PROJECT NAME: Corpus Christi Stage 1 Liquefaction Facility OWNER: Corpus Christi Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 6, 2013 | CHANGE ORDER NUMBER: CO-00042 DATE OF CHANGE ORDER: April 30, 2018 |
• | Component 00A-4000 Warehouse 1 - a portion of System 040-22 - “MISC STORAGE BUILDINGS” (“Warehouse 1”) |
• | Component 00A-4052 Laboratory - a portion of System 040-01, “O&M AND CONTROL ROOM BUILDING 00A-4024 AND LABORATORY 00A-4052” (the “Lab”, together with Warehouse 1, the “Buildings”) |
1) | “Phase 1” means the time period beginning upon execution of this Change Order and ending: (i) with respect to the Lab, when Contractor obtains a certificate of occupancy or other applicable authorization for the Lab from the appropriate Governmental Instrumentality for the occupancy of the Lab (a “Certificate of Occupancy”); and (ii) with respect to Warehouse 1, when Contractor obtains a Certificate of Occupancy for Warehouse 1. |
2) | “Phase 2” means the time period following the end of Phase 1 and ending on the date of Substantial Completion of Subproject 1. |
a) | Contractor shall complete fit out of the Buildings in accordance with the Agreement (including the Specifications) so that the Buildings are ready for full occupancy and shall obtain a Certificate of Occupancy for each of the Buildings according to the Project Schedule. Prior to Phase 2, Contractor shall have full and unrestricted access in and to the Buildings as is necessary to perform the Work inside, outside and adjacent to the Buildings as described in Exhibit B to this Change Order. |
b) | Owner may perform only construction and fit-out activities within the Buildings. To assist Owner with the modifications to the Buildings, Contractor hereby delivers to Owner the Buildings packages attached hereto as Exhibit A. |
c) | Contractor shall deliver to Owner the keys to the Buildings and Owner shall maintain access control and security inside the Buildings. Contractor will install a barricade around the Buildings with access points for Owner and its subcontractors to enter the Buildings. Subject to Clause 3.a above, Contractor shall not occupy or operate the Buildings. |
d) | Owner shall follow Contractor’s work authorization and lockout/tagout processes and comply with the applicable operations and maintenance manuals for the mechanical systems in the Buildings. |
e) | Owner shall obtain Contractor’s approval for modifications that require tie-ins to the utilities. |
f) | For purposes of this Change Order, Owner shall cause its subcontractors performing the Owner activities described herein to stay within the designated area around the Buildings and use La Quinta Road for access to the Site and Buildings. |
g) | Contractor shall continue to perform preventive maintenance on the Buildings and their systems according to the operating and maintenance manuals. Immediately prior to Phase 2, Owner and Contractor shall jointly inspect the |
(a) | Owner shall have the right to occupy and use the Buildings, locate operators in the Buildings and use and store parts in Warehouse 1. |
(b) | Owner shall designate one (1) individual as Contractor’s point of contact for Warehouse 1 for purposes of administering a commissioning parts usage and replacement program for those parts owned by Owner and stored in Warehouse 1. Such program shall be in writing and approved by Owner. The designated individual shall be onsite and readily available. |
(c) | Owner shall perform work in the Buildings under Owner’s work processes and not Contractor’s work authorization or lockout/tagout processes. |
(d) | Contractor shall continue to provide utilities (temporary and permanent) to the Buildings. |
(e) | Owner will transport its personnel to the Buildings. |
(f) | Owner will perform preventive maintenance on the Buildings. |
(g) | Owner shall have risk of loss of any of Owner’s parts stored in Warehouse 1. |
5) | Other than for the Work described in Exhibit B, the Defect Correction Period for each Building shall commence upon the commencement of Phase 1. The Defect Correction Period for all Work set forth in Exhibit B to this Change Order shall commence upon the commencement of Phase 2. |
6) | Contractor’s builder’s risk insurance shall continue to cover the Buildings until the end of Phase 1; provided, however, that Owner shall be responsible for the per occurrence deductible under Contractor’s builder’s risk policy to the extent damage to the Buildings is caused by Owner Group’s fault during Phase 1. |
7) | Owner shall manage Environmental, Safety & Health incidents involving Owner’s work within the Buildings, with Contractor’s reasonable assistance as needed on a cost reimbursable basis. |
The original Contract Price was......................................................................................................................... | $ | 7,080,830,000 | |
Net change by previously authorized Change Orders (0001-00041)................................................................. | $ | 695,002,402 | |
The Contract Price prior to this Change Order was........................................................................................... | $ | 7,775,832,402 | |
The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... | $ | *** | |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... | $ | *** | |
The new Contract Price including this Change Order will be........................................................................... | $ | 7,775,832,402 |
The original Aggregate Equipment Price was................................................................................................... | $ | *** |
Net change by previously authorized Change Orders (0001-00041)................................................................. | $ | *** |
The Aggregate Equipment Price prior to this Change Order was...................................................................... | $ | *** |
The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... | $ | *** |
The new Aggregate Equipment Price including this Change Order will be ..................................................... | $ | *** |
The original Aggregate Labor and Skills Price was.......................................................................................... | $ | *** |
Net change by previously authorized Change Orders (0001-00041)................................................................. | $ | *** |
The Aggregate Labor and Skills Price prior to this Change Order was............................................................. | $ | *** |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... | $ | *** |
The new Contract Price including this Change Order will be........................................................................... | $ | *** |
The original Aggregate Provisional Sum was.................................................................................................... | $ | 950,561,351 | |
Net change by previously authorized Change Orders (0001-00041)................................................................. | $ | (812,283,979 | ) |
The Aggregate Provisional Sum prior to this Change Order was...................................................................... | $ | 138,277,372 | |
The Aggregate Provisional Sum will be unchanged by this Change Order in the amount of........................... | $ | — | |
The new Aggregate Provisional Sum including this Change Order will be...................................................... | $ | 138,277,372 |
/s/ Ed Lehotsky | /s/ Sergio Buoncristiano | |
Owner | Contractor | |
Ed Lehotsky | Sergio Buoncristiano | |
Name | Name | |
SVP E&C | SVP | |
Title | Title | |
May 3, 2018 | April 30, 2018 | |
Date of Signing | Date of Signing |
PROJECT NAME: Corpus Christi Stage 1 Liquefaction Facility OWNER: Corpus Christi Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 6, 2013 | CHANGE ORDER NUMBER: CO-00043 DATE OF CHANGE ORDER: May 18, 2018 |
1. | Per Section 6.8 of the Agreement, the Parties agree that Contractor is entitled to an adjustment to the Contract Price for the Force Majeure impacts of Hurricane Harvey for the Stage 1 Liquefaction Facility. Section 6.8.A.2 provides that Contractor is entitled to an adjustment of the Contract Price for any delay or prevention that meets the requirements of Section 6.8A of the Agreement, if such delay or prevention, alone or in conjunction with other Force Majeure Events, continues for a period of at least thirty (30) Days, in the aggregate. The Parties agree that the Force Majeure impacts of Hurricane Harvey prevented or delayed the Work for a period of thirty-eight (38) Days and that Contractor is entitled to compensation for the reasonable costs necessarily incurred by Contractor during the eight (8) Days after the expiration of the thirty (30) Day period. The Parties agree that Owner will compensate Contractor in the amount of Nine Million Two Hundred Thousand U.S. Dollars (U.S. $9,200,000) for such costs (the “Hurricane Harvey Force Majeure Compensation”). The Hurricane Harvey Force Majeure Compensation shall reduce the Owner’s total liability set forth in Section 6.8.A.2.c of the Agreement from Fifty Million U.S. Dollars (U.S. $50,000,000) to Forty Million Eight Hundred Thousand U.S. Dollars (U.S. $40,800,000). |
2. | Owner shall pay Contractor the Hurricane Harvey Force Majeure Compensation according to the payment terms of the Agreement upon receipt of Contractor’s invoice for the month of July 2018. Contractor shall include a line item in such invoice identifying the Hurricane Harvey Force Majeure Compensation. |
3. | The Parties hereby amend the Agreement by adding as a new Article 13.3 as follows: |
E. | The total of all above Special Schedule Rewards shall not exceed Thirty Million U.S. Dollars (U.S. $30,000,000). |
4. | Contractor waives any entitlement to or claims for an adjustment to Target Substantial Completion Dates and Guaranteed Substantial Completion Dates for the impacts of Hurricane Harvey. |
5. | Both Parties agree that the intent of the phrase in Sections 13.2.A(ii) and 13.2.B(ii) of the Agreement “sold by Owner to one of its customers” means with respect to the sale of LNG “loaded onto an LNG Tanker for export to one of Owner’s customers.” With respect to the Schedule Bonus for SP2, the Parties further agree that the LNG produced by Subproject 2 after the Schedule Bonus Date for SP1 (as defined in Section 13.2A) is not eligible for any Schedule Bonus. |
The original Contract Price was......................................................................................................................... | $ | 7,080,830,000 | |
Net change by previously authorized Change Orders (0001-00042)................................................................. | $ | 695,002,402 | |
The Contract Price prior to this Change Order was........................................................................................... | $ | 7,775,832,402 | |
The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... | $ | *** | |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... | $ | *** | |
The new Contract Price including this Change Order will be........................................................................... | $ | 7,785,032,402 |
The original Aggregate Equipment Price was................................................................................................... | $ | *** |
Net change by previously authorized Change Orders (0001-00042)................................................................. | $ | *** |
The Aggregate Equipment Price prior to this Change Order was...................................................................... | $ | *** |
The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... | $ | *** |
The new Aggregate Equipment Price including this Change Order will be ..................................................... | $ | *** |
The original Aggregate Labor and Skills Price was.......................................................................................... | $ | *** |
Net change by previously authorized Change Orders (0001-00042)................................................................. | $ | *** |
The Aggregate Labor and Skills Price prior to this Change Order was............................................................. | $ | *** |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... | $ | *** |
The new Contract Price including this Change Order will be........................................................................... | $ | *** |
The original Aggregate Provisional Sum was.................................................................................................... | $ | 950,561,351 | |
Net change by previously authorized Change Orders (0001-00042)................................................................. | $ | (812,283,979 | ) |
The Aggregate Provisional Sum prior to this Change Order was...................................................................... | $ | 138,277,372 | |
The Aggregate Provisional Sum will be unchanged by this Change Order in the amount of........................... | $ | — | |
The new Aggregate Provisional Sum including this Change Order will be...................................................... | $ | 138,277,372 |
/s/ Ed Lehotsky | /s/ Sergio Buoncristiano | |
Owner | Contractor | |
Ed Lehotsky | Sergio Buoncristiano | |
Name | Name | |
SVP E&C | SVP | |
Title | Title | |
June 5, 2018 | May 18, 2018 | |
Date of Signing | Date of Signing |
PROJECT NAME: Corpus Christi Stage 1 Liquefaction Facility OWNER: Corpus Christi Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 6, 2013 | CHANGE ORDER NUMBER: CO-00044 DATE OF CHANGE ORDER: June 6, 2018 |
1) | Per Articles 6.1 and 6.2 of the Agreement, Parties agree Contractor will implement changes to incorporate condensate takeaway modifications and revisions for tell-tale signs for leak detection and repair for Subprojects 1 and 2. |
2) | Parties agree Contractor will reduce the contract price to return to Owner the agreed settlement value for Contractor’s Craft Incentive Due to Hurricane Harvey that was negotiated in CO-00038, Exhibit A, Scope of Work, Item 16. Contractor has negotiated a reimbursement from our insurer for this amount. |
3) | The scope of this Change Order is further detailed in Exhibit A. |
4) | The cost breakdowns for the scope of work noted above in this Change Order are detailed in Exhibit B. These costs are as detailed in Trend S1-2061 and Trend S1-2064. |
5) | Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the Milestone(s) listed in Exhibit C-1 of this Change Order. In addition to the adjustments associated with the above changes, four (4) milestone payment descriptions (milestone numbers ALS 43.3, ALS 43.4c12, ALS 52.2, and ALS 52.3c12) are adjusted as shown in Exhibit C-2 of this Change Order. These milestones payment description adjustments do not modify the overall total amounts of Attachment C of the Agreement. |
The original Contract Price was......................................................................................................................... | $ | 7,080,830,000 | |
Net change by previously authorized Change Orders (0001-00043)................................................................. | $ | 704,202,402 | |
The Contract Price prior to this Change Order was........................................................................................... | $ | 7,785,032,402 | |
The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... | $ | *** | |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... | $ | *** | |
The new Contract Price including this Change Order will be........................................................................... | $ | 7,784,388,100 |
The original Aggregate Equipment Price was................................................................................................... | $ | *** |
Net change by previously authorized Change Orders (0001-00043)................................................................. | $ | *** |
The Aggregate Equipment Price prior to this Change Order was...................................................................... | $ | *** |
The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... | $ | *** |
The new Aggregate Equipment Price including this Change Order will be ..................................................... | $ | *** |
The original Aggregate Labor and Skills Price was.......................................................................................... | $ | *** |
Net change by previously authorized Change Orders (0001-00043)................................................................. | $ | *** |
The Aggregate Labor and Skills Price prior to this Change Order was............................................................. | $ | *** |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... | $ | *** |
The new Contract Price including this Change Order will be........................................................................... | $ | *** |
The original Aggregate Provisional Sum was.................................................................................................... | $ | 950,561,351 | |
Net change by previously authorized Change Orders (0001-00043)................................................................. | $ | (812,283,979 | ) |
The Aggregate Provisional Sum prior to this Change Order was...................................................................... | $ | 138,277,372 | |
The Aggregate Provisional Sum will be unchanged by this Change Order in the amount of........................... | $ | — | |
The new Aggregate Provisional Sum including this Change Order will be...................................................... | $ | 138,277,372 |
/s/ Ed Lehotsky | /s/ Bhupesh Thakkar | |
For Owner | For Contractor | |
Ed Lehotsky | Bhupesh Thakkar | |
Name | Name | |
SVP E&C | Senior Project Manager | |
Title | Title | |
July 2, 2018 | June 29, 2018 | |
Date of Signing | Date of Signing |
PROJECT NAME: Corpus Christi Stage 1 Liquefaction Facility OWNER: Corpus Christi Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 6, 2013 | CHANGE ORDER NUMBER: CO-00045 DATE OF CHANGE ORDER: June 6, 2018 |
• | Component 00A-4053 Security Operations Building- a portion of System 040-27 “Miscellaneous Security Buildings” |
1) | “Phase 1” means the time period beginning upon the date this Change Order is executed and prior to the date the Building is turned over to Owner. |
2) | “Phase 2” means the time period beginning the date the Building is turned over to Owner and ending on the date of Substantial Completion of Subproject 1. |
3) | During Phase 1: |
a) | Contractor shall complete the Building in accordance with the Agreement (including the Specifications) so that the Building is ready for full occupancy and shall obtain a Certificate of Occupancy for each of the Building according to the Project Schedule. |
b) | Contractor shall continue to perform preventive maintenance on the Building and their systems according to the operating and maintenance manuals. |
c) | On or before July 6, 2018, Owner and Contractor shall jointly inspect the Remaining Work (as set forth in Exhibit B) to determine and record the condition of the Remaining Work. The Parties shall agree on a punchlist of items identified as needing to be completed or corrected as a result of such inspection. |
d) | On or before July 6, 2018, Contractor shall deliver to Owner the keys to the Building and Owner shall maintain access control and security inside the Building. Contractor will install a barricade around the Building with access points for Owner and its subcontractors to enter the Building. |
4) | During Phase 2: |
e) | Owner shall have the right to occupy and use the Building, locate personnel in the Building and use and store materials as required. |
f) | Owner shall provide Contractor with reasonable access to complete all punchlist items so long as such access does not unreasonably interfere with Owner’s use of the Building. |
g) | Contractor shall continue to provide utilities (temporary and permanent) to the Building. |
h) | Owner will transport its personnel to the Building. |
i) | Owner will perform preventive maintenance on the Building. |
j) | Owner shall have risk of loss of any of material stored in the Building. |
5) | The Defect Correction Period for the Building shall commence upon the commencement of Phase 2. |
6) | Owner’s operational insurance shall cover the Building upon commencement of Phase 2. |
7) | Owner shall manage Environmental, Safety & Health incidents involving Owner’s work within the Building, with Contractor’s reasonable assistance as needed on a cost reimbursable basis. |
8) | If Owner Group’s use of the Building adversely impacts Contractor’s Work, Contractor will be entitled to a Change Order adjusting the Project Schedule in accordance with Sections 6.2A or 8.2C of the Agreement. |
The original Contract Price was......................................................................................................................... | $ | 7,080,830,000 | |
Net change by previously authorized Change Orders (0001-00044)................................................................. | $ | 703,558,100 | |
The Contract Price prior to this Change Order was........................................................................................... | $ | 7,784,388,100 | |
The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... | $ | *** | |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... | $ | *** | |
The new Contract Price including this Change Order will be........................................................................... | $ | 7,784,388,100 |
The original Aggregate Equipment Price was................................................................................................... | $ | *** |
Net change by previously authorized Change Orders (0001-00044)................................................................. | $ | *** |
The Aggregate Equipment Price prior to this Change Order was...................................................................... | $ | *** |
The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... | $ | *** |
The new Aggregate Equipment Price including this Change Order will be ..................................................... | $ | *** |
The original Aggregate Labor and Skills Price was.......................................................................................... | $ | *** |
Net change by previously authorized Change Orders (0001-00044)................................................................. | $ | *** |
The Aggregate Labor and Skills Price prior to this Change Order was............................................................. | $ | *** |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... | $ | *** |
The new Contract Price including this Change Order will be........................................................................... | $ | *** |
The original Aggregate Provisional Sum was.................................................................................................... | $ | 950,561,351 | |
Net change by previously authorized Change Orders (0001-00044)................................................................. | $ | (812,283,979 | ) |
The Aggregate Provisional Sum prior to this Change Order was...................................................................... | $ | 138,277,372 | |
The Aggregate Provisional Sum will be unchanged by this Change Order in the amount of........................... | $ | — | |
The new Aggregate Provisional Sum including this Change Order will be...................................................... | $ | 138,277,372 |
/s/ Ed Lehotsky | /s/ Bhupesh Thakkar | |
For Owner | For Contractor | |
Ed Lehotsky | Bhupesh Thakkar | |
Name | Name | |
SVP E&C | Senior Project Manager | |
Title | Title | |
July 2, 2018 | June 29, 2018 | |
Date of Signing | Date of Signing |