EXHIBIT 10.95
Schedule D-1
CHANGE ORDER FORM
(for use when the parties mutually agree upon and execute the Change Order Pursuant to Section 6.1B or 6.2C)
PROJECT NAME: Creole Trail Pipeline Segment 1 |
CHANGE ORDER NUMBER: CO 1-001 | |
Project, Preferred Route Single Line Option |
||
OWNER: Cheniere Creole Trail Pipeline, L.P. |
DATE OF CHANGE ORDER: 2/7/08 | |
CONTRACTOR: Sunland Construction, Inc. |
||
DATE OF AGREEMENT: March 12, 2007 |
The Agreement between the Parties listed above is changed as follows: (attach additional documentation if necessary)
Provide labor and equipment to install and remove one extra push site at MLV 1-3. This change order includes additional board road material and mats required at the site. Seventy percent (70%) will be payable upon installation of the push site ($1,029,221.20) and thirty percent (30%) will be payable upon removal of the push site ($441,094.80).
Adjustment to Estimated Contract Price |
|||
The original Estimated Contract Price was |
$ | 43,617,209 | |
Net change by previously authorized Change Order (# ) |
$ | 0 | |
The Estimated Contract Price prior to this Change Order was |
$ | 43,617,209 | |
The Estimated Contract Price will be increased by this Change Order in the amount of |
$ | 1,470,316 | |
The new Estimated Contract Price including this Change Order will be |
$ | 45,087,525 | |
Adjustment to dates in Project Schedule
The following dates are modified (list all dates modified; insert N/A if no dates modified):
The Required Mechanical Completion Date will be unchanged by ( ) Days
The Required Mechanical Completion Date as of the date of this Change Order therefore is March 15, 20 08
(attach additional documentation if necessary) No Attachment
The Required Substantial Completion Date will be unchanged by ( ) Days
The Required Substantial Completion Date as of the date of this Change Order therefore is
(attach additional documentation if necessary) No Attachment
The Required Final Completion Date will be unchanged by ( ) Days
The Required Final Completion Date as of the date of this Change Order therefore is
(attach additional documentation if necessary) No Attachment
Adjustment to other Changed Criteria (insert N/A if no changes or impact; attach additional documentation if necessary) N/A
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previous issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties duly authorized representatives.
Cheniere Creole Trail Pipeline, L.P. | Sunland Construction, Inc. | |||
Owner | Contractor | |||
/s/ R. Keith Teague | /s/ Randy P. Mat | |||
Name |
Name | |||
R. Keith Teague/President | Project Manager | |||
Title | Title | |||
2/21/2008 | 2-19-08 | |||
Date of Signing | Date of Signing |