 
Revenues from External Customers
 
Year Ended December 31,
 
2019
 
2018
 
2017
United States
$
2,807

 
$
1,911

 
$
1,592

South Korea
1,207

 
1,517

 
762

India
1,160

 
1,048

 
48

Ireland
989

 
1,098

 
787

Spain
598

 

 
50

United Kingdom
559

 
155

 
102

Singapore
533

 
417

 
203

Japan
157

 
193

 
1,246

Other countries
1,720

 
1,648

 
811

Total
$
9,730

 
$
7,987

 
$
5,601



NOTE 21—SUPPLEMENTAL CASH FLOW INFORMATION

The following table provides supplemental disclosure of cash flow information (in millions): 
 
 
Year Ended December 31,
 
 
2019
 
2018
 
2017
Cash paid during the period for interest on debt, net of amounts capitalized
 
$
1,126

 
$
707

 
$
305

Cash paid for income taxes
 
24

 
14

 
3

Non-cash investing and financing activities:
 
 
 
 
 
 
Acquisition of non-controlling interest in Cheniere Holdings
 

 
702

 
2

Contribution of assets to equity method investee
 

 

 
14

Acquisition of assets under capital lease (1)
 

 
60

 


 
(1)
See Note 12—Leases for our supplemental cash flow information related to our leases in 2019 following the adoption of ASC 842.
 
The balance in property, plant and equipment, net funded with accounts payable and accrued liabilities was $473 million, $420 million and $521 million as of years ended December 31, 2019, 2018 and 2017, respectively.

117


CHENIERE ENERGY, INC. AND SUBSIDIARIES
SUPPLEMENTAL INFORMATION TO CONSOLIDATED FINANCIAL STATEMENTS
SUMMARIZED QUARTERLY FINANCIAL DATA
(unaudited)

Summarized Quarterly Financial Data—(in millions, except per share amounts)
 
 
First
Quarter
 
Second
Quarter
 
Third
Quarter
 
Fourth
Quarter
Year ended December 31, 2019:
 
 
 
 
 
 
 
 
Revenues
 
$
2,261

 
$
2,292

 
$
2,170

 
$
3,007

Income from operations
 
606

 
432

 
307

 
1,016

Net income (loss)
 
337

 
2

 
(260
)
 
1,153

Net income (loss) attributable to common stockholders
 
141

 
(114
)
 
(318
)
 
939

Net income (loss) per share attributable to common stockholders—basic (1)
 
0.55

 
(0.44
)
 
(1.25
)
 
3.70

Net income (loss) per share attributable to common stockholders—diluted (1)
 
0.54

 
(0.44
)
 
(1.25
)
 
3.34

 
 
 
 
 
 
 
 
 
Year ended December 31, 2018:
 
 

 
 

 
 

 
 

Revenues
 
$
2,242

 
$
1,543

 
$
1,819

 
$
2,383

Income from operations
 
747

 
336

 
425

 
516

Net income
 
600

 
150

 
227

 
223

Net income (loss) attributable to common stockholders
 
357

 
(18
)
 
65

 
67

Net income (loss) per share attributable to common stockholders—basic (1)
 
1.52

 
(0.07
)
 
0.26

 
0.26

Net income (loss) per share attributable to common stockholders—diluted (1)
 
1.50

 
(0.07
)
 
0.26

 
0.26

 
 
 
 
 
(1)
The sum of the quarterly net income (loss) per share—basic and diluted may not equal the full year amount as the computations of the weighted average common shares outstanding for basic and diluted shares outstanding for each quarter and the full year are performed independently.


118


ITEM 9.
CHANGES IN AND DISAGREEMENTS WITH ACCOUNTANTS ON ACCOUNTING AND FINANCIAL DISCLOSURE
 
None.

ITEM 9A.
CONTROLS AND PROCEDURES
 
Evaluation of Disclosure Controls and Procedures
 
Disclosure controls and procedures include, without limitation, controls and procedures designed to ensure that information required to be disclosed by us in reports we file or submit under the Exchange Act is recorded, processed, summarized and reported within the time periods specified in the SEC’s rules and forms, and that such information is accumulated and communicated to our management, including our principal executive officer and principal financial officer, as appropriate, to allow timely decisions regarding required disclosure.

Based on their evaluation as of the end of the fiscal year ended December 31, 2019, our principal executive officer and principal financial officer have concluded that our disclosure controls and procedures (as defined in Rules 13a-15(e) and 15d-15(e) under the Exchange Act) are effective to ensure that information required to be disclosed in reports that we file or submit under the Exchange Act are (1) accumulated and communicated to our management, including our principal executive officer and principal financial officer, as appropriate, to allow timely decisions regarding required disclosure and (2) recorded, processed, summarized and reported within the time periods specified in the SEC’s rules and forms.
 
During the most recent fiscal quarter, there have been no changes in our internal control over financial reporting that have materially affected, or are reasonably likely to materially affect, our internal control over financial reporting.
 
Management’s Report on Internal Control Over Financial Reporting
 
Our Management’s Report on Internal Control Over Financial Reporting is included in our Consolidated Financial Statements on page 68 and is incorporated herein by reference.

ITEM 9B.
OTHER INFORMATION

None.

PART III
 
Pursuant to paragraph 3 of General Instruction G to Form 10-K, the information required by Items 10 through 14 of Part III of this Report is incorporated by reference from Cheniere’s definitive proxy statement, which is to be filed pursuant to Regulation 14A within 120 days after the end of Cheniere’s fiscal year ended December 31, 2019.


119


PART IV

ITEM 15.
EXHIBITS AND FINANCIAL STATEMENT SCHEDULES
 
(a)
Financial Statements, Schedules and Exhibits
(1)
Financial Statements—Cheniere Energy, Inc. and Subsidiaries: 
(2)
Financial Statement Schedules: 
(3)
 Exhibits:

Certain of the agreements filed as exhibits to this Form 10-K contain representations, warranties, covenants and conditions by the parties to the agreements that have been made solely for the benefit of the parties to the agreement. These representations, warranties, covenants and conditions:
    
should not in all instances be treated as categorical statements of fact, but rather as a way of allocating the risk to one of the parties if those statements prove to be inaccurate;

may have been qualified by disclosures that were made to the other parties in connection with the    negotiation of the agreements, which disclosures are not necessarily reflected in the agreements;
    
may apply standards of materiality that differ from those of a reasonable investor; and
    
were made only as of specified dates contained in the agreements and are subject to subsequent developments and changed circumstances.

Accordingly, these representations and warranties may not describe the actual state of affairs as of the date they were made or at any other time. These agreements are included to provide you with information regarding their terms and are not intended to provide any other factual or disclosure information about the Company or the other parties to the agreements. Investors should not rely on them as statements of fact.
Exhibit No.
 
 
 
Incorporated by Reference (1)
 
Description
 
Entity
Form
Exhibit
Filing Date
2.1
 
 
Cheniere Partners
8-K
10.2
8/9/2012
3.1
 
 
Cheniere
10-Q
3.1
8/10/2004
3.2
 
 
Cheniere
8-K
3.1
2/8/2005
3.3
 
 
Cheniere
(SEC File No. 333-160017)
S-8
4.3
6/16/2009
3.4
 
 
Cheniere
8-K
3.1
6/7/2012

120


Exhibit No.
 
 
 
Incorporated by Reference (1)
 
Description
 
Entity
Form
Exhibit
Filing Date
3.5
 
 
Cheniere
8-K
3.1
2/5/2013
3.6
 
 
Cheniere
8-K
3.1
12/15/2015
3.7
 
 
Cheniere
8-K
3.1
9/19/2016
4.1
 
 
Cheniere
(SEC File No. 333-10905)
S-1
4.1
8/27/1996
4.2
 
 
Cheniere Partners
8-K
4.1
2/4/2013
4.3
 
 
Cheniere Partners
8-K
4.1
2/4/2013
4.4
 
 
Cheniere Partners
8-K
4.1.1
4/16/2013
4.5
 
 
Cheniere Partners
8-K
4.1.2
4/16/2013
4.6
 
 
Cheniere Partners
8-K
4.1.2
4/16/2013
4.7
 
 
Cheniere Partners
8-K
4.1
11/25/2013
4.8
 
 
Cheniere Partners
8-K
4.1
11/25/2013
4.9
 
 
Cheniere Partners
8-K
4.1
5/22/2014
4.10
 
 
Cheniere Partners
8-K
4.1
5/22/2014
4.11
 
 
Cheniere Partners
8-K
4.2
5/22/2014
4.12
 
 
Cheniere Partners
8-K
4.2
5/22/2014
4.13
 
 
Cheniere Partners
8-K
4.1
3/3/2015
4.14
 
 
Cheniere Partners
8-K
4.1
3/3/2015
4.15
 
 
Cheniere Partners
8-K
4.1
6/14/2016
4.16
 
 
Cheniere Partners
8-K
4.1
6/14/2016
4.17
 
 
Cheniere Partners
8-K
4.1
9/23/2016
4.18
 
 
Cheniere Partners
8-K
4.2
9/23/2016
4.19
 
 
Cheniere Partners
8-K
4.2
9/23/2016
4.20
 
 
Cheniere Partners
8-K
4.1
3/6/2017
4.21
 
 
Cheniere Partners
8-K
4.1
3/6/2017

121


Exhibit No.
 
 
 
Incorporated by Reference (1)
 
Description
 
Entity
Form
Exhibit
Filing Date
4.22
 
 
Cheniere Partners
8-K
4.1
2/27/2017
4.23
 
 
Cheniere Partners
8-K
4.1
2/27/2017
4.24
 
 
Cheniere
8-K
4.1
12/2/2014
4.25
 
 
Cheniere
8-K
4.1
12/2/2014
4.26
 
 
Cheniere
8-K
4.1
3/13/2015
4.27
 
 
Cheniere
8-K
4.2
3/13/2015
4.28
 
 
Cheniere
8-K
4.2
3/13/2015
4.29
 
 
Cheniere
8-K
4.1
5/18/2016
4.30
 
 
Cheniere
8-K
4.1
5/18/2016
4.31
 
 
Cheniere
8-K
4.1
12/9/2016
4.32
 
 
Cheniere
8-K
4.1
12/9/2016
4.33
 
 
CCH
8-K
4.1
5/19/2017
4.34
 
 
CCH
8-K
4.1
5/19/2017
4.35
 
 
CCH
8-K
4.1
9/12/2019
4.36
 
 
CCH
8-K
4.1
11/13/2019
4.37
 
 
Cheniere Partners
8-K
4.1
9/18/2017
4.38
 
 
Cheniere Partners
8-K
4.2
9/18/2017
4.39
 
 
Cheniere Partners
8-K
4.2
9/18/2017
4.40
 
 
Cheniere Partners
8-K
4.1
9/12/2018
4.41
 
 
Cheniere Partners
8-K
4.1
9/12/2018
4.42
 
 
Cheniere Partners
8-K
4.1
9/12/2019

122


Exhibit No.
 
 
 
Incorporated by Reference (1)
 
Description
 
Entity
Form
Exhibit
Filing Date
4.43
 
 
CCH
8-K
4.1
9/30/2019
4.44
 
 
CCH
8-K
4.1
10/18/2019
4.45*
 
 
 
 
 
 
10.1
 
 
Cheniere
10-Q
10.1
11/15/2004
10.2
 
 
Cheniere
10-K
10.40
3/10/2005
10.3
 
 
Cheniere
10-Q
10.2
8/6/2010
10.4
 
 
Cheniere
10-Q
10.2
11/15/2004
10.5
 
 
Cheniere
10-Q
10.3
11/15/2004
10.6
 
 
Cheniere Partners
10-Q
10.1
11/2/2012
10.7
 
 
Cheniere
10-Q
10.4
11/15/2004
10.8
 
 
SPLNG
S-4
10.28
11/22/2006
10.9
 
 
Cheniere
10-Q
10.3
8/6/2010
10.10
 
 
Cheniere
10-Q
10.5
11/15/2004
10.11
 
 
SPLNG
S-4
10.12
11/22/2006
10.12
 
 
SPLNG
8-K
10.1
8/6/2012
10.13
 
 
SPLNG
10-Q
10.1
8/2/2013
10.14
 
 
SPLNG
8-K
10.2
8/6/2012
10.15†
 
 
Cheniere
10-Q
10.1
8/8/2017
10.16†
 
 
Cheniere
8-K
10.13
8/10/2012
10.17†
 
 
Cheniere
8-K
10.14
8/10/2012
10.18†
 
 
Cheniere
10-Q
10.20
7/30/2015
10.19†
 
 
Cheniere
10-K
10.37
2/24/2017
10.20†
 
 
Cheniere
10-Q
10.2
5/4/2017
10.21†
 
 
Cheniere
10-K
10.38
2/24/2017
10.22†
 
 
Cheniere
10-Q
10.3
5/4/2017

123


Exhibit No.
 
 
 
Incorporated by Reference (1)
 
Description
 
Entity
Form
Exhibit
Filing Date
10.23†
 
 
Cheniere
10-K
10.39
2/24/2017
10.24†
 
 
Cheniere
10-K
10.40
2/24/2017
10.25†
 
 
Cheniere
10-Q
10.4
5/4/2017
10.26†
 
 
Cheniere
10-Q
10.5
5/4/2017
10.27†
 
 
Cheniere
10-Q
10.6
5/4/2017
10.28†
 
 
Cheniere
10-K
10.41
2/24/2017
10.29†
 
 
Cheniere
10-Q
10.7
5/4/2017
10.30†
 
 
Cheniere
10-K
10.42
2/24/2017
10.31†
 
 
Cheniere
10-Q
10.8
5/4/2017
10.32†
 
 
Cheniere
10-K
10.43
2/24/2017
10.33†
 
 
Cheniere
10-K
10.44
2/24/2017
10.34†
 
 
Cheniere
10-Q
10.9
5/4/2017
10.35†
 
 
Cheniere
10-K
10.35
2/26/2019
10.36†
 
 
Cheniere
10-K
10.45
2/24/2017
10.37†
 
 
Cheniere
10-Q
10.9
4/30/2015
10.38†
 
 
Cheniere
10-Q
10.10
4/30/2015
10.39†
 
 
Cheniere
10-Q
10.11
4/30/2015
10.40†
 
 
Cheniere
10-Q
10.12
4/30/2015
10.41†
 
 
Cheniere
10-Q
10.13
4/30/2015
10.42†
 
 
Cheniere
10-Q
10.14
4/30/2015
10.43†
 
 
Cheniere
10-Q
10.15
4/30/2015
10.44†
 
 
Cheniere
(SEC File No. 333-207651)
S-8
4.8
10/29/2015
10.45†
 
 
Cheniere
10-Q
10.7
10/30/2015

124


Exhibit No.
 
 
 
Incorporated by Reference (1)
 
Description
 
Entity
Form
Exhibit
Filing Date
10.46†
 
 
Cheniere
10-Q
10.3
11/1/2019
10.47†
 
 
Cheniere
8-K
10.1
5/12/2016
10.48†
 
 
Cheniere
8-K
10.1
8/15/2019
10.49*†
 
 
 
 
 
 
10.50†
 
 
Cheniere
10-K
10.73
2/19/2016
10.51†
 
 
Cheniere
10-K
10.74
2/19/2016
10.52†
 
 
Cheniere
8-K
10.1
11/1/2019
10.53
 
 
Cheniere Partners
8-K
10.2
7/1/2015
10.54
 
 
Cheniere Partners
10-Q
10.6
10/30/2015
10.55
 
 
Cheniere Partners
10-Q
10.7
5/5/2016
10.56
 
 
Cheniere Partners
8-K
10.1
9/11/2015
10.57
 
 
Cheniere Partners
(SEC File No. 333-225684)
S-4
10.3
6/15/2018

125


Exhibit No.
 
 
 
Incorporated by Reference (1)
 
Description
 
Entity
Form
Exhibit
Filing Date
10.58
 
Fourth Omnibus Amendment, dated as of September 17, 2018, to (a) the Second Amended and Restated Common Terms Agreement, dated as of June 30, 2015, by and among SPL, as Borrower, Société Générale, as the Common Security Trustee and as the Intercreditor Agent, The Bank of Nova Scotia, as the Secured Debt Holder Group Representative for the Working Capital Debt and other Secured Debt Holder Group Representatives party thereto from time to time, the Secured Hedge Representatives and the Secured Gas Hedge Representatives party thereto from time to time and (b) the Amended and Restated Senior Working Capital Revolving Credit and Letter of Credit Reimbursement Agreement, dated as of September 4, 2015, by and among SPL, as Borrower, Société Générale as the Swing Line Lender and as the Common Security Trustee, The Bank of Nova Scotia as the Senior Issuing Bank and Senior Facility Agent and the other agents and lenders from time to time party thereto
 
Cheniere
10-Q
10.1
11/8/2018
10.59*
 
Fifth Omnibus Amendment, dated as of May 29, 2019, to (a) the Second Amended and Restated Common Terms Agreement, dated as of June 30, 2015, by and among SPL, as Borrower, Société Générale, as the Common Security Trustee and as the Intercreditor Agent, The Bank of Nova Scotia, as the Secured Debt Holder Group Representative for the Working Capital Debt and other Secured Debt Holder Group Representatives party thereto from time to time, the Secured Hedge Representatives and the Secured Gas Hedge Representatives party thereto from time to time and (b) the Amended and Restated Senior Working Capital Revolving Credit and Letter of Credit Reimbursement Agreement, dated as of September 4, 2015, by and among SPL, as Borrower, Société Générale as the Swing Line Lender and as the Common Security Trustee, The Bank of Nova Scotia as the Senior Issuing Bank and Senior Facility Agent and the other agents and lenders from time to time party thereto
 
 
 
 
 
10.60
 
 
Cheniere
8-K
10.1
12/2/2014
10.61
 
 
Cheniere
8-K
10.1
5/24/2018
10.62
 
 
Cheniere
8-K
10.2
5/24/2018
10.63
 
 
Cheniere
10-K
10.60
2/26/2019
10.64
 
 
Cheniere
10-Q
10.4
11/1/2019

126


Exhibit No.
 
 
 
Incorporated by Reference (1)
 
Description
 
Entity
Form
Exhibit
Filing Date
10.65
 
 
Cheniere
8-K
10.3
5/24/2018
10.66
 
 
Cheniere
10-K
10.62
2/26/2019
10.67
 
 
Cheniere
10-Q
10.5
11/1/2019
10.68
 
 
Cheniere
8-K
10.4
5/24/2018
10.69
 
 
Cheniere
8-K
10.5
5/24/2018
10.70
 
 
Cheniere
8-K
10.1
3/2/2015
10.71
 
 
Cheniere
8-K
4.2
5/13/2015
10.72
 
 
Cheniere
8-K
4.3
5/13/2015
10.73
 
 
Cheniere
8-K
10.6
5/24/2018
10.74
 
 
Cheniere
8-K
4.4
5/13/2015
10.75
 
 
Cheniere
8-K
10.6
5/13/2015
10.76
 
 
Cheniere
8-K
10.7
5/13/2015
10.77
 
 
Cheniere
8-K
10.8
5/13/2015

127


Exhibit No.
 
 
 
Incorporated by Reference (1)
 
Description
 
Entity
Form
Exhibit
Filing Date
10.78
 
 
Cheniere
8-K
10.1
7/2/2018
10.79
 
 
Cheniere
8-K
10.1
12/17/2018
10.80
 
 
Cheniere
10-Q
10.7
11/1/2019
10.81
 
 
Cheniere
8-K
10.1
6/3/2019
10.82
 
 
Cheniere
10-Q
10.2
8/8/2019
10.83
 
 
Cheniere Partners
8-K
10.1
9/12/2019
10.84
 
 
CCH
8-K
10.1
11/13/2019
10.85
 
 
Cheniere
8-K
10.1
11/9/2018
10.86
 
 
Cheniere
10-Q
10.6
8/8/2019

128


Exhibit No.
 
 
 
Incorporated by Reference (1)
 
Description
 
Entity
Form
Exhibit
Filing Date
10.87
 
Change order to the Lump Sum Turnkey Agreement for the Engineering, Procurement and Construction of the Sabine Pass LNG Stage 4 Liquefaction Facility, dated November 7, 2018, by and between SPL and Bechtel Oil Gas and Chemicals, Inc.: (i) the Change Order CO-00002 Fuel Provisional Sum Closure, dated July 8, 2019, (ii) the Change Order CO-00003 Currency Provisional Sum Closure, dated July 8, 2019, (iii) the Change Order CO-00004 Foreign Trade Zone, dated July 2, 2019, (iv) the Change Order CO-00005 NGPL Gate Access Security Coordination Provisional Sum, dated July 17, 2019, (v) the Change Order CO-00006 Alternate to Adams Valves, dated August 14, 2019, (vi) the Change Order CO-00007 E-1503 to HRU Permanent Drain Piping, dated August 14, 2019, (vii) the Change Order CO-00008 Differing Subsurface Soil Conditions - Train 6 ISBL, dated August 27, 2019, (viii) the Change Order CO-00009 LNG Berth 3, dated September 25, 2019 and (iv) the Change Order CO-00010 Cold Box Redesign and Addition of Inspection Boxes on Methane Cold Box, dated September 16, 2019
 
Cheniere
10-Q
10.10
11/1/2019
10.88*
 
 
 
 
 
 
10.89
 
 
Cheniere
10-K/A
10.23
4/27/2018
10.90
 
Change orders to the Amended and Restated Fixed Price Separated Turnkey Agreement for the Engineering, Procurement and Construction of the Corpus Christi Stage 2 Liquefaction Facility, dated as of December 12, 2017, between CCL and Bechtel Oil, Gas and Chemicals, Inc.: (i) the Change Order CO-00001 Stage 2 EPC Agreement Revised Table A-2, dated May 18, 2018, (ii) the Change Order CO-00002 Stage 2 EPC Agreement Amended and Restated Attachment C, dated May 18, 2018, (iii) the Change Order CO-00003 Fuel Provisional Sum Adjustment, dated May 24, 2018, (iv) the Change Order CO-00004 Currency Provisional Sum Adjustment, dated May 29, 2018, (v) the Change Order CO-00005 JT Valve Modifications, dated July 10, 2018 and (vi) the Change Order CO-00006 Tank B Soil Conditions, International Building Code, and East Jetty Marine Facility Schedule Acceleration, dated September 5, 2018 (Portions of this exhibit have been omitted and filed separately with the SEC pursuant to a request for confidential treatment.)
 
Cheniere
10-Q
10.3
11/8/2018
10.91
 
 
Cheniere
10-K
10.117
2/26/2019

129


Exhibit No.
 
 
 
Incorporated by Reference (1)
 
Description
 
Entity
Form
Exhibit
Filing Date
10.92
 
 
Cheniere
10-Q
10.2
5/9/2019
10.93
 
 
Cheniere
10-Q
10.4
8/8/2019
10.94
 
 
Cheniere
10-Q
10.9
11/1/2019
10.95*
 
Change orders to the Amended and Restated Fixed Price Separated Turnkey Agreement for the Engineering, Procurement and Construction of the Corpus Christi Stage 2 Liquefaction Facility, dated as of December 12, 2017, between CCL and Bechtel Oil, Gas and Chemicals, Inc.: (i) the Change Order CO-00019 Aircraft Warning Lights, dated September 23, 2019, (ii) the Change Order CO-00020 Section 232 Steel and Aluminum Tariffs & Anti-dumping (ADA) and Countervailing Duties (CVD) Q2_2019, dated October 8, 2019, (iii) the Change Order CO-00021 Spare Transition Joints for Potential Future Cold Box Modifications, dated October 8, 2019, (iv) the Change Order CO-00022 Modification of the Train 3 Methane Cold Box, dated December 6, 2019 and (v) the Change Order Co-00023 Section 232 Steel & Aluminum Tariffs & Anti-dumping (ADA) and Countervailing Duties (CVD) Q3_2019, dated December 10, 2019 (Portions of this exhibit have been omitted.)
 
 
 
 
 
10.96
 
 
Cheniere Partners
8-K
10.1
11/21/2011
10.97
 
 
Cheniere Partners
10-Q
10.1
5/3/2013
10.98
 
 
SPL
(SEC File No. 333-215882)
S-4
10.3
2/3/2017

130


Exhibit No.
 
 
 
Incorporated by Reference (1)
 
Description
 
Entity
Form
Exhibit
Filing Date
10.99
 
 
Cheniere Partners
8-K
10.1
12/12/2011
10.100
 
 
Cheniere Partners
10-K
10.18
2/22/2013
10.101
 
 
Cheniere Partners
8-K
10.1
1/26/2012
10.102
 
 
SPL
(SEC File No. 333-215882)
S-4
10.7
2/3/2017
10.103
 
 
Cheniere Partners
8-K
10.1
1/30/2012
10.104
 
 
Cheniere Partners
10-K
10.19
2/22/2013
10.105
 
 
SPL
8-K
10.1
8/11/2014
10.106
 
 
SPL
10-K
10.14
2/24/2017
10.107
 
 
Cheniere
8-K
10.1
4/2/2014
10.108
 
 
Cheniere
8-K
10.1
4/8/2014
10.109
 
 
Cheniere
10-Q
10.3
5/1/2014
10.110
 
 
Cheniere
10-Q
10.9
10/30/2015
10.111
 
 
Cheniere
10-Q
10.10
10/30/2015
10.112
 
 
Cheniere
10-Q
10.5
4/30/2015
10.113
 
 
CCH
S-4
10.22
1/5/2017
10.114
 
 
CCH
10-Q
10.1
11/1/2019
10.115
 
 
Cheniere
8-K
10.1
6/2/2014
10.116
 
 
Cheniere
10-Q
10.6
5/4/2018
10.117
 
 
CCH
S-4
10.32
1/5/2017

131


Exhibit No.
 
 
 
Incorporated by Reference (1)
 
Description
 
Entity
Form
Exhibit
Filing Date
10.118
 
 
CCH
S-4
10.33
1/5/2017
10.119
 
 
CCH
S-4
10.34
1/5/2017
10.120
 
 
Cheniere
10-Q
10.7
11/6/2007
10.121
 
 
Cheniere Partners
8-K
10.1
8/6/2012
10.122
 
 
Cheniere Partners
8-K
3.1
2/21/2017
10.123
 
 
Cheniere Holdings
8-K
10.3
12/18/2013
10.123
 
 
Cheniere
8-K
99.1
8/24/2015
21.1*
 
 
 
 
 
 
23.1*
 
 
 
 
 
 
31.1*
 
 
 
 
 
 
31.2*
 
 
 
 
 
 
32.1**
 
 
 
 
 
 
32.2**
 
 
 
 
 
 
101.INS*
 
XBRL Instance Document
 
 
 
 
 
101.SCH*
 
XBRL Taxonomy Extension Schema Document
 
 
 
 
 
101.CAL*
 
XBRL Taxonomy Extension Calculation Linkbase Document
 
 
 
 
 
101.DEF*
 
XBRL Taxonomy Extension Definition Linkbase Document
 
 
 
 
 
101.LAB*
 
XBRL Taxonomy Extension Labels Linkbase Document
 
 
 
 
 
101.PRE*
 
XBRL Taxonomy Extension Presentation Linkbase Document
 
 
 
 
 
104*
 
Cover Page Interactive Data File (formatted as Inline XBRL and contained in Exhibit 101)
 
 
 
 
 
 
(1)
Exhibits are incorporated by reference to reports of Cheniere (SEC File No. 001-16383), Cheniere Partners (SEC File No. 001-33366), Cheniere Holdings (SEC File No. 001-36234), SPL (SEC File No. 333-192373), CCH (SEC File No. 333-215435) and SPLNG (SEC File No. 333-138916), as applicable, unless otherwise indicated.
*
Filed herewith.
**
Furnished herewith.
Management contract or compensatory plan or arrangement.

132



SCHEDULE I—CONDENSED FINANCIAL INFORMATION OF REGISTRANT


CHENIERE ENERGY, INC.

CONDENSED BALANCE SHEETS
(in millions) 
 
December 31,
 
2019
 
2018
ASSETS
 

 
 
Current assets
 
 
 
Cash and cash equivalents
$
55

 
$

Other current assets
1

 
1

Total current assets
56

 
1

 
 
 
 
Property, plant and equipment, net
17

 
14

Operating lease assets, net
24

 

Debt issuance and deferred financing costs, net
16

 
21

Investments in subsidiaries
1,139

 
883

Deferred tax assets, net
315

 

Total assets
$
1,567

 
$
919

 
 
 
 
LIABILITIES AND STOCKHOLDERS’ DEFICIT
 
 
 
Current liabilities
 
 
 
Current operating lease liabilities
$
5

 
$

Other current liabilities
9

 
9

Total current liabilities
14

 
9

 
 
 
 
Long-term debt, net
1,534

 
1,436

Non-current operating lease liabilities
33

 

 
 
 
 
Stockholders’ deficit
(14
)
 
(526
)
Total liabilities and stockholders’ deficit
$
1,567

 
$
919


























The accompanying notes are an integral part of these condensed financial statements.

133



SCHEDULE I—CONDENSED FINANCIAL INFORMATION OF REGISTRANT


CHENIERE ENERGY, INC.

CONDENSED STATEMENTS OF OPERATIONS
(in millions) 
 
Year Ended December 31,
 
2019
 
2018
 
2017
General and administrative expense
$
17

 
$
8

 
$
7

 
 
 
 
 
 
Other income (expense)
 
 
 
 
 
Interest expense, net
(141
)
 
(128
)
 
(118
)
Interest income
1

 

 

Equity in income (loss) of subsidiaries
490

 
607

 
(268
)
Total other income (expense)
350

 
479

 
(386
)
 
 
 
 
 
 
Income (loss) before income taxes
333

 
471

 
(393
)
Income tax benefit
315

 

 

 
 
 
 
 
 
Net income (loss) attributable to common stockholders
$
648

 
$
471

 
$
(393
)



































The accompanying notes are an integral part of these condensed financial statements.

134



SCHEDULE I—CONDENSED FINANCIAL INFORMATION OF REGISTRANT


CHENIERE ENERGY, INC.

CONDENSED STATEMENTS OF STOCKHOLDERS’ DEFICIT
(in millions)
 
Common Stock
 
Treasury Stock
 
Additional Paid-in Capital
 
Accumulated Deficit
 
Total Member’s Deficit
Balance at December 31, 2016
$
1

 
$
(374
)
 
$
3,211

 
$
(4,234
)
 
$
(1,396
)
Issuance of stock to acquire additional interest in Cheniere Holdings

 

 
2

 

 
2

Share-based compensation

 

 
34

 

 
34

Shares withheld from employees related to share-based compensation, at cost

 
(12
)
 

 

 
(12
)
Equity portion of convertible notes, net

 

 
1

 

 
1

Net loss

 

 

 
(393
)
 
(393
)
Balance at December 31, 2017
1

 
(386
)
 
3,248

 
(4,627
)
 
(1,764
)
Issuance of stock to acquire additional interest in Cheniere Holdings and other merger related adjustments

 

 
694

 

 
694

Share-based compensation

 

 
90

 

 
90

Shares withheld from employees related to share-based compensation, at cost

 
(20
)
 

 

 
(20
)
Equity portion of convertible notes, net

 

 
3

 

 
3

Net income

 

 

 
471

 
471

Balance at December 31, 2018
1

 
(406
)
 
4,035

 
(4,156
)
 
(526
)
Share-based compensation

 

 
131

 

 
131

Shares withheld from employees related to share-based compensation, at cost

 
(19
)
 

 

 
(19
)
Shares repurchased, at cost

 
(249
)
 

 

 
(249
)
Equity portion of convertible notes, net

 

 
1

 

 
1

Net income

 

 

 
648

 
648

Balance at December 31, 2019
$
1

 
$
(674
)
 
$
4,167

 
$
(3,508
)
 
$
(14
)
























The accompanying notes are an integral part of these condensed financial statements.

135



SCHEDULE I—CONDENSED FINANCIAL INFORMATION OF REGISTRANT


CHENIERE ENERGY, INC.
CONDENSED STATEMENTS OF CASH FLOWS
(in millions) 
 
Year Ended December 31,
 
2019
 
2018
 
2017
Net cash provided by (used in) operating activities
$
74

 
$
48

 
$
(4
)
 
 
 
 
 
 
Cash flows from investing activities
 

 
 

 
 

Property, plant and equipment, net
(2
)
 

 

Investments in subsidiaries
842

 
568

 
209

Net cash provided by investing activities
840


568


209

 
 
 
 
 
 
Cash flows from financing activities
 

 
 

 
 

Debt issuance and deferred financing costs

 
(13
)
 
(15
)
Distribution and dividends to non-controlling interest
(591
)
 
(576
)
 
(185
)
Payments related to tax withholdings for share-based compensation
(19
)
 
(20
)
 
(12
)
Repurchase of common stock
(249
)
 

 

Other

 
(7
)
 

Net cash used in financing activities
(859
)
 
(616
)
 
(212
)
 
 
 
 
 
 
Net increase (decrease) in cash and cash equivalents
55

 

 
(7
)
Cash and cash equivalents—beginning of period

 

 
7

Cash and cash equivalents—end of period
$
55

 
$

 
$






























The accompanying notes are an integral part of these condensed financial statements.

136



SCHEDULE I—CONDENSED FINANCIAL INFORMATION OF REGISTRANT


CHENIERE ENERGY, INC.

NOTES TO CONDENSED FINANCIAL STATEMENTS

NOTE 1—SUMMARY OF SIGNIFICANT ACCOUNTING POLICIES

The Condensed Financial Statements represent the financial information required by Securities and Exchange Commission Regulation S-X 5-04 for Cheniere.
 
In the Condensed Financial Statements, Cheniere’s investments in affiliates are presented under the equity method of accounting. Under this method, the assets and liabilities of affiliates are not consolidated. The investments in net assets of the affiliates are recorded on the Condensed Balance Sheets. The loss from operations of the affiliates is reported on a net basis as investment in affiliates (investment in and equity in net income (loss) of affiliates).
 
A substantial amount of Cheniere’s operating, investing and financing activities are conducted by its affiliates. The Condensed Financial Statements should be read in conjunction with Cheniere’s Consolidated Financial Statements.

Recent Accounting Standards

We adopted ASU 2016-02, Leases (Topic 842), and subsequent amendments thereto (“ASC 842”) on January 1, 2019 using the optional transition approach to apply the standard at the beginning of the first quarter of 2019 with no retrospective adjustments to prior periods. The adoption of the standard resulted in the recognition of right-of-use assets and lease liabilities for operating leases of approximately $3 million on our Condensed Balance Sheets, with no material impact on our Condensed Statements of Operations or Condensed Statements of Cash Flows. We have elected the practical expedients to (1) carryforward prior conclusions related to lease identification and classification for existing leases, (2) combine lease and non-lease components of an arrangement for all classes of leased assets and (3) omit short-term leases with a term of 12 months or less from recognition on the balance sheet. See Note 4—Leases for additional information on our leases following the adoption of this standard.

NOTE 2—DEBT

As of December 31, 2019 and 2018, our debt consisted of the following (in millions): 
 
 
December 31,
 
 
2019
 
2018
Long-term debt:
 
 
 
 
4.875% Convertible Unsecured Notes due 2021
 
$
1,278

 
$
1,218

4.25% Convertible Senior Notes due 2045
 
625

 
625

$1.25 billion Cheniere Revolving Credit Facility
 

 

Unamortized premium, discount and debt issuance costs, net
 
(369
)
 
(407
)
Total long-term debt, net
 
$
1,534


$
1,436



In December 2018, we amended and restated the Cheniere Revolving Credit Facility to increase total commitments under the Cheniere Revolving Credit Facility from $750 million to $1.25 billion. We have posted $585 million of letters of credit on behalf of CCH under the Cheniere Revolving Credit Facility, which is available to us to back-stop our obligations under the Equity Contribution Agreement with CCH and, provided that certain conditions are met, for general corporate purposes.

Below is a schedule of future principal payments that we are obligated to make on our outstanding debt at December 31, 2019 (in millions): 
Years Ending December 31,
 
Principal Payments
2020
 
$

2021
 
1,278

2022
 

2023
 

2024
 

Thereafter
 
625

Total
 
$
1,903



137



SCHEDULE I—CONDENSED FINANCIAL INFORMATION OF REGISTRANT


CHENIERE ENERGY, INC.

NOTES TO CONDENSED FINANCIAL STATEMENTS—CONTINUED

NOTE 3—GUARANTEES
 
Cheniere has various financial and performance guarantees and indemnifications which are issued in the normal course of business. These contracts include performance guarantees and stand-by letters of credit. Cheniere enters into these arrangements to facilitate commercial transactions with third parties by enhancing the value of the transaction to the third party. As of December 31, 2019, outstanding guarantees and other assurances aggregated approximately $542 million of varying duration, consisting of parental guarantees. No liabilities were recognized under these guarantee arrangements as of December 31, 2019.

NOTE 4—LEASES

Our leased assets consist primarily of office space and facilities, which are classified as operating leases.

The following table shows the classification and location of our right-of-use assets and lease liabilities on our Condensed Balance Sheets (in millions):
 
Condensed Balance Sheet Location
 
December 31, 2019
Right-of-use assets—Operating
Operating lease assets, net
 
$
24

Total right-of-use assets
 
 
$
24

 
 
 
 
Current operating lease liabilities
Current operating lease liabilities
 
$
5

Non-current operating lease liabilities
Non-current operating lease liabilities
 
33

Total lease liabilities
 
 
$
38



The following table shows the classification and location of our lease cost on our Condensed Statements of Operations (in millions):
 
Condensed Statement of Operations Location
 
Year Ended December 31, 2019
Operating lease cost (1)
General and administrative expense
 
$
9

 
(1)
Includes $3 million of variable lease costs paid to the lessor.
Future annual minimum lease payments for operating leases as of December 31, 2019 are as follows (in millions): 
Years Ending December 31,
Operating Leases (1)
2020
$
7

2021
7

2022
7

2023
7

2024
7

Thereafter
12

Total lease payments
47

Less: Interest
(9
)
Present value of lease liabilities
$
38

 
(1)
Does not include $1 million of legally binding minimum lease payments for an office space lease which was executed as of December 31, 2019 but will commence in 2020 and has a fixed minimum lease terms of up to two years.

138



SCHEDULE I—CONDENSED FINANCIAL INFORMATION OF REGISTRANT


CHENIERE ENERGY, INC.

NOTES TO CONDENSED FINANCIAL STATEMENTS—CONTINUED

Future annual minimum lease payments for operating leases as of December 31, 2018, prepared in accordance with accounting standards prior to the adoption of ASC 842, were as follows (in millions):
Years Ending December 31,
Operating Leases (1)
2019
$
8

2020
6

2021
6

2022
6

2023
7

Thereafter
18

Total lease payments
$
51

 
(1)
Includes payments for certain non-lease components.

The following table shows the weighted-average remaining lease term (in years) and the weighted-average discount rate for our operating leases:
 
December 31, 2019
Weighted-average remaining lease term (in years)
6.6
Weighted-average discount rate
5.5%

The following table includes other quantitative information for our operating leases (in millions):
 
Year Ended December 31, 2019
Cash paid for amounts included in the measurement of lease liabilities:
 
Operating cash flows from operating leases
$
7

Right-of-use assets obtained in exchange for new operating lease liabilities
1



NOTE 5—SHARE REPURCHASE PROGRAM

On June 3, 2019, we announced that our Board authorized a 3-year, $1.0 billion share repurchase program. During the year ended December 31, 2019, we repurchased an aggregate of 4.0 million shares of our common stock for $249 million, for a weighted average price per share of $62.27.

As of December 31, 2019, we had up to $751 million of the share repurchase program available. Under the share repurchase program, repurchases can be made from time to time using a variety of methods, which may include open market purchases, privately negotiated transactions or otherwise, all in accordance with the rules of the SEC and other applicable legal requirements. The timing and amount of any shares of our common stock that are repurchased under the share repurchase program will be determined by our management based on market conditions and other factors.  The share repurchase program does not obligate us to acquire any particular amount of common stock, and may be modified, suspended or discontinued at any time or from time to time at our discretion.

139



SCHEDULE I—CONDENSED FINANCIAL INFORMATION OF REGISTRANT


CHENIERE ENERGY, INC.

NOTES TO CONDENSED FINANCIAL STATEMENTS—CONTINUED

NOTE 6 —SUPPLEMENTAL CASH FLOW INFORMATION

The following table provides supplemental disclosure of cash flow information (in millions): 
 
 
Year Ended December 31,
 
 
2019
 
2018
 
2017
Cash paid during the period for interest, net of amounts capitalized
 
$
36

 
$
32

 
$
31

Non-cash investing and financing activities:
 
 
 
 
 
 
Non-cash capital distribution (contributions) (1)
 
490

 
607

 
(268
)
Additional interest in Cheniere Holdings acquired
 

 
702

 
2

 
(1)
Amounts represent equity income (losses) of affiliates.

140


ITEM 16.
FORM 10-K SUMMARY

None.


141



SIGNATURES

Pursuant to the requirements of Section 13 or 15(d) of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized. 

 
 
CHENIERE ENERGY, INC.
 
 
(Registrant)
 
 
 
 
 
 
By:
/s/ Jack A. Fusco
 
 
 
Jack A. Fusco
 
 
 
President and Chief Executive Officer
(Principal Executive Officer)
 
 
Date:
February 24, 2020
Pursuant to the requirements of the Securities Exchange Act of 1934, this report has been signed below by the following persons on behalf of the registrant and in the capacities and on the dates indicated. 
Signature
Title
Date
 
 
 
/s/ Jack A. Fusco
President and Chief Executive Officer and Director
(Principal Executive Officer)
February 24, 2020
Jack A. Fusco
 
 
 
/s/ Michael J. Wortley
Executive Vice President and Chief Financial Officer
(Principal Financial Officer)
February 24, 2020
Michael J. Wortley
 
 
 
/s/ Leonard E. Travis
Vice President and Chief Accounting Officer
(Principal Accounting Officer)
February 24, 2020
Leonard E. Travis
 
 
 
/s/ G. Andrea Botta
Chairman of the Board
February 24, 2020
G. Andrea Botta
 
 
 
/s/ Vicky A. Bailey
Director
February 24, 2020
Vicky A. Bailey
 
 
 
/s/ Nuno Brandolini
Director
February 24, 2020
Nuno Brandolini
 
 
 
/s/ Michele A. Evans
Director
February 24, 2020
Michele A. Evans
 
 
 
/s/ David I. Foley
Director
February 24, 2020
David I. Foley
 
 
 
/s/ David B. Kilpatrick
Director
February 24, 2020
David B. Kilpatrick
 
 
 
/s/ Andrew Langham
Director
February 24, 2020
Andrew Langham
 
 
 
/s/ Courtney R. Mather 
Director
February 24, 2020
Courtney R. Mather
 
 
 
/s/ Donald F. Robillard, Jr.
Director
February 24, 2020
Donald F. Robillard, Jr.
 
 
 
/s/ Neal A. Shear
Director
February 24, 2020
Neal A. Shear
 
 
 

142