PROJECT NAME: Corpus Christi Stage 2 Liquefaction Facility OWNER: Corpus Christi Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 12, 2017 | CHANGE ORDER NUMBER: 00031 DATE OF CHANGE ORDER: April 1, 2020 |
1. | Pursuant to Article 6.1 of the Agreement (Change Orders Requested by Owner), Parties agree this Change Order includes Contractor’s costs to engineer, procure, construct and commission the new isolations necessary to support a proposed fourth in-tank LNG pump (2,000 m3/hr) by Owner (post Transfer, Care, Custody and Control (“TCCC”) of Tank B to Owner). |
2. | The summary cost breakdown for the total Scope of Work of this Change Order is detailed in Exhibit 1 of this Change Order. |
3. | The detailed cost breakdown for the Scope of Work of this Change Order is provided in Exhibit 3 of this Change Order. |
4. | Schedules C-1 and C-3 (Milestone Payment Schedules) of Attachment C of the Agreement will be amended by including the Milestones listed in Exhibit 2 of this Change Order. |
5. | The Work in this Change Order may not support the CCL Stage 2 construction installation schedule; therefore, completion of the additional Work under this Change Order shall not be a condition precedent to Contractor achieving Substantial Completion and Final Completion of the CCL Stage 2 EPC Agreement. |
The original Contract Price was......................................................................................................................... | $ | 2,360,000,000 | |
Net change by previously authorized Change Orders (00001-00030)............................................................... | $ | 45,037,263 | |
The Contract Price prior to this Change Order was........................................................................................... | $ | 2,405,037,263 | |
The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... | $ | [***] | |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... | $ | [***] | |
The new Contract Price including this Change Order will be........................................................................... | $ | 2,405,701,083 |
The original Aggregate Equipment Price was................................................................................................... | $ | [***] |
Net change by previously authorized Change Orders (00001-00030)............................................................... | $ | [***] |
The Aggregate Equipment Price prior to this Change Order was...................................................................... | $ | [***] |
The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... | $ | [***] |
The new Aggregate Equipment Price including this Change Order will be ..................................................... | $ | [***] |
The original Aggregate Labor and Skills Price was.......................................................................................... | $ | [***] |
Net change by previously authorized Change Orders (00001-00030)............................................................... | $ | [***] |
The Aggregate Labor and Skills Price prior to this Change Order was............................................................. | $ | [***] |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... | $ | [***] |
The new Aggregate Labor and Skills Price including this Change Order will be............................................. | $ | [***] |
The original Aggregate Provisional Sum was.................................................................................................... | $ | 295,549,906 | |
Net change by previously authorized Change Orders (00001-00030)............................................................... | $ | (15,701,306 | ) |
The Aggregate Provisional Sum prior to this Change Order was...................................................................... | $ | 279,848,600 | |
The Aggregate Provisional Sum will be changed by this Change Order in the amount of............................... | $ | — | |
The new Aggregate Provisional Sum including this Change Order will be...................................................... | $ | 279,848,600 |
/s/ David Craft | /s/ Bhupesh Thakkar | |
Owner | Contractor | |
David Craft | Bhupesh Thakkar | |
Name | Name | |
SVP, E&C | Cheniere Program Manager | |
Title | Title | |
April 14, 2020 | April 3, 2020 | |
Date of Signing | Date of Signing |
PROJECT NAME: Corpus Christi Stage 2 Liquefaction Facility OWNER: Corpus Christi Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 12, 2017 | CHANGE ORDER NUMBER: 00032 DATE OF CHANGE ORDER: April 3, 2020 |
1. | Pursuant to Article 6.1 of the Agreement (Change Orders Requested by Owner), Parties agree this Change Order includes Contractor’s costs to procure and install ninety-six (96) new thermowells outside the cold boxes in Train 3 as requested by Owner. Exhibits 4 and 5 list the thermowells being replaced. This Change Order also includes the re-installment of the fifty-four (54) thermowells which were already installed in Train 3 at the time of the change request. |
2. | The summary cost breakdown for the total Scope of Work of this Change Order is detailed in Exhibit 1 of this Change Order. |
3. | The detailed cost breakdown for the Scope of Work of this Change Order is provided in Exhibit 3 of this Change Order. |
4. | Schedules C-1 and C-3 (Milestone Payment Schedules) of Attachment C of the Agreement will be amended by including the Milestones listed in Exhibit 2 of this Change Order. |
5. | The Design Basis in the Agreement is not changed by this Change Order. |
The original Contract Price was......................................................................................................................... | $ | 2,360,000,000 | |
Net change by previously authorized Change Orders (00001-00031)............................................................... | $ | 45,701,083 | |
The Contract Price prior to this Change Order was........................................................................................... | $ | 2,405,701,083 | |
The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... | $ | [***] | |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... | $ | [***] | |
The new Contract Price including this Change Order will be........................................................................... | $ | 2,405,900,647 |
The original Aggregate Equipment Price was................................................................................................... | $ | [***] |
Net change by previously authorized Change Orders (00001-00031)............................................................... | $ | [***] |
The Aggregate Equipment Price prior to this Change Order was...................................................................... | $ | [***] |
The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... | $ | [***] |
The new Aggregate Equipment Price including this Change Order will be ..................................................... | $ | [***] |
The original Aggregate Labor and Skills Price was.......................................................................................... | $ | [***] |
Net change by previously authorized Change Orders (00001-00031)............................................................... | $ | [***] |
The Aggregate Labor and Skills Price prior to this Change Order was............................................................. | $ | [***] |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... | $ | [***] |
The new Aggregate Labor and Skills Price including this Change Order will be............................................. | $ | [***] |
The original Aggregate Provisional Sum was.................................................................................................... | $ | 295,549,906 | |
Net change by previously authorized Change Orders (00001-00031)............................................................... | $ | (15,701,306 | ) |
The Aggregate Provisional Sum prior to this Change Order was...................................................................... | $ | 279,848,600 | |
The Aggregate Provisional Sum will be changed by this Change Order in the amount of............................... | $ | — | |
The new Aggregate Provisional Sum including this Change Order will be...................................................... | $ | 279,848,600 |
/s/ David Craft | /s/ Bhupesh Thakkar | |
Owner | Contractor | |
David Craft | Bhupesh Thakkar | |
Name | Name | |
SVP, Engineering and Construction | Cheniere Program Manager | |
Title | Title | |
April 15, 2020 | April 6, 2020 | |
Date of Signing | Date of Signing |
PROJECT NAME: Corpus Christi Stage 2 Liquefaction Facility OWNER: Corpus Christi Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 12, 2017 | CHANGE ORDER NUMBER: 00033 DATE OF CHANGE ORDER: April 28, 2020 |
1. | Pursuant to Article 6.1 of the Agreement (Change Orders Requested by Owner), Parties agree this Change Order includes Contractor’s home office costs incurred for development of the Tank B Rundown Line (Part 2) scope of work and trend, which was subsequently cancelled by Owner. |
2. | The summary cost breakdown of this Change Order is detailed in Exhibit 1 of this Change Order. |
3. | The detailed cost breakdown of this Change Order is provided in Exhibit 3 of this Change Order. |
4. | Schedules C-1 and C-3 (Milestone Payment Schedules) of Attachment C of the Agreement will be amended by including the Milestones listed in Exhibit 2 of this Change Order. |
5. | Additionally, Exhibit 4 of this Change Order supersedes the Exhibit 2 (Payment Milestones) of Change Order No. 00032 (Train 3 Thermowell Upgrades) to reflect the correct adjustments to the Aggregate Equipment Price (AEP) and Aggregate Labor and Skills Price (ALS). |
The original Contract Price was......................................................................................................................... | $ | 2,360,000,000 | |
Net change by previously authorized Change Orders (00001-00032)............................................................... | $ | 45,900,647 | |
The Contract Price prior to this Change Order was........................................................................................... | $ | 2,405,900,647 | |
The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... | $ | [***] | |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... | $ | [***] | |
The new Contract Price including this Change Order will be........................................................................... | $ | 2,405,976,692 |
The original Aggregate Equipment Price was................................................................................................... | $ | [***] |
Net change by previously authorized Change Orders (00001-00032)............................................................... | $ | [***] |
The Aggregate Equipment Price prior to this Change Order was...................................................................... | $ | [***] |
The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... | $ | [***] |
The new Aggregate Equipment Price including this Change Order will be ..................................................... | $ | [***] |
The original Aggregate Labor and Skills Price was.......................................................................................... | $ | [***] |
Net change by previously authorized Change Orders (00001-00032)............................................................... | $ | [***] |
The Aggregate Labor and Skills Price prior to this Change Order was............................................................. | $ | [***] |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... | $ | [***] |
The new Aggregate Labor and Skills Price including this Change Order will be............................................. | $ | [***] |
The original Aggregate Provisional Sum was.................................................................................................... | $ | 295,549,906 | |
Net change by previously authorized Change Orders (00001-00032)............................................................... | $ | (15,701,306 | ) |
The Aggregate Provisional Sum prior to this Change Order was...................................................................... | $ | 279,848,600 | |
The Aggregate Provisional Sum will be changed by this Change Order in the amount of............................... | $ | — | |
The new Aggregate Provisional Sum including this Change Order will be...................................................... | $ | 279,848,600 |
/s/ David Craft | /s/ Bhupesh Thakkar | |
Owner | Contractor | |
David Craft | Bhupesh Thakkar | |
Name | Name | |
Senior Vice President, Engineering and Construction | Cheniere Program Manager | |
Title | Title | |
May 12, 2020 | April 29, 2020 | |
Date of Signing | Date of Signing |
PROJECT NAME: Corpus Christi Stage 2 Liquefaction Facility OWNER: Corpus Christi Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 12, 2017 | CHANGE ORDER NUMBER: 00034 DATE OF CHANGE ORDER: May 21, 2020 |
1. | Pursuant to Article 6.1 of the Agreement (Change Orders Requested by Owner), Parties agree this Change Order includes Contractor’s engineering, procurement and construction costs to modify eleven (11) medium voltage (MV) motors to operate on uninterruptable power supply (UPS) as further described in Exhibit 4 of this Change Order. |
2. | The summary cost breakdown of this Change Order is detailed in Exhibit 1 of this Change Order. |
3. | The detailed cost breakdown of this Change Order is provided in Exhibit 3 of this Change Order. |
4. | Schedules C-1 and C-3 (Milestone Payment Schedules) of Attachment C of the Agreement will be amended by including the Milestones listed in Exhibit 2 of this Change Order. |
5. | The Design Basis in the Agreement is not changed by this Change Order. |
The original Contract Price was......................................................................................................................... | $ | 2,360,000,000 | |
Net change by previously authorized Change Orders (00001-00033)............................................................... | $ | 45,976,692 | |
The Contract Price prior to this Change Order was........................................................................................... | $ | 2,405,976,692 | |
The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... | $ | [***] | |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... | $ | [***] | |
The new Contract Price including this Change Order will be........................................................................... | $ | 2,406,284,073 |
The original Aggregate Equipment Price was................................................................................................... | $ | [***] |
Net change by previously authorized Change Orders (00001-00033)............................................................... | $ | [***] |
The Aggregate Equipment Price prior to this Change Order was...................................................................... | $ | [***] |
The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... | $ | [***] |
The new Aggregate Equipment Price including this Change Order will be ..................................................... | $ | [***] |
The original Aggregate Labor and Skills Price was.......................................................................................... | $ | [***] |
Net change by previously authorized Change Orders (00001-00033)............................................................... | $ | [***] |
The Aggregate Labor and Skills Price prior to this Change Order was............................................................. | $ | [***] |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... | $ | [***] |
The new Aggregate Labor and Skills Price including this Change Order will be............................................. | $ | [***] |
The original Aggregate Provisional Sum was.................................................................................................... | $ | 295,549,906 | |
Net change by previously authorized Change Orders (00001-00033)............................................................... | $ | (15,701,306 | ) |
The Aggregate Provisional Sum prior to this Change Order was...................................................................... | $ | 279,848,600 | |
The Aggregate Provisional Sum will be changed by this Change Order in the amount of............................... | $ | — | |
The new Aggregate Provisional Sum including this Change Order will be...................................................... | $ | 279,848,600 |
/s/ David Craft | /s/ Bhupesh Thakkar | |
Owner | Contractor | |
David Craft | Bhupesh Thakkar | |
Name | Name | |
SVP, Engineering & Construction | Cheniere Program Manager | |
Title | Title | |
June 3, 2020 | May 21, 2020 | |
Date of Signing | Date of Signing |