PROJECT NAME: Corpus Christi Stage 1 Liquefaction Facility OWNER: Corpus Christi Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 6, 2013 | CHANGE ORDER NUMBER: CO-00038 DATE OF CHANGE ORDER: November 10, 2017 |
1. | Per Article 6.1 of the Agreement, Parties agree to implement changes for cover 24 separate scope items as identified in Attachment A. |
2. | The scope of this Change Order is as detailed in Exhibit A. The parties agree that Exhibit A represents all known unresolved issues and provides for a resolution for these items. |
3. | The cost breakdowns for the scopes of work noted above in this Change Order are detailed in Exhibit B. The cost identified is a summary of the all the scope as identified in Exhibit A. |
4. | Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the Milestone(s) listed in Exhibit C of this Change Order. |
$ | 7,080,830,000 | ||
Net change by previously authorized Change Orders (0001-00037) | $ | 721,849,295 | |
The Contract Price prior to this Change Order was | $ | 7,802,679,295 | |
The Aggregate Equipment Price will be changed by this Change Order in the amount of | $ | *** | |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of | $ | *** | |
The new Contract Price including this Change Order will be | $ | 7,808,179,295 |
The original Aggregate Equipment Price was | $ | *** |
Net change by previously authorized Change Orders (0001-00037) | $ | *** |
The Aggregate Equipment Price prior to this Change Order was | $ | *** |
The Aggregate Equipment Price will be changed by this Change Order in the amount of | $ | *** |
The new Aggregate Equipment Price including this Change Order will be | $ | *** |
The original Aggregate Labor and Skills Price was | $ | *** |
Net change by previously authorized Change Orders (0001-00037) | $ | *** |
The Aggregate Labor and Skills Price prior to this Change Order was | $ | *** |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of | $ | *** |
The new Aggregate Labor and Skills Price including this Change Order will be | $ | *** |
The original Aggregate Provisional Sum was | $ | 950,561,351 | |
Net change by previously authorized Change Orders (0001-00037) | $ | (763,283,979 | ) |
The Aggregate Provisional Sum prior to this Change Order was | $ | 187,277,372 | |
The Aggregate Provisional Sum will be changed by this Change Order in the amount of | $ | — | |
The new Aggregate Provisional Sum including this Change Order will be | $ | 187,277,372 |
/s/ Ed Lehotsky | /s/ Sergio Buoncristiano | |
Owner | Contractor | |
Ed Lehotsky | Sergio Buoncristiano | |
Name | Name | |
Sr. VP E&C | SVP | |
Title | Title | |
January 3, 2018 | November 13, 2017 | |
Date of Signing | Date of Signing |
PROJECT NAME: Corpus Christi Stage 1 Liquefaction Facility OWNER: Corpus Christi Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 6, 2013 | CHANGE ORDER NUMBER: CO-00039 DATE OF CHANGE ORDER: February 26, 2018 |
1. | Per Articles 6.1 and 6.2 of the Agreement, Parties agree to implement changes due to (1) compliance with revised OSHA regulation (29 CFR 1910 Subpart D) as specifically set forth in Exhibit A of this Change Order, (2) removal of the east jetty scaffolding to facilitate work by Luhr Brothers, (3) the replacement of Attachment Y of the Agreement, (4) the replacement of Section 2.4 of Attachment EE, Schedule EE-2, and (5) the interim adjustment to the Insurance Provisional Sum pursuant to Section 2.4(A) of such new Section 2.4 of Attachment EE, Schedule EE-2. |
2. | The scope of this Change Order is further detailed in Exhibit A. Exhibit A also includes two attachments: (1) a new Attachment Y of the Agreement and (2) a new Section 2.4 of Attachment EE, Schedule EE-2 of the Agreement. In connection with the new Attachment Y, the Parties agree to remove Article 6.2(A)(13) in its entirety and replace it with the following: |
3. | The cost breakdowns for the scopes of work noted above in this Change Order are detailed in Exhibit B. These costs are as detailed in Trend S1-2017 (dated Nov. 27, 2017), Trend S1-2054 (dated Dec. 14, 2017), and Trend S1-2041 (dated Dec. 14, 2017). The new Attachment Y does not have a trend as the Parties agree this update has no cost impact. |
4. | Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the Milestone(s) listed in Exhibit C of this Change Order. |
The original Contract Price was | $ | 7,080,830,000 | |
Net change by previously authorized Change Orders (0001-00038) | $ | 727,349,295 | |
The Contract Price prior to this Change Order was | $ | 7,808,179,295 | |
The Aggregate Equipment Price will be changed by this Change Order in the amount of | $ | *** | |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of | $ | *** | |
The new Contract Price including this Change Order will be | $ | 7,764,397,743 |
The original Aggregate Equipment Price was | $ | *** |
Net change by previously authorized Change Orders (0001-00038) | $ | *** |
The Aggregate Equipment Price prior to this Change Order was | $ | *** |
The Aggregate Equipment Price will be changed by this Change Order in the amount of | $ | *** |
The new Aggregate Equipment Price including this Change Order will be | $ | *** |
The original Aggregate Labor and Skills Price was | $ | *** |
Net change by previously authorized Change Orders (0001-00038) | $ | *** |
The Aggregate Labor and Skills Price prior to this Change Order was | $ | *** |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of | $ | *** |
The new Aggregate Labor and Skills Price including this Change Order will be | $ | *** |
The original Aggregate Provisional Sum was | $ | 950,561,351 | |
Net change by previously authorized Change Orders (0001-00038) | $ | (763,283,979 | ) |
The Aggregate Provisional Sum prior to this Change Order was | $ | 187,277,372 | |
The Aggregate Provisional Sum will be changed by this Change Order in the amount of | $ | (49,000,000 | ) |
The new Aggregate Provisional Sum including this Change Order will be | $ | 138,277,372 |
/s/ Ed Lehotsky | /s/ Sergio Buoncristiano | |
Owner | Contractor | |
Ed Lehotsky | Sergio Buoncristiano | |
Name | Name | |
Sr. VP E&C | SVP | |
Title | Title | |
March 18, 2018 | March 7, 2018 | |
Date of Signing | Date of Signing |
PROJECT NAME: Corpus Christi Stage 1 Liquefaction Facility OWNER: Corpus Christi Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 6, 2013 | CHANGE ORDER NUMBER: CO-00041 DATE OF CHANGE ORDER: March 6, 2018 |
1. | Per Articles 6.1 and 6.2 of the Agreement, Parties agree Contractor will implement changes to incorporate GE depot Service Bulletins (SB) No. 272, 278 and 286 for the 12 GE gas turbines for Train 1 and Train 2. |
2. | Per Articles 6.1 and 6.2 of the Agreement, Parties agree Contractor will implement changes to the trim on the JT valves 11PV-16002 and 12PV-16002, located in the methane cold boxes of Train 1 and Train 2. |
3. | The scope of this Change Order is further detailed in Exhibit A. |
4. | The cost breakdowns for the scope of work noted above in this Change Order are detailed in Exhibit B. These costs are as detailed in Trend S1-2056 and Trend S1-2049. |
5. | Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the Milestone(s) listed in Exhibit C-1 of this Change Order. In addition to the adjustments associated with the above changes, three (3) other milestone payment descriptions (milestone numbers ALS 42.4, ALS 46.4 and ALS 47.5) are adjusted as shown in Exhibit C-2 of this Change Order. These milestones payment description adjustments do not modify the overall total amounts of Attachment C of the Agreement. |
The original Contract Price was | $ | 7,080,830,000 | |
Net change by previously authorized Change Orders (0001-00040) | $ | 691,567,743 | |
The Contract Price prior to this Change Order was | $ | 7,772,397,743 | |
The Aggregate Equipment Price will be changed by this Change Order in the amount of | $ | *** | |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of | $ | *** | |
The new Contract Price including this Change Order will be | $ | 7,775,832,402 |
The original Aggregate Equipment Price was | $ | *** |
Net change by previously authorized Change Orders (0001-00040) | $ | *** |
The Aggregate Equipment Price prior to this Change Order was | $ | *** |
The Aggregate Equipment Price will be changed by this Change Order in the amount of | $ | *** |
The new Aggregate Equipment Price including this Change Order will be | $ | *** |
The original Aggregate Labor and Skills Price was | $ | *** |
Net change by previously authorized Change Orders (0001-00040) | $ | *** |
The Aggregate Labor and Skills Price prior to this Change Order was | $ | *** |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of | $ | *** |
The new Aggregate Labor and Skills Price including this Change Order will be | $ | *** |
The original Aggregate Provisional Sum was | $ | 950,561,351 | |
Net change by previously authorized Change Orders (0001-00040) | $ | (812,283,979 | ) |
The Aggregate Provisional Sum prior to this Change Order was | $ | 138,277,372 | |
The Aggregate Provisional Sum will be changed by this Change Order in the amount of | $ | — | |
The new Aggregate Provisional Sum including this Change Order will be | $ | 138,277,372 |
/s/ Ed Lehotsky | /s/ Sergio Buoncristiano | |
Owner | Contractor | |
Ed Lehotsky | Sergio Buoncristiano | |
Name | Name | |
Sr. VP E&C | SVP | |
Title | Title | |
March 19, 2018 | March 6, 2018 | |
Date of Signing | Date of Signing |