PROJECT NAME: Corpus Christi Stage 1 Liquefaction Facility OWNER: Corpus Christi Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 6, 2013 | CHANGE ORDER NUMBER: CO-00022 DATE OF CHANGE ORDER: June 20, 2016 |
1. | Per Article 6.1.B of the Agreement, Parties agree Contractor will incorporate one hundred and fifty-one (151) Owner-requested modifications into the Buildings Subcontract. The list of one hundred and fifty-one (151) Owner-requested modifications is included in Exhibit A of this Change Order. |
2. | The cost breakdowns for the scopes of work noted above in this Change Order are detailed in Exhibit B of this Change Order. |
3. | Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the Milestone(s) listed in Exhibit C of this Change Order. |
The original Contract Price was | $ | 7,080,830,000 | |
Net change by previously authorized Change Orders (0001-00021) | $ | 558,629,312 | |
The Contract Price prior to this Change Order was | $ | 7,639,459,312 | |
The Aggregate Equipment Price will be changed by this Change Order in the amount of | $ | *** | |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of | $ | *** | |
The new Contract Price including this Change Order will be | $ | 7,641,412,919 |
The original Aggregate Equipment Price was | $ | *** |
Net change by previously authorized Change Orders (0001-00021) | $ | *** |
The Aggregate Equipment Price prior to this Change Order was | $ | *** |
The Aggregate Equipment Price will be changed by this Change Order in the amount of | $ | *** |
The new Aggregate Equipment Price including this Change Order will be | $ | *** |
The original Aggregate Labor and Skills Price was | $ | *** |
Net change by previously authorized Change Orders (0001-00021) | $ | *** |
The Aggregate Labor and Skills Price prior to this Change Order was | $ | *** |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of | $ | *** |
The new Aggregate Labor and Skills Price including this Change Order will be | $ | *** |
The original Aggregate Provisional Sum was | $ | 950,561,351 | |
Net change by previously authorized Change Orders (0001-00021) | $ | (745,966,926 | ) |
The Aggregate Provisional Sum prior to this Change Order was | $ | 204,594,425 | |
The Aggregate Provisional Sum will be changed by this Change Order in the amount of | $ | — | |
The new Aggregate Provisional Sum including this Change Order will be | $ | 204,594,425 |
/s/ Ed Lehotsky | /s/ Walker Kimball | |
Owner | Contractor | |
Ed Lehotsky | Walker Kimball | |
Name | Name | |
Sr. VP LNG E&C | Senior Project Manager, SVP | |
Title | Title | |
July 21, 2016 | June 29, 2016 | |
Date of Signing | Date of Signing |
PROJECT NAME: Corpus Christi Stage 1 Liquefaction Facility OWNER: Corpus Christi Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 6, 2013 | CHANGE ORDER NUMBER: CO-00024 DATE OF CHANGE ORDER: June 28, 2016 |
1. | Per Article 6.1.B of the Agreement, Parties agree Contractor will incorporate additional scope for the Nitrogen Dewar System. Specifically, Contractor will: |
a. | Design and construct a 35’ x 35’ foundation to accommodate all equipment. Exhibit A depicts the foundation and notes the addition of high and low point elevations. Owner’s subcontractor will be responsible for placing the equipment on the foundation, anchoring the equipment with post-install anchor bolts, and applying grout between the foundation and supports to account for the slope. Exhibit A also depicts the tie point locations for the 8” nitrogen and 2” boil-off gas lines. |
b. | Owner’s subcontractor’s equipment is depicted in Exhibit B of this Change Order. |
2. | Per Article 6.1.B of the Agreement, Parties agree Contractor will provide temporary construction power to the southeast corner of 102R04 for use by Owner to support the air cooler test requirements. A new 6” conduit with associated 930 feet of trenching for power cable installation is added from the 102F01 Construction CMT office to the designated location for the air cooler test. The cooler fan foundation scope will be managed by Owner. This scope is depicted in Exhibit C of this Change Order. |
3. | Per Article 6.1.B of the Agreement, Parties agree Contractor will change the design pressure of the downstream condensate pipeline to 1480 psig at 100°F, which will require the addition of two (2) more pressure sensors to create a 2 out of 3 sensing capability, as well as adding a second in-line XV valve. |
4. | The cost breakdowns for the scopes of work noted above in this Change Order are detailed in Exhibit D. |
5. | Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the Milestone(s) listed in Exhibit E of this Change Order. |
The original Contract Price was | $ | 7,080,830,000 | |
Net change by previously authorized Change Orders (0001-00023) | $ | 573,441,192 | |
The Contract Price prior to this Change Order was | $ | 7,654,271,192 | |
The Aggregate Equipment Price will be changed by this Change Order in the amount of | $ | *** | |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of | $ | *** | |
The new Contract Price including this Change Order will be | $ | 7,654,633,299 |
The original Aggregate Equipment Price was | $ | *** |
Net change by previously authorized Change Orders (0001-00023) | $ | *** |
The Aggregate Equipment Price prior to this Change Order was | $ | *** |
The Aggregate Equipment Price will be changed by this Change Order in the amount of | $ | *** |
The new Aggregate Equipment Price including this Change Order will be | $ | *** |
The original Aggregate Labor and Skills Price was | $ | *** |
Net change by previously authorized Change Orders (0001-00023) | $ | *** |
The Aggregate Labor and Skills Price prior to this Change Order was | $ | *** |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of | $ | *** |
The new Aggregate Labor and Skills Price including this Change Order will be | $ | *** |
The original Aggregate Provisional Sum was | $ | 950,561,351 | |
Net change by previously authorized Change Orders (0001-00023) | $ | (745,966,926 | ) |
The Aggregate Provisional Sum prior to this Change Order was | $ | 204,594,425 | |
The Aggregate Provisional Sum will be changed by this Change Order in the amount of | $ | — | |
The new Aggregate Provisional Sum including this Change Order will be | $ | 204,594,425 |
/s/ Ed Lehotsky | /s/ Walker Kimball | |
Owner | Contractor | |
Ed Lehotsky | Walker Kimball | |
Name | Name | |
Sr. VP LNG E&C | Senior Project Manager, SVP | |
Title | Title | |
July 21, 2016 | June 29, 2016 | |
Date of Signing | Date of Signing |