• | First LNG commissioning cargo exported in February marking transition towards operations |
• | In February, the first commissioning cargo with LNG produced at the Sabine Pass Liquefaction Project (defined below) was successfully loaded and exported. A total of four LNG commissioning cargoes were loaded and exported during the three months ended March 31, 2016, and a total of seven LNG commissioning cargoes have been loaded and exported to date. |
• | In February, Cheniere Partners closed on up to approximately $2.8 billion of senior secured credit facilities (the “CQP Credit Facilities”). The four-year credit facilities consist of a $450 million CTPL tranche term loan, an approximately $2.1 billion Sabine Pass LNG, L.P. (“SPLNG”) tranche term loan, a $125 million debt service reserve credit facility, and a $115 million revolving credit facility. The CTPL tranche term loan was used to prepay the $400 million senior secured term loan at CTPL subsequent to closing of the facilities. Remaining proceeds from the facilities will be used by Cheniere Partners (i) to redeem or repay the approximately $1.7 billion senior secured notes due 2016 and the $420 million senior secured notes due 2020 that were issued by SPLNG, (ii) to pay associated transaction costs and make-whole amounts, if any, and (iii) for general business purposes of Cheniere Partners and its subsidiaries. |
▪ | Construction on Trains 1 and 2 began in August 2012, and as of March 31, 2016, the overall project completion percentage for Trains 1 and 2 was approximately 98.3%, which is ahead of the contractual schedule. Cheniere Partners expects substantial completion of Train 1 to be achieved in May 2016. The commissioning process on Train 2 has commenced, and Cheniere Partners expects substantial completion of Train 2 to be achieved in September 2016. |
▪ | Construction on Trains 3 and 4 began in May 2013, and as of March 31, 2016, the overall project completion percentage for Trains 3 and 4 was approximately 83.8%, which is ahead of the contractual schedule. Cheniere Partners expects Trains 3 and 4 to reach substantial completion in 2017. |
▪ | Construction on Train 5 began in June 2015, and as of March 31, 2016, the overall project completion percentage for Train 5 was approximately 28.8%, which is ahead of the contractual schedule. Engineering, procurement, subcontract work and Bechtel direct hire construction were approximately 59.1%, 45.1%, 24.2% and 0.4% complete, respectively. Cheniere Partners expects Train 5 to reach substantial completion in 2019. |
▪ | Train 6 is currently under development, with all necessary regulatory approvals in place. Cheniere Partners expects to make a final investment decision and commence construction on Train 6 upon, among other things, entering into an EPC contract, entering into acceptable commercial arrangements, and obtaining adequate financing. |
Sabine Pass Liquefaction Project | ||||
Liquefaction Train | Train 1 | Train 2 | Trains 3-4 | Train 5 |
Project Status | Commissioning / Producing LNG | Commissioning | 84% Overall Completion | 29% Overall Completion |
Expected Substantial Completion | 1H 2016 | 2H 2016 | 2017 | 2019 |
▪ | Construction on Trains 1 and 2 began in May 2015, and as of March 31, 2016, the overall project completion percentage for Trains 1 and 2 was approximately 32.5%, which is ahead of the contractual schedule. Engineering, procurement and construction were approximately 97.1%, 46.0% and 4.6% complete, respectively. We expect Trains 1 and 2 to reach substantial completion in 2019. |
▪ | Train 3 is under development, with all necessary regulatory approvals in place. We have entered into an LNG Sale and Purchase Agreement (“SPA”) for approximately 0.8 mtpa of LNG volumes that commence with Train 3 and expect to commence construction upon entering into additional SPAs and obtaining adequate financing. |
Corpus Christi LNG Terminal | |
Liquefaction Train | Trains 1-2 |
Project Status | 33% Overall Completion |
Expected Substantial Completion | 2019 |
Three Months Ended | |||||||
March 31, | |||||||
2016 | 2015 | ||||||
Revenues | |||||||
Regasification revenues | $ | 65,551 | $ | 66,802 | |||
LNG revenues | 2,704 | 662 | |||||
Other revenues | 826 | 905 | |||||
Total revenues | 69,081 | 68,369 | |||||
Operating costs and expenses | |||||||
Cost of sales (excluding depreciation and amortization expense shown separately below) | 14,507 | 693 | |||||
Operating and maintenance expense | 36,317 | 35,706 | |||||
Development expense | 1,547 | 16,096 | |||||
Marketing expense | 24,978 | 13,046 | |||||
General and administrative expense | 47,924 | 44,971 | |||||
Depreciation and amortization expense | 24,089 | 17,769 | |||||
Impairment expense | 10,166 | 176 | |||||
Other | 112 | 156 | |||||
Total operating costs and expenses | 159,640 | 128,613 | |||||
Loss from operations | (90,559 | ) | (60,244 | ) | |||
Other income (expense) | |||||||
Interest expense, net of capitalized interest | (76,337 | ) | (59,612 | ) | |||
Loss on early extinguishment of debt | (1,457 | ) | (88,992 | ) | |||
Derivative loss, net | (180,934 | ) | (126,690 | ) | |||
Other income | 929 | 372 | |||||
Total other expense | (257,799 | ) | (274,922 | ) | |||
Loss before income taxes and non-controlling interest | (348,358 | ) | (335,166 | ) | |||
Income tax provision | (616 | ) | (678 | ) | |||
Net loss | (348,974 | ) | (335,844 | ) | |||
Less: net loss attributable to non-controlling interest | (28,136 | ) | (68,135 | ) | |||
Net loss attributable to common stockholders | $ | (320,838 | ) | $ | (267,709 | ) | |
Net loss per share attributable to common stockholders—basic and diluted | $ | (1.41 | ) | $ | (1.18 | ) | |
Weighted average number of common shares outstanding—basic and diluted | 228,138 | 226,328 |
(1) | Please refer to the Cheniere Energy, Inc. Quarterly Report on Form 10-Q for the quarter ended March 31, 2016, filed with the Securities and Exchange Commission. |
March 31, | December 31, | ||||||
2016 | 2015 | ||||||
ASSETS | (unaudited) | ||||||
Current assets | |||||||
Cash and cash equivalents | $ | 1,094,833 | $ | 1,201,112 | |||
Restricted cash | 732,551 | 503,397 | |||||
Accounts and interest receivable | 23,979 | 5,749 | |||||
Inventory | 31,243 | 18,125 | |||||
Other current assets | 63,509 | 54,203 | |||||
Total current assets | 1,946,115 | 1,782,586 | |||||
Non-current restricted cash | 31,724 | 31,722 | |||||
Property, plant and equipment, net | 17,674,548 | 16,193,907 | |||||
Debt issuance costs, net | 409,894 | 378,677 | |||||
Non-current derivative assets | 29,361 | 30,887 | |||||
Goodwill | 76,819 | 76,819 | |||||
Other non-current assets | 262,486 | 314,455 | |||||
Total assets | $ | 20,430,947 | $ | 18,809,053 | |||
LIABILITIES AND STOCKHOLDERS’ EQUITY | |||||||
Current liabilities | |||||||
Accounts payable | $ | 35,398 | $ | 22,820 | |||
Accrued liabilities | 670,584 | 427,199 | |||||
Current debt, net | 1,785,318 | 1,673,379 | |||||
Deferred revenue | 26,669 | 26,669 | |||||
Derivative liabilities | 50,561 | 35,201 | |||||
Other current liabilities | 93 | — | |||||
Total current liabilities | 2,568,623 | 2,185,268 | |||||
Long-term debt, net | 16,348,099 | 14,920,427 | |||||
Non-current deferred revenue | 8,500 | 9,500 | |||||
Non-current derivative liabilities | 239,372 | 79,387 | |||||
Other non-current liabilities | 61,668 | 53,068 | |||||
Commitments and contingencies | |||||||
Stockholders’ equity | |||||||
Preferred stock, $0.0001 par value, 5.0 million shares authorized, none issued | — | — | |||||
Common stock, $0.003 par value | |||||||
Authorized: 480.0 million shares at March 31, 2016 and December 31, 2015 | |||||||
Issued and outstanding: 235.5 million shares and 235.6 million shares at March 31, 2016 and December 31, 2015, respectively | 707 | 708 | |||||
Treasury stock: 11.7 million shares and 11.6 million shares at March 31, 2016 and December 31, 2015, respectively, at cost | (354,903 | ) | (353,927 | ) | |||
Additional paid-in-capital | 3,088,648 | 3,075,317 | |||||
Accumulated deficit | (3,944,786 | ) | (3,623,948 | ) | |||
Total stockholders’ deficit | (1,210,334 | ) | (901,850 | ) | |||
Non-controlling interest | 2,415,019 | 2,463,253 | |||||
Total equity | 1,204,685 | 1,561,403 | |||||
Total liabilities and equity | $ | 20,430,947 | $ | 18,809,053 |
(1) | Please refer to the Cheniere Energy, Inc. Quarterly Report on Form 10-Q for the quarter ended March 31, 2016, filed with the Securities and Exchange Commission. |