PROJECT NAME: Corpus Christi Stage 2 Liquefaction Facility OWNER: Corpus Christi Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 12, 2017 | CHANGE ORDER NUMBER: 00019 DATE OF CHANGE ORDER: Sep 23, 2019 |
1. | Pursuant to Article 6.1 of the Agreement (Change Orders Requested by Owner), Parties agree this Change Order includes Contractor’s cost for changes to the Train 3 aircraft warning lights. |
2. | The summary cost breakdown for this Change Order is detailed in Exhibit 1 of this Change Order. |
3. | The detailed cost breakdown of this Change Order is provided in Exhibit 3 of this Change Order. |
4. | Schedules C-1 and C-3 (Milestone Payment Schedules) of Attachment C of the Agreement will be amended by including the Milestones listed in Exhibit 2 of this Change Order. |
The original Contract Price was......................................................................................................................... | $ | 2,360,000,000 | |
Net change by previously authorized Change Orders (00001-00018)............................................................... | $ | 26,202,435 | |
The Contract Price prior to this Change Order was........................................................................................... | $ | 2,386,202,435 | |
The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... | $ | [***] | |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... | $ | [***] | |
The new Contract Price including this Change Order will be........................................................................... | $ | 2,386,268,002 |
The original Aggregate Equipment Price was................................................................................................... | $ | [***] |
Net change by previously authorized Change Orders (00001-00018)............................................................... | $ | [***] |
The Aggregate Equipment Price prior to this Change Order was...................................................................... | $ | [***] |
The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... | $ | [***] |
The new Aggregate Equipment Price including this Change Order will be ..................................................... | $ | [***] |
The original Aggregate Labor and Skills Price was.......................................................................................... | $ | [***] |
Net change by previously authorized Change Orders (00001-00018)............................................................... | $ | [***] |
The Aggregate Labor and Skills Price prior to this Change Order was............................................................. | $ | [***] |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... | $ | [***] |
The new Aggregate Labor and Skills Price including this Change Order will be............................................. | $ | [***] |
The original Aggregate Provisional Sum was.................................................................................................... | $ | 295,549,906 | |
Net change by previously authorized Change Orders (00001-00018)............................................................... | $ | (18,272,757 | ) |
The Aggregate Provisional Sum prior to this Change Order was...................................................................... | $ | 277,277,149 | |
The Aggregate Provisional Sum will be changed by this Change Order in the amount of............................... | $ | — | |
The new Aggregate Provisional Sum including this Change Order will be...................................................... | $ | 277,277,149 |
/s/ David Craft | /s/ Bhupesh Thakkar | |
Owner | Contractor | |
David Craft | Bhupesh Thakkar | |
Name | Name | |
SVP, E&C | Program Manager, Cheniere Projects | |
Title | Title | |
October 10, 2019 | September 23, 2019 | |
Date of Signing | Date of Signing |
PROJECT NAME: Corpus Christi Stage 2 Liquefaction Facility OWNER: Corpus Christi Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 12, 2017 | CHANGE ORDER NUMBER: 00020 DATE OF CHANGE ORDER: October 8, 2019 |
1. | Pursuant to Article 6 of the Agreement, Parties agree this Change Order includes impacts from Section 232 Tariffs on Steel and Aluminum on Applicable Law, and Change in Law impacts imposing Anti-dumping (ADA) and Countervailing Duties (CVD) on specific steel and aluminum imports, which are based on the following two (2) approved Trends: |
i. | Trend No. S2-0005c - Impacts of Policy Change/Applicable Law Imposing Tariff on Steel and Aluminum (Section 232); and |
ii. | Trend No. S2-0006c - Anti-Dumping and Countervailing Duties (ADA/CVD). |
2. | This Change Order includes the costs during the 2nd Quarter of 2019, and excludes all costs, cost impacts, or effects of the change associated with these trends beyond these dates. Any subsequent costs, cost impacts, or effects of the change associated with these trends beyond these dates will be assessed on a quarterly basis and included in separate, future Change Order(s). |
3. | The summary cost breakdown for the scope of this Change Order is detailed in Exhibit 1 of this Change Order. |
4. | The detailed cost breakdown for the scope of this Change Order is detailed in Exhibit 3 (Trend No. S2-0005c) and Exhibit 4 (Trend No. S2-0006c). |
5. | The detailed costs for Customs Entry for the scope of this Change Order is detailed in Exhibit 5 (Trend No. S2-0005c) and Exhibit 6 (Trend No. S2-0006c). |
6. | Schedules C-1 and C-3 (Milestone Payment Schedules) of Attachment C of the Agreement will be amended by including the Milestones listed in Exhibit 2 of this Change Order. |
The original Contract Price was......................................................................................................................... | $ | 2,360,000,000 | |
Net change by previously authorized Change Orders (00001-00019)............................................................... | $ | 26,268,002 | |
The Contract Price prior to this Change Order was........................................................................................... | $ | 2,386,268,002 | |
The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... | $ | [***] | |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... | $ | [***] | |
The new Contract Price including this Change Order will be........................................................................... | $ | 2,389,688,411 |
The original Aggregate Equipment Price was................................................................................................... | $ | [***] |
Net change by previously authorized Change Orders (00001-00019)............................................................... | $ | [***] |
The Aggregate Equipment Price prior to this Change Order was...................................................................... | $ | [***] |
The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... | $ | [***] |
The new Aggregate Equipment Price including this Change Order will be ..................................................... | $ | [***] |
The original Aggregate Labor and Skills Price was.......................................................................................... | $ | [***] |
Net change by previously authorized Change Orders (00001-00019)............................................................... | $ | [***] |
The Aggregate Labor and Skills Price prior to this Change Order was............................................................. | $ | [***] |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... | $ | [***] |
The new Aggregate Labor and Skills Price including this Change Order will be............................................. | $ | [***] |
The original Aggregate Provisional Sum was.................................................................................................... | $ | 295,549,906 | |
Net change by previously authorized Change Orders (00001-00019)............................................................... | $ | (18,272,757 | ) |
The Aggregate Provisional Sum prior to this Change Order was...................................................................... | $ | 277,277,149 | |
The Aggregate Provisional Sum will be changed by this Change Order in the amount of............................... | $ | — | |
The new Aggregate Provisional Sum including this Change Order will be...................................................... | $ | 277,277,149 |
/s/ David Craft | /s/ Bhupesh Thakkar | |
Owner | For Contractor | |
David Craft | Bhupesh Thakkar | |
Name | Name | |
SVP, E&C | SVP, Program Manager | |
Title | Title | |
October 11, 2019 | October 8, 2019 | |
Date of Signing | Date of Signing |
PROJECT NAME: Corpus Christi Stage 2 Liquefaction Facility OWNER: Corpus Christi Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 12, 2017 | CHANGE ORDER NUMBER: 00021 DATE OF CHANGE ORDER: October 8, 2019 |
1. | Pursuant to Article 6 of the Agreement, Parties agree this Change Order includes the cost of engineering and sourcing of spare transition joints for potential future Train 3 cold box modifications. Per this Change Order, a total of seven (7) transition joints: five (5) for Methane Cold Box and two (2) for Ethylene Cold Box - 1504A/B shall be procured and made available at Site should Owner elect to proceed with the field modification of the Train 3 cold boxes to implement the modified design to reduce the number of transition joints. |
2. | The summary cost breakdown for the total Scope of Work of this Change Order is detailed in Exhibit 1 of this Change Order. |
3. | The detailed cost breakdown for the Scope of Work of this Change Order is provided in Exhibit 3 of this Change Order. |
4. | Schedules C-1 and C-3 (Milestone Payment Schedules) of Attachment C of the Agreement will be amended by including the Milestones listed in Exhibit 2 of this Change Order. |
The original Contract Price was......................................................................................................................... | $ | 2,360,000,000 | |
Net change by previously authorized Change Orders (00001-00020)............................................................... | $ | 29,688,411 | |
The Contract Price prior to this Change Order was........................................................................................... | $ | 2,389,688,411 | |
The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... | $ | [***] | |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... | $ | [***] | |
The new Contract Price including this Change Order will be........................................................................... | $ | 2,389,888,443 |
The original Aggregate Equipment Price was................................................................................................... | $ | [***] |
Net change by previously authorized Change Orders (00001-00020)............................................................... | $ | [***] |
The Aggregate Equipment Price prior to this Change Order was...................................................................... | $ | [***] |
The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... | $ | [***] |
The new Aggregate Equipment Price including this Change Order will be ..................................................... | $ | [***] |
The original Aggregate Labor and Skills Price was.......................................................................................... | $ | [***] |
Net change by previously authorized Change Orders (00001-00020)............................................................... | $ | [***] |
The Aggregate Labor and Skills Price prior to this Change Order was............................................................. | $ | [***] |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... | $ | [***] |
The new Aggregate Labor and Skills Price including this Change Order will be............................................. | $ | [***] |
The original Aggregate Provisional Sum was.................................................................................................... | $ | 295,549,906 | |
Net change by previously authorized Change Orders (00001-00020)............................................................... | $ | (18,272,757 | ) |
The Aggregate Provisional Sum prior to this Change Order was...................................................................... | $ | 277,277,149 | |
The Aggregate Provisional Sum will be changed by this Change Order in the amount of............................... | $ | — | |
The new Aggregate Provisional Sum including this Change Order will be...................................................... | $ | 277,277,149 |
/s/ David Craft | /s/ Bhupesh Thakkar | |
Owner | For Contractor | |
David Craft | Bhupesh Thakkar | |
Name | Name | |
SVP, E&C | SVP, Program Manager | |
Title | Title | |
October 11, 2019 | October 8, 2019 | |
Date of Signing | Date of Signing |
PROJECT NAME: Corpus Christi Stage 2 Liquefaction Facility OWNER: Corpus Christi Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 12, 2017 | CHANGE ORDER NUMBER: 00022 DATE OF CHANGE ORDER: December 6, 2019 |
1. | Pursuant to Article 6.1 of the Agreement (Change Orders Requested by Owner), Parties agree this Change Order sets forth the scope of work to perform modifications to the Train 3 Methane Cold Box (E-1605) as described in more detail in Exhibit 4 of this Change Order (“Cold Box Modification Scope of Work”). Other than Contractor’s costs and expenses pertaining only to the additional Work described in Exhibit 4 for the Cold Box Modification Scope of Work, this Change Order does not set forth the effect, if any, of the Cold Box Modifications Scope of Work on the Changed Criteria. For example, impacts on Project Schedule (such as delays associated with potential damage to the core of the exchanger or other long lead items) and any costs incurred by Contractor arising from such impacts are not covered in this Change Order. If any such impacts occur, then the effects, if any, will be addressed by Owner and Contractor. |
2. | As further described in Exhibit 4 of this Change Order, Contractor shall reduce the number of transition joints (“TJs”) inside the methane cold box (E-1605) by replacing stainless steel pipe with aluminum and relocating TJs outside of the cold box. The design will have five (5) TJs on the exterior of the cold box in lieu of sixteen (16) TJs inside (original design basis). The Cold Box Modification Scope of Work includes the following activities: scaffolding, rigging, temporary supports, cutting of the cold box roof/walls, opening manways, cutting pipe, welding, testing and closing of the methane cold box (E1605). |
3. | The summary cost breakdown for the Scope of Work of this Change Order is provided in Exhibit 1 of this Change Order. |
4. | The detailed cost breakdown for the Scope of Work of this Change Order is provided in Exhibit 3 of this Change Order. |
5. | Schedules C-1 and C-3 (Milestone Payment Schedules) of Attachment C of the Agreement will be amended by including the Milestones listed in Exhibit 2 of this Change Order. |
The original Contract Price was......................................................................................................................... | $ | 2,360,000,000 | |
Net change by previously authorized Change Orders (00001-00021)............................................................... | $ | 29,888,443 | |
The Contract Price prior to this Change Order was........................................................................................... | $ | 2,389,888,443 | |
The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... | $ | [***] | |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... | $ | [***] | |
The new Contract Price including this Change Order will be........................................................................... | $ | 2,395,637,222 |
The original Aggregate Equipment Price was................................................................................................... | $ | [***] |
Net change by previously authorized Change Orders (00001-00021)............................................................... | $ | [***] |
The Aggregate Equipment Price prior to this Change Order was...................................................................... | $ | [***] |
The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... | $ | [***] |
The new Aggregate Equipment Price including this Change Order will be ..................................................... | $ | [***] |
The original Aggregate Labor and Skills Price was.......................................................................................... | $ | [***] |
Net change by previously authorized Change Orders (00001-00021)............................................................... | $ | [***] |
The Aggregate Labor and Skills Price prior to this Change Order was............................................................. | $ | [***] |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... | $ | [***] |
The new Aggregate Labor and Skills Price including this Change Order will be............................................. | $ | [***] |
The original Aggregate Provisional Sum was.................................................................................................... | $ | 295,549,906 | |
Net change by previously authorized Change Orders (00001-00021)............................................................... | $ | (18,272,757 | ) |
The Aggregate Provisional Sum prior to this Change Order was...................................................................... | $ | 277,277,149 | |
The Aggregate Provisional Sum will be changed by this Change Order in the amount of............................... | $ | — | |
The new Aggregate Provisional Sum including this Change Order will be...................................................... | $ | 277,277,149 |
/s/ David Craft | /s/ Bhupesh Thakkar | |
Owner | For Contractor | |
David Craft | Bhupesh Thakkar | |
Name | Name | |
SVP, E&C | Program Manager | |
Title | Title | |
December 20, 2019 | December 9, 2019 | |
Date of Signing | Date of Signing |
PROJECT NAME: Corpus Christi Stage 2 Liquefaction Facility OWNER: Corpus Christi Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 12, 2017 | CHANGE ORDER NUMBER: 00023 DATE OF CHANGE ORDER: December 10, 2019 |
1. | Pursuant to Article 6 of the Agreement, Parties agree this Change Order includes impacts from Section 232 Tariffs on Steel and Aluminum on Applicable Law, and Change in Law impacts imposing Anti-dumping (ADA) and Countervailing Duties (CVD) on specific steel and aluminum imports, which are based on the following two (2) approved Trends: |
i. | Trend No. S2-0005d - Impacts of Policy Change/Applicable Law Imposing Tariff on Steel and Aluminum (Section 232); and |
ii. | Trend No. S2-0006d - Anti-Dumping and Countervailing Duties (ADA/CVD). |
2. | This Change Order includes the costs during the 3rd Quarter of 2019, and excludes all costs, cost impacts, or effects of the change associated with these trends beyond these dates. Any subsequent costs, cost impacts, or effects of the change associated with these trends beyond these dates will be assessed on a quarterly basis and included in separate, future Change Order(s). |
3. | The summary cost breakdown for the scope of this Change Order is detailed in Exhibit 1 of this Change Order. |
4. | The detailed cost breakdown for the scope of this Change Order is detailed in Exhibit 3 (Trend No. S2-0005d) and Exhibit 4 (Trend No. S2-0006d). |
5. | The detailed costs for Customs Entry for the scope of this Change Order is detailed in Exhibit 5 (Trend No. S2-0005d) and Exhibit 6 (Trend No. S2-0006d). |
6. | Schedules C-1 and C-3 (Milestone Payment Schedules) of Attachment C of the Agreement will be amended by including the Milestones listed in Exhibit 2 of this Change Order. |
The original Contract Price was......................................................................................................................... | $ | 2,360,000,000 | |
Net change by previously authorized Change Orders (00001-00022)............................................................... | $ | 35,637,222 | |
The Contract Price prior to this Change Order was........................................................................................... | $ | 2,395,637,222 | |
The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... | $ | [***] | |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... | $ | [***] | |
The new Contract Price including this Change Order will be........................................................................... | $ | 2,395,690,192 |
The original Aggregate Equipment Price was................................................................................................... | $ | [***] |
Net change by previously authorized Change Orders (00001-00022)............................................................... | $ | [***] |
The Aggregate Equipment Price prior to this Change Order was...................................................................... | $ | [***] |
The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... | $ | [***] |
The new Aggregate Equipment Price including this Change Order will be ..................................................... | $ | [***] |
The original Aggregate Labor and Skills Price was.......................................................................................... | $ | [***] |
Net change by previously authorized Change Orders (00001-00022)............................................................... | $ | [***] |
The Aggregate Labor and Skills Price prior to this Change Order was............................................................. | $ | [***] |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... | $ | [***] |
The new Aggregate Labor and Skills Price including this Change Order will be............................................. | $ | [***] |
The original Aggregate Provisional Sum was.................................................................................................... | $ | 295,549,906 | |
Net change by previously authorized Change Orders (00001-00022)............................................................... | $ | (18,272,757 | ) |
The Aggregate Provisional Sum prior to this Change Order was...................................................................... | $ | 277,277,149 | |
The Aggregate Provisional Sum will be changed by this Change Order in the amount of............................... | $ | — | |
The new Aggregate Provisional Sum including this Change Order will be...................................................... | $ | 277,277,149 |
/s/ David Craft | /s/ Bhupesh Thakkar | |
Owner | For Contractor | |
David Craft | Bhupesh Thakkar | |
Name | Name | |
SVP, E&C | Program Manager | |
Title | Title | |
December 18, 2019 | December 11, 2019 | |
Date of Signing | Date of Signing |