PROJECT NAME: Sabine Pass LNG Stage 4 Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: November 7, 2018 | CHANGE ORDER NUMBER: CO-00011 DATE OF CHANGE ORDER: October 01, 2019 |
1. | Pursuant to the instructions in Section 2.3.B of the Second Amended and Restated Umbrella Agreement in Attachment O of the Agreement, this Change Order amends the Insurance Provisional Sum amount to the Stage 4 Anticipated Actual Insurance Cost. |
2. | The Insurance Provisional Sum in Section 2.3 of Attachment EE, Schedule EE-2 of the Agreement prior to this Change Order was Fifty-Two Million, Five Hundred Thousand U.S. Dollars (U.S. $52,500,000). The Insurance Provisional Sum is hereby decreased by Eighteen Million, Two Hundred Fifty-Five Thousand, One Hundred Fifty U. S. Dollars (U.S. $18,255,150) and the new value as amended by this Change Order shall be Thirty-Four Million, Two Hundred Forty-Four Thousand, Eight Hundred Fifty U.S. Dollars (U.S. $34,244,850). |
3. | The detailed cost breakdown for this Change Order is detailed in Exhibit A of this Change Order. |
4. | Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit B of this Change Order. |
5. | The final adjustment to the Insurance Provisional Sum will be made in accordance with Section 2.3.C of the Second Amended and Restated Umbrella Agreement in Attachment O of the Agreement. |
1. | The original Contract Price Applicable to Subproject 6(a) was.............................................................................................................................................................. | $ | 2,016,892,573 | |
2. | Net change for Contract Price Applicable to Subproject 6(a) by previously authorized Change Orders (#00001-#00010)........................................................................................................................................ | $ | (1,414,200 | ) |
3. | The Contract Price Applicable to Subproject 6(a) prior to this Change Order was.............................................................................................................................................................. | $ | 2,015,478,373 | |
4. | The Contract Price Applicable to Subproject 6(a) will be decreased by this Change Order in the amount of.................................................................................................................................................... | $ | (18,255,150 | ) |
5. | The Provisional Sum Applicable to Subproject 6(a) will be decreased by this Change Order in the amount of.................................................................................................................................................... | $ | (18,255,150 | ) |
6. | The new Contract Price Applicable to Subproject 6(a) including this Change Order will be................................................................................................................................................................ | $ | 2,017,281,830 |
7. | The original Contract Price Applicable to Subproject 6(b) was............................................................................................................................................................. | $ | — | |
8. | Net change for Contract Price Applicable to Subproject 6(b) by previously authorized Change Orders (#00001-#00010)........................................................................................................................................ | $ | 457,696,000 | |
9. | The Contract Price Applicable to Subproject 6(b) prior to this Change Order was............................................................................................................................................................. | $ | 457,696,000 | |
10. | The Contract Price Applicable to Subproject 6(b) will be unchanged by this Change Order.......................................................................................................................................................... | $ | — | |
11. | The Provisional Sum Applicable to Subproject 6(b) will be unchanged by this Change Order.......................................................................................................................................................... | $ | — | |
12. | The new Contract Price Applicable to Subproject 6(b) including this Change Order will be................................................................................................................................................................ | $ | 457,696,000 |
13. | The original Contract Price was (add lines 1 and 7)................................................................................. | $ | 2,016,892,573 | |
14. | The Contract Price prior to this Change Order was (add lines 3 and 9).................................................... | $ | 2,473,174,373 | |
15. | The Contract Price will be decreased by this Change Order in the amount of (add lines 4 and 10)......... | $ | (18,255,150 | ) |
16. | The new Contract Price including this Change Order will be (add lines 14 and 15)................................ | $ | 2,454,919,223 |
/s/ David Craft | /s/ Maurissa D. Rogers | |
Owner | Contractor | |
David Craft | Maurissa D. Rogers | |
Name | Name | |
SVP E&C | Sr Project Manager, PVP | |
Title | Title | |
October 10, 2019 | October 1, 2019 | |
Date of Signing | Date of Signing |
PROJECT NAME: Sabine Pass LNG Stage 4 Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: November 7, 2018 | CHANGE ORDER NUMBER: CO-00012 DATE OF CHANGE ORDER: October 30, 2019 |
1. | In accordance with Section 6.1 of the Agreement (Change Orders Requested by Owner), the Parties agree this change order reflects the change in Scope of Work and total costs to replace two hundred four (204) existing timber piles with pre-stressed concrete piles in Areas F01, C02, B01 and L01, and the addition of ninety-seven (97) pre-stressed concrete piles in Areas K01 and F01. |
2. | The detailed cost breakdown for this Change Order is detailed in Exhibit A of this Change Order. |
3. | Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit B of this Change Order. |
1. | The original Contract Price Applicable to Subproject 6(a) was.............................................................................................................................................................. | $ | 2,016,892,573 | |
2. | Net change for Contract Price Applicable to Subproject 6(a) by previously authorized Change Orders (#00001-#00011)........................................................................................................................................ | $ | (19,669,350 | ) |
3. | The Contract Price Applicable to Subproject 6(a) prior to this Change Order was.............................................................................................................................................................. | $ | 1,997,223,223 | |
4. | The Contract Price Applicable to Subproject 6(a) will be increased by this Change Order in the amount of.................................................................................................................................................... | $ | 585,088 | |
5. | The Provisional Sum Applicable to Subproject 6(a) will be unchanged by this Change Order in the amount of.................................................................................................................................................... | $ | — | |
6. | The new Contract Price Applicable to Subproject 6(a) including this Change Order will be................................................................................................................................................................ | $ | 1,997,808,311 |
7. | The original Contract Price Applicable to Subproject 6(b) was............................................................................................................................................................. | $ | — | |
8. | Net change for Contract Price Applicable to Subproject 6(b) by previously authorized Change Orders (#00001-#00011)........................................................................................................................................ | $ | 457,696,000 | |
9. | The Contract Price Applicable to Subproject 6(b) prior to this Change Order was............................................................................................................................................................. | $ | 457,696,000 | |
10. | The Contract Price Applicable to Subproject 6(b) will be unchanged by this Change Order.......................................................................................................................................................... | $ | — | |
11. | The Provisional Sum Applicable to Subproject 6(b) will be unchanged by this Change Order.......................................................................................................................................................... | $ | — | |
12. | The new Contract Price Applicable to Subproject 6(b) including this Change Order will be................................................................................................................................................................ | $ | 457,696,000 |
13. | The original Contract Price was (add lines 1 and 7)................................................................................. | $ | 2,016,892,573 | |
14. | The Contract Price prior to this Change Order was (add lines 3 and 9).................................................... | $ | 2,454,919,223 | |
15. | The Contract Price will be increased by this Change Order in the amount of (add lines 4 and 10)......... | $ | 585,088 | |
16. | The new Contract Price including this Change Order will be (add lines 14 and 15)................................ | $ | 2,455,504,311 |
/s/ David Craft | /s/ Maurissa D. Rogers | |
Owner | Contractor | |
David Craft | Maurissa D. Rogers | |
Name | Name | |
SVP E&C | Sr Project Manager, PVP | |
Title | Title | |
November 13, 2019 | October 30, 2019 | |
Date of Signing | Date of Signing |