PROJECT NAME: Sabine Pass LNG Stage 4 Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: November 7, 2018 | CHANGE ORDER NUMBER: CO-00013 DATE OF CHANGE ORDER: February 10, 2020 |
1. | In accordance with Section 6.1 of the Agreement (Change Orders Requested by Owner), the Parties agree this Change Order reflects Contractor’s costs to comply with Owner’s Foreign-Trade-Zone No. 291 in Cameron, Louisiana (the “FTZ”) for the import of pipe spools from Turkey. |
2. | The Parties executed Change Order CO-00004 (Foreign Trade Zone), which defines responsibilities of Owner and Contractor with respect to FTZ compliance. |
3. | This Change Order is specific to Contractor’s costs incurred while Owner established the Project as FTZ and costs associated with changes in transportation and handling necessary to comply with FTZ requirements. This Change Order includes cost of actions taken by Contractor to avoid the application of tariffs, which otherwise would have occurred, while Owner was in the process of establishing its FTZ. Contractor’s costs include: |
i. | FTZ entries for pipe spools; |
ii. | Bonded transports of pipe spools; |
iii. | Receipt and storage for initial shipments of above-ground pipe spools (81 Containers) for Subproject 6(a) at Dixie Cullen FTZ Warehouse; |
4. | The detailed cost breakdown for this Change Order is detailed in Exhibit A of this Change Order. |
5. | Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit B of this Change Order. |
6. | This Change Order excludes (i) costs to comply with Owner’s Foreign-Trade-Zone No. 291 other than those for the import of pipe spools from Turkey and (ii) Subproject 6(b), LNG Berth 3. |
1. | The original Contract Price Applicable to Subproject 6(a) was................................................................. | $ | 2,016,892,573 | |
2. | Net change for Contract Price Applicable to Subproject 6(a) by previously authorized Change Orders (#00001-#00012)........................................................................................................................................ | $ | (19,084,262 | ) |
3. | The Contract Price Applicable to Subproject 6(a) prior to this Change Order was................................... | $ | 1,997,808,311 | |
4. | The Contract Price Applicable to Subproject 6(a) will be increased by this Change Order in the amount of.................................................................................................................................................... | $ | 551,068 | |
5. | The Provisional Sum Applicable to Subproject 6(a) will be unchanged by this Change Order in the amount of.................................................................................................................................................... | $ | — | |
6. | The new Contract Price Applicable to Subproject 6(a) including this Change Order will be................... | $ | 1,998,359,379 |
7. | The original Contract Price Applicable to Subproject 6(b) was................................................................ | $ | — | |
8. | Net change for Contract Price Applicable to Subproject 6(b) by previously authorized Change Orders (#00001-#00012)........................................................................................................................................ | $ | 457,696,000 | |
9. | The Contract Price Applicable to Subproject 6(b) prior to this Change Order was.................................. | $ | 457,696,000 | |
10. | The Contract Price Applicable to Subproject 6(b) will be unchanged by this Change Order................... | $ | — | |
11. | The Provisional Sum Applicable to Subproject 6(b) will be unchanged by this Change Order................ | $ | — | |
12. | The new Contract Price Applicable to Subproject 6(b) including this Change Order will be................... | $ | 457,696,000 |
13. | The original Contract Price was (add lines 1 and 7)................................................................................. | $ | 2,016,892,573 | |
14. | The Contract Price prior to this Change Order was (add lines 3 and 9).................................................... | $ | 2,455,504,311 | |
15. | The Contract Price will be increased by this Change Order in the amount of (add lines 4 and 10)......... | $ | 551,068 | |
16. | The new Contract Price including this Change Order will be (add lines 14 and 15)................................ | $ | 2,456,055,379 |
/s/ David Craft | /s/ Maurissa D. Rogers | |
Owner | Contractor | |
David Craft | Maurissa D. Rogers | |
Name | Name | |
Sr VP E&C | Sr Project Manager, PVP | |
Title | Title | |
February 26, 2020 | February 10, 2020 | |
Date of Signing | Date of Signing |
PROJECT NAME: Sabine Pass LNG Stage 4 Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: November 7, 2018 | CHANGE ORDER NUMBER: CO-00014 DATE OF CHANGE ORDER: February 10, 2020 |
1. | In accordance with Section 6.1 of the Agreement (Change Orders Requested by Owner), the Parties agree this change order reflects Contractor’s cost to install a permanent access road to the Third Berth (Subproject 6(b)) as requested by Owner on November 11, 2019 via Letter No. SPL4-BE-C19-044. |
2. | This additional access way will allow access to the Third Berth construction area without moving the existing guard shack or adding an additional guard shack off of Lighthouse Road. Refer to the attached drawing depicting the new Third Berth access road as provided in Exhibit C of this Change Order. |
3. | The detailed cost breakdown for this Change Order is detailed in Exhibit A of this Change Order. |
4. | Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit B of this Change Order. |
1. | The original Contract Price Applicable to Subproject 6(a) was................................................................. | $ | 2,016,892,573 | |
2. | Net change for Contract Price Applicable to Subproject 6(a) by previously authorized Change Orders (#00001-#00013)........................................................................................................................................ | $ | (18,533,194 | ) |
3. | The Contract Price Applicable to Subproject 6(a) prior to this Change Order was................................... | $ | 1,998,359,379 | |
4. | The Contract Price Applicable to Subproject 6(a) will be increased by this Change Order in the amount of.................................................................................................................................................... | $ | — | |
5. | The Provisional Sum Applicable to Subproject 6(a) will be unchanged by this Change Order in the amount of.................................................................................................................................................... | $ | — | |
6. | The new Contract Price Applicable to Subproject 6(a) including this Change Order will be................... | $ | 1,998,359,379 |
7. | The original Contract Price Applicable to Subproject 6(b) was................................................................ | $ | — | |
8. | Net change for Contract Price Applicable to Subproject 6(b) by previously authorized Change Orders (#00001-#00013)........................................................................................................................................ | $ | 457,696,000 | |
9. | The Contract Price Applicable to Subproject 6(b) prior to this Change Order was.................................. | $ | 457,696,000 | |
10. | The Contract Price Applicable to Subproject 6(b) will be unchanged by this Change Order................... | $ | 393,929 | |
11. | The Provisional Sum Applicable to Subproject 6(b) will be unchanged by this Change Order................ | $ | — | |
12. | The new Contract Price Applicable to Subproject 6(b) including this Change Order will be................... | $ | 458,089,929 |
13. | The original Contract Price was (add lines 1 and 7)................................................................................. | $ | 2,016,892,573 | |
14. | The Contract Price prior to this Change Order was (add lines 3 and 9).................................................... | $ | 2,456,055,379 | |
15. | The Contract Price will be increased by this Change Order in the amount of (add lines 4 and 10)......... | $ | 393,929 | |
16. | The new Contract Price including this Change Order will be (add lines 14 and 15)................................ | $ | 2,456,449,308 |
/s/ David Craft | /s/ Maurissa D. Rogers | |
Owner | Contractor | |
David Craft | Maurissa D. Rogers | |
Name | Name | |
SVP E&C | Sr Project Manager, PVP | |
Title | Title | |
February 19, 2020 | February 10, 2020 | |
Date of Signing | Date of Signing |
PROJECT NAME: Sabine Pass LNG Stage 4 Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: November 7, 2018 | CHANGE ORDER NUMBER: CO-00015 DATE OF CHANGE ORDER: February 10, 2020 |
1. | The Parties agree to amend Article 13.2A of the Agreement to replace the reference to “NTP” to “LNTP No. 1” to calculate the “Schedule Bonus Date for SP6(a)”. |
2. | Now therefore, Section 13.2A of the Agreement is deleted and replaced with the following: |
13.2 | Schedule Bonus. |
3. | The Contract Price is not adjusted by this Change Order. |
1. | The original Contract Price Applicable to Subproject 6(a) was................................................................. | $ | 2,016,892,573 | |
2. | Net change for Contract Price Applicable to Subproject 6(a) by previously authorized Change Orders (#00001-#00014)........................................................................................................................................ | $ | (18,533,194 | ) |
3. | The Contract Price Applicable to Subproject 6(a) prior to this Change Order was................................... | $ | 1,998,359,379 | |
4. | The Contract Price Applicable to Subproject 6(a) will be increased by this Change Order in the amount of.................................................................................................................................................... | $ | — | |
5. | The Provisional Sum Applicable to Subproject 6(a) will be unchanged by this Change Order in the amount of.................................................................................................................................................... | $ | — | |
6. | The new Contract Price Applicable to Subproject 6(a) including this Change Order will be................... | $ | 1,998,359,379 |
7. | The original Contract Price Applicable to Subproject 6(b) was................................................................ | $ | — | |
8. | Net change for Contract Price Applicable to Subproject 6(b) by previously authorized Change Orders (#00001-#00014)........................................................................................................................................ | $ | 458,089,929 | |
9. | The Contract Price Applicable to Subproject 6(b) prior to this Change Order was.................................. | $ | 458,089,929 | |
10. | The Contract Price Applicable to Subproject 6(b) will be unchanged by this Change Order................... | $ | — | |
11. | The Provisional Sum Applicable to Subproject 6(b) will be unchanged by this Change Order................ | $ | — | |
12. | The new Contract Price Applicable to Subproject 6(b) including this Change Order will be................... | $ | 458,089,929 |
13. | The original Contract Price was (add lines 1 and 7)................................................................................. | $ | 2,016,892,573 | |
14. | The Contract Price prior to this Change Order was (add lines 3 and 9).................................................... | $ | 2,456,449,308 | |
15. | The Contract Price will be increased by this Change Order in the amount of (add lines 4 and 10)......... | $ | — | |
16. | The new Contract Price including this Change Order will be (add lines 14 and 15)................................ | $ | 2,456,449,308 |
/s/ David Craft | /s/ Maurissa D. Rogers | |
Owner | Contractor | |
David Craft | Maurissa D. Rogers | |
Name | Name | |
SVP E&C | Sr Project Manager, PVP | |
Title | Title | |
February 19, 2020 | February 10, 2020 | |
Date of Signing | Date of Signing |
PROJECT NAME: Sabine Pass LNG Stage 4 Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: November 7, 2018 | CHANGE ORDER NUMBER: CO-00016 DATE OF CHANGE ORDER: January 31, 2020 |
1. | In accordance with Article 5.1.A.4 (“Other Limited Notices to Proceed”) and Article 5.2.B (“NTP for Subproject 6(b)”), the Parties agree to amend the Agreement by way of adding a new Limited Notice to Proceed No. 3 for Subproject 6(b) in the form attached hereto as Schedule H-8 (“LNTP No. 3”), authorizing Contractor to commence performance of the Work as described in Schedule H-8. |
2. | Work performed under LNTP No. 3 shall be performed in accordance with the terms and conditions of the Agreement and Contractor shall be paid for such specified Work pursuant to the terms and conditions of LNTP No. 3 and the Agreement, with all such payments credited against the Contract Price if NTP for Subproject 6(b) is issued. The Portion of the Contract Price payable for Work under LNTP No. 3 shall be made in accordance with the Payment Schedule set forth in Schedule H-8 (as may be amended by Change Order) and the applicable provisions of Article 7. |
3. | This Change Order excludes any potential cost and schedule impacts pursuant to the instructions in Article 5.2.C.2 (“Subproject 6(b)”). |
4. | The Contract Price is not adjusted by this Change Order. |
1. | The original Contract Price Applicable to Subproject 6(a) was................................................................. | $ | 2,016,892,573 | |
2. | Net change for Contract Price Applicable to Subproject 6(a) by previously authorized Change Orders (#00001-#00015)........................................................................................................................................ | $ | (18,533,194 | ) |
3. | The Contract Price Applicable to Subproject 6(a) prior to this Change Order was................................... | $ | 1,998,359,379 | |
4. | The Contract Price Applicable to Subproject 6(a) will be increased by this Change Order in the amount of.................................................................................................................................................... | $ | — | |
5. | The Provisional Sum Applicable to Subproject 6(a) will be unchanged by this Change Order in the amount of.................................................................................................................................................... | $ | — | |
6. | The new Contract Price Applicable to Subproject 6(a) including this Change Order will be................... | $ | 1,998,359,379 |
7. | The original Contract Price Applicable to Subproject 6(b) was................................................................ | $ | — | |
8. | Net change for Contract Price Applicable to Subproject 6(b) by previously authorized Change Orders (#00001-#00015)........................................................................................................................................ | $ | 458,089,929 | |
9. | The Contract Price Applicable to Subproject 6(b) prior to this Change Order was.................................. | $ | 458,089,929 | |
10. | The Contract Price Applicable to Subproject 6(b) will be unchanged by this Change Order................... | $ | — | |
11. | The Provisional Sum Applicable to Subproject 6(b) will be unchanged by this Change Order................ | $ | — | |
12. | The new Contract Price Applicable to Subproject 6(b) including this Change Order will be................... | $ | 458,089,929 |
13. | The original Contract Price was (add lines 1 and 7)................................................................................. | $ | 2,016,892,573 | |
14. | The Contract Price prior to this Change Order was (add lines 3 and 9).................................................... | $ | 2,456,449,308 | |
15. | The Contract Price will be increased by this Change Order in the amount of (add lines 4 and 10)......... | $ | — | |
16. | The new Contract Price including this Change Order will be (add lines 14 and 15)................................ | $ | 2,456,449,308 |
/s/ David Craft | /s/ Maurissa D. Rogers | |
Owner | Contractor | |
David Craft | Maurissa D. Rogers | |
Name | Name | |
SVP E&C | Sr Project Manager, PVP | |
Title | Title | |
January 31, 2020 | January 31, 2020 | |
Date of Signing | Date of Signing |
PROJECT NAME: Sabine Pass LNG Stage 4 Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: November 7, 2018 | CHANGE ORDER NUMBER: CO-00017 DATE OF CHANGE ORDER: March 18, 2020 |
1. | In accordance with Section 6.1 of the Agreement (Change Orders Requested by Owner), the Parties agree this change order reflects Contractor’s cost to install a total of eight (8) pneumatic fender guards and ancillary material at the SPL Construction Dock as requested by Owner via Letter No. SPL4-BE-C20-003. |
2. | In accordance with Section 6.1 of the Agreement (Change Orders Requested by Owner), the Parties agree this change order reflects Contractor’s cost to add an interlock control system to close 46XV-22047 on high pressure to the LP Fuel Gas Knock Out Drum 46V-2202 as requested by Owner via Letter No. SPL4-BE-C20-002. |
3. | The detailed cost breakdown for this Change Order is detailed in Exhibits A1 and A2 of this Change Order. |
4. | Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit B of this Change Order. |
1. | The original Contract Price Applicable to Subproject 6(a) was................................................................. | $ | 2,016,892,573 | |
2. | Net change for Contract Price Applicable to Subproject 6(a) by previously authorized Change Orders (#00001-#00016)........................................................................................................................................ | $ | (18,533,194 | ) |
3. | The Contract Price Applicable to Subproject 6(a) prior to this Change Order was................................... | $ | 1,998,359,379 | |
4. | The Contract Price Applicable to Subproject 6(a) will be increased by this Change Order in the amount of.................................................................................................................................................... | $ | 163,174 | |
5. | The Provisional Sum Applicable to Subproject 6(a) will be unchanged by this Change Order in the amount of.................................................................................................................................................... | $ | — | |
6. | The new Contract Price Applicable to Subproject 6(a) including this Change Order will be................... | $ | 1,998,522,553 |
7. | The original Contract Price Applicable to Subproject 6(b) was................................................................ | $ | — | |
8. | Net change for Contract Price Applicable to Subproject 6(b) by previously authorized Change Orders (#00001-#00016)........................................................................................................................................ | $ | 458,089,929 | |
9. | The Contract Price Applicable to Subproject 6(b) prior to this Change Order was.................................. | $ | 458,089,929 | |
10. | The Contract Price Applicable to Subproject 6(b) will be unchanged by this Change Order................... | $ | — | |
11. | The Provisional Sum Applicable to Subproject 6(b) will be unchanged by this Change Order................ | $ | — | |
12. | The new Contract Price Applicable to Subproject 6(b) including this Change Order will be................... | $ | 458,089,929 |
13. | The original Contract Price was (add lines 1 and 7)................................................................................. | $ | 2,016,892,573 | |
14. | The Contract Price prior to this Change Order was (add lines 3 and 9).................................................... | $ | 2,456,449,308 | |
15. | The Contract Price will be increased by this Change Order in the amount of (add lines 4 and 10)......... | $ | 163,174 | |
16. | The new Contract Price including this Change Order will be (add lines 14 and 15)................................ | $ | 2,456,612,482 |
/s/ David Craft | /s/ Maurissa D. Rogers | |
Owner | Contractor | |
David Craft | Maurissa D. Rogers | |
Name | Name | |
SVP E&C | Sr Project Manager, PVP | |
Title | Title | |
March 26, 2020 | March 18, 2020 | |
Date of Signing | Date of Signing |