Annual report pursuant to Section 13 and 15(d)

Commitments and Contingencies

v3.8.0.1
Commitments and Contingencies
12 Months Ended
Dec. 31, 2017
Commitments and Contingencies Disclosure [Abstract]  
Commitments and Contingencies
COMMITMENTS AND CONTINGENCIES

We have various contractual obligations which are recorded as liabilities in our Consolidated Financial Statements. Other items, such as certain purchase commitments and other executed contracts which do not meet the definition of a liability as of December 31, 2017, are not recognized as liabilities but require disclosures in our Consolidated Financial Statements.

LNG Terminal Commitments and Contingencies
 
Obligations under EPC Contracts

SPL has lump sum turnkey contract with Bechtel Oil, Gas and Chemicals, Inc. (“Bechtel”) for the engineering, procurement and construction of Train 5 of the SPL Project. The EPC contract for SPL Train 5 provides that SPL will pay Bechtel a contract price of $3.1 billion, subject to adjustment by change order.  SPL has the right to terminate the EPC contract for its convenience, in which case Bechtel will be paid (1) the portion of the contract price for the work performed, (2) costs reasonably incurred by Bechtel on account of such termination and demobilization and (3) a lump sum of up to $30 million depending on the termination date.

CCL has lump sum turnkey contracts with Bechtel for the engineering, procurement and construction of Stage 1 and Stage 2 of the CCL Project. The EPC contract for Stage 2 of the CCL Project was amended and restated in December 2017. The EPC contract prices for Stage 1 of the CCL Project and Stage 2 of the CCL Project are approximately $7.8 billion and $2.4 billion, respectively, reflecting amounts incurred under change orders through December 31, 2017. CCL has the right to terminate each of the EPC contracts for its convenience, in which case Bechtel will be paid the portion of the contract price for the work performed plus costs reasonably incurred by Bechtel on account of such termination and demobilization. If the EPC contract for Stage 1 of the CCL Project is terminated, Bechtel will also be paid a lump sum of up to $30 million depending on the termination date. If the amended and restated EPC contract for Stage 2 of the CCL Project is terminated, Bechtel will be paid a lump sum of up to $2.5 million if the termination date is prior to the issuance of the notice to proceed, or Bechtel will be paid a lump sum of up to $30 million if the termination date is after the issuance of the notice to proceed, depending on the termination date.

Obligations under SPAs

SPL has third-party SPAs which obligate SPL to purchase and liquefy sufficient quantities of natural gas to deliver contracted volumes of LNG to the customers’ vessels, subject to completion of construction of specified Trains of the SPL Project.

CCL has third-party SPAs which obligate CCL to purchase and liquefy sufficient quantities of natural gas to deliver contracted volumes of LNG to the customers’ vessels, subject to completion of construction of specified Trains of the CCL Project.
 
Obligations under LNG TUAs
 
SPLNG has third-party TUAs with Total Gas & Power North America, Inc. and Chevron U.S.A. Inc. to provide berthing for LNG vessels and for the unloading, storage and regasification of LNG at the Sabine Pass LNG terminal.

Obligations under Natural Gas Supply, Transportation and Storage Service Agreements

SPL and CCL have index-based physical natural gas supply contracts to secure natural gas feedstock for the SPL Project and CCL Project, respectively. The terms of these contracts primarily range from approximately one to six years and commence upon the occurrence of conditions precedent, including declaration by SPL or CCL to the respective natural gas supplier that it is ready to commence the term of the supply arrangement in anticipation of the date of first commercial operation of the applicable, specified Trains of the SPL Project or CCL Project. As of December 31, 2017, SPL and CCL have secured up to approximately 2,214 TBtu and 2,024 TBtu, respectively, of natural gas feedstock through natural gas supply contracts, a portion of which are considered purchase obligations if the conditions precedent were met.

Additionally, SPL has transportation and storage service agreements for the SPL Project. The initial terms of the transportation agreements range from one to 20 years, with renewal options for certain contracts, and commences upon the occurrence of conditions precedent. The term of the SPL storage service agreements ranges from three to ten years.

As of December 31, 2017, our obligations under natural gas supply, transportation and storage service agreements for contracts in which conditions precedent were met were as follows (in millions): 
Years Ending December 31,
Payments Due (1)
2018
$
2,274

2019
1,527

2020
1,397

2021
981

2022
336

Thereafter
1,169

Total
$
7,684

 
(1)
Pricing of natural gas supply contracts are variable based on market commodity basis prices adjusted for basis spread. Amounts included are based on prices and basis spreads as of December 31, 2017.
    
Restricted Net Assets
 
At December 31, 2017, our restricted net assets of consolidated subsidiaries were approximately $3.4 billion.

Obligations under Certain Guarantee Contracts

Cheniere and certain of its subsidiaries enter into guarantee arrangements in the normal course of business to facilitate transactions with third parties. These arrangements include financial guarantees, letters of credit and debt guarantees. As of December 31, 2017 and 2016, there were no liabilities recognized under these guarantee arrangements.

Other Commitments
 
In the ordinary course of business, we have entered into certain multi-year licensing and service agreements, none of which are considered material to our financial position. Additionally, we have various lease commitments, as disclosed in Note 18—Leases.

Legal Proceedings

We may in the future be involved as a party to various legal proceedings, which are incidental to the ordinary course of business. We regularly analyze current information and, as necessary, provide accruals for probable liabilities on the eventual disposition of these matters.

Parallax Litigation

In 2015, our wholly owned subsidiary, Cheniere LNG Terminals, LLC (“CLNGT”), entered into discussions with Parallax Enterprises, LLC (“Parallax Enterprises”) regarding the potential joint development of two liquefaction plants in Louisiana (the “Potential Liquefaction Transactions”). While the parties negotiated regarding the Potential Liquefaction Transactions, CLNGT loaned Parallax Enterprises approximately $46 million, as reflected in a secured note dated April 23, 2015, as amended on June 30, 2015, September 30, 2015 and November 4, 2015 (the “Secured Note”). The Secured Note was secured by all assets of Parallax Enterprises and its subsidiary entities. On June 30, 2015, Parallax Enterprises’ parent entity, Parallax Energy LLC (“Parallax Energy”), executed a Pledge and Guarantee Agreement further securing repayment of the Secured Note by providing a parent guaranty and a pledge of all of the equity of Parallax Enterprises in satisfaction of the Secured Note (the “Pledge Agreement”). CLNGT and Parallax Enterprises never executed a definitive agreement to pursue the Potential Liquefaction Transactions. The Secured Note matured on December 11, 2015, and Parallax Enterprises failed to make payment. On February 3, 2016, CLNGT filed an action against Parallax Energy, Parallax Enterprises and certain of Parallax Enterprises’ subsidiary entities, styled Cause No. 4:16-cv-00286, Cheniere LNG Terminals, LLC v. Parallax Energy LLC, et al., in the United States District Court for the Southern District of Texas (the “Texas Federal Suit”). CLNGT asserted claims in the Texas Federal Suit for (1) recovery of all amounts due under the Secured Note and (2) declaratory relief establishing that CLNGT is entitled to enforce its rights under the Secured Note and Pledge Agreement in accordance with each instrument’s terms and that CLNGT has no obligations of any sort to Parallax Enterprises concerning the Potential Liquefaction Transactions. On March 11, 2016, Parallax Enterprises and the other defendants in the Texas Federal Suit moved to dismiss the suit for lack of subject matter jurisdiction. On August 2, 2016, the court denied the defendants’ motion to dismiss without prejudice and permitted the parties to pursue jurisdictional discovery.

On March 11, 2016, Parallax Enterprises filed a suit against us and CLNGT styled Civil Action No. 62-810, Parallax Enterprises LLP v. Cheniere Energy, Inc. and Cheniere LNG Terminals, LLC, in the 25th Judicial District Court of Plaquemines Parish, Louisiana (the “Louisiana Suit”), wherein Parallax Enterprises asserted claims for breach of contract, fraudulent inducement, negligent misrepresentation, detrimental reliance, unjust enrichment and violation of the Louisiana Unfair Trade Practices Act. Parallax Enterprises predicated its claims in the Louisiana Suit on an allegation that we and CLNGT breached a purported agreement to jointly develop the Potential Liquefaction Transactions. Parallax Enterprises sought $400 million in alleged economic damages and rescission of the Secured Note. On April 15, 2016, we and CLNGT removed the Louisiana Suit to the United States District Court for the Eastern District of Louisiana, which subsequently transferred the Louisiana Suit to the United States District Court for the Southern District of Texas, where it was assigned Civil Action No. 4:16-cv-01628 and transferred to the same judge presiding over the Texas Federal Suit for coordinated handling. On August 22, 2016, Parallax Enterprises voluntarily dismissed all claims asserted against CLNGT and us in the Louisiana Suit without prejudice to refiling.

On July 27, 2017, the Parallax entities named as defendants in the Texas Federal Suit reurged their motion to dismiss and simultaneously filed counterclaims against CLNGT and third party claims against us for breach of contract, breach of fiduciary duty, promissory estoppel, quantum meruit and fraudulent inducement of the Secured Note and Pledge Agreement, based on substantially the same factual allegations Parallax Enterprises made in the Louisiana Suit. These Parallax entities also simultaneously filed an action styled Cause No. 2017-49685, Parallax Enterprises, LLC, et al. v. Cheniere Energy, Inc., et al., in the 61st District Court of Harris County, Texas (the “Texas State Suit”), which asserts substantially the same claims these entities asserted in the Texas Federal Suit. On July 31, 2017, CLNGT withdrew its opposition to the dismissal of the Texas Federal Suit without prejudice on jurisdictional grounds and the federal court subsequently dismissed the Texas Federal Suit without prejudice. We and CLNGT simultaneously filed an answer and counterclaims in the Texas State Suit, asserting the same claims CLNGT had previously asserted in the Texas Federal Suit. Additionally, CLNGT filed third party claims against Parallax principals Martin Houston, Christopher Bowen Daniels, Howard Candelet and Mark Evans, as well as Tellurian Investments, Inc., Driftwood LNG, LLC, Driftwood LNG Pipeline LLC and Tellurian Services LLC, formerly known as Parallax Services LLC, including claims for tortious interference with CLNGT’s collateral rights under the Secured Note and Pledge Agreement, fraudulent transfer, conspiracy/aiding and abetting. Discovery in the Texas State Suit is ongoing. Trial is currently set for September 2018.

We do not expect that the resolution of this litigation will have a material adverse impact on our financial results.