Exhibit 10.8
[***] indicates certain identified information has been excluded because it is both (a) not material and (b) would be competitively harmful if publicly disclosed.
CHANGE ORDER
Train 2 Nitrogen Supply for Commissioning Units 16, 17 and Feed Gas
PROJECT NAME:  Corpus Christi Stage 1 Liquefaction Facility

OWNER: Corpus Christi Liquefaction, LLC

CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc.

DATE OF AGREEMENT: December 6, 2013
CHANGE ORDER NUMBER: CO-00053

DATE OF CHANGE ORDER: June 26, 2019


The Agreement between the Parties listed above is changed as follows:

1)
Pursuant to Article 6 of the Agreement, Parties agree this Change Order includes Contractor’s use of nitrogen for Subproject 2 (Train 2) Commissioning activities (dryout and defrosting of Units 16, 17 and Feed Gas) in lieu of Feed Gas as requested by Owner.

i.
This Change Order is in accordance with the approved Trend No. S1-3017.

2)
The summary cost breakdown for the scope of this Change Order is detailed in Exhibit 1 of this Change Order.

3)
The detailed cost breakdown for the scope of this Change Order is detailed in Exhibit 3 (Trend No. S1-3017) and Exhibit 4 (Supplier Invoice).

4)
Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the Milestone(s) listed in Exhibit 2 of this Change Order.


Adjustment to Contract Price
The original Contract Price was.........................................................................................................................
$
7,080,830,000

Net change by previously authorized Change Orders (0001-00052).................................................................
$
706,243,783

The Contract Price prior to this Change Order was...........................................................................................
$
7,787,073,783

The Aggregate Equipment Price will be changed by this Change Order in the amount of...............................
$
[***]

The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of......................
$
[***]

The new Contract Price including this Change Order will be...........................................................................
$
7,789,250,599


Adjustment to Aggregate Equipment Price
The original Aggregate Equipment Price was...................................................................................................
$
[***]
Net change by previously authorized Change Orders (0001-00052).................................................................
$
[***]
The Aggregate Equipment Price prior to this Change Order was......................................................................
$
[***]
The Aggregate Equipment Price will be changed by this Change Order in the amount of...............................
$
[***]
The new Aggregate Equipment Price including this Change Order will be .....................................................
$
[***]






Adjustment to Aggregate Labor and Skills Price
The original Aggregate Labor and Skills Price was..........................................................................................
$
[***]
Net change by previously authorized Change Orders (0001-00052).................................................................
$
[***]
The Aggregate Labor and Skills Price prior to this Change Order was.............................................................
$
[***]
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of......................
$
[***]
The new Aggregate Labor and Skills Price including this Change Order will be.............................................
$
[***]

Adjustment to Aggregate Provisional Sum
The original Aggregate Provisional Sum was....................................................................................................
$
950,561,351

Net change by previously authorized Change Orders (0001-00052).................................................................
$
(812,283,979
)
The Aggregate Provisional Sum prior to this Change Order was......................................................................
$
138,277,372

The Aggregate Provisional Sum will be changed by this Change Order in the amount of...............................
$

The new Aggregate Provisional Sum including this Change Order will be......................................................
$
138,277,372


Adjustment to dates in Project Schedule
The following dates are modified (list all dates modified; insert N/A if no dates modified): N/A

Adjustment to other Changed Criteria (insert N/A if no changes or impact; attach additional documentation if necessary): N/A

Adjustment to Payment Schedule: Yes. See Exhibit 2 of this Change Order.

Adjustment to Minimum Acceptance Criteria: N/A

Adjustment to Performance Guarantees: N/A

Adjustment to Design Basis: N/A

Other adjustments to liability or obligation of Contractor or Owner under the Agreement:     N/A

Select either A or B:

[A] This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials:  /s/ BT Contractor /s/ DC Owner

[B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: ____ Contractor ____ Owner

Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.






/s/ David Craft
 
/s/ Bhupesh Thakkar
For Owner
 
For Contractor
David Craft
 
Bhupesh Thakkar
Name
 
Name
SVP, Engineering & Construction
 
SVP, Cheniere Program
Title
 
Title
July 15, 2019
 
June 27, 2019
Date of Signing
 
Date of Signing