PROJECT NAME: Corpus Christi Stage 1 Liquefaction Facility OWNER: Corpus Christi Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 6, 2013 | CHANGE ORDER NUMBER: CO-00014 DATE OF CHANGE ORDER: January 11, 2016 |
1. | Per Article 6.1.B of the Agreement, Parties agree Contractor will implement the scope changes that are detailed in Exhibit A of this Change Order. |
2. | The scope changes are depicted in the drawings in Exhibit B of this Change Order. |
3. | The cost breakdowns for the scopes of work noted above in this Change Order are detailed in Exhibit C. |
4. | Schedules C-1 and C-3 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestones listed in Exhibit D of this Change Order. |
The original Contract Price was | $ | 7,080,830,000 | |
Net change by previously authorized Change Orders (0001-00013) | $ | 410,656,403 | |
The Contract Price prior to this Change Order was | $ | 7,491,486,403 | |
The Aggregate Equipment Price will be changed by this Change Order in the amount of | $ | *** | |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of | $ | *** | |
The new Contract Price including this Change Order will be | $ | 7,506,562,833 |
The original Aggregate Equipment Price was | $ | *** |
Net change by previously authorized Change Orders (0001-00013) | $ | *** |
The Aggregate Equipment Price prior to this Change Order was | $ | *** |
The Aggregate Equipment Price will be changed by this Change Order in the amount of | $ | *** |
The new Aggregate Equipment Price including this Change Order will be | $ | *** |
The original Aggregate Labor and Skills Price was | $ | *** |
Net change by previously authorized Change Orders (0001-00013) | $ | *** |
The Aggregate Labor and Skills Price prior to this Change Order was | $ | *** |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of | $ | *** |
The new Aggregate Labor and Skills Price including this Change Order will be | $ | *** |
/s/ Ed Lehotsky | /s/ Maria K Brady | |
Owner | Contractor | |
Ed Lehotsky | Maria K Brady | |
Name | Name | |
VP LNG Projects | Senior Vice President | |
Title | Title | |
2/2/2016 | January 11, 2016 | |
Date of Signing | Date of Signing |
PROJECT NAME: Corpus Christi Stage 1 Liquefaction Facility OWNER: Corpus Christi Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 6, 2013 | CHANGE ORDER NUMBER: CO-00015 DATE OF CHANGE ORDER: January 20, 2016 |
1. | In Change Order CO-00002, executed on April 7, 2015, Owner and Contractor agreed to change from SAC to DLE Compressor Turbine Drivers, include the Inlet Air Chilling (IAC) while removing the Inlet Air Humidification, and resize and relocate water treatment facilities. Exhibit A of this Change Order depicts the changes from CO-00002 that are effective upon execution of this CO-00015. |
2. | The value of the IAC Provisional Sum was U.S. $165,125,800. Per Article 6.1.B of the Agreement, Parties agree to close this Provisional Sum. The contract price will be increased by $89,325,232. |
3. | The cost breakdowns for the scopes of work noted above in this Change Order are detailed in Exhibit B. |
4. | Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the Milestone(s) listed in Exhibit C of this Change Order. |
The original Contract Price was | $ | 7,080,830,000 | |
Net change by previously authorized Change Orders (0001-00014) | $ | 425,732,833 | |
The Contract Price prior to this Change Order was | $ | 7,506,562,833 | |
The Aggregate Equipment Price will be changed by this Change Order in the amount of | $ | *** | |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of | $ | *** | |
The new Contract Price including this Change Order will be | $ | 7,595,888,065 |
The original Aggregate Equipment Price was | $ | *** |
Net change by previously authorized Change Orders (0001-00014) | $ | *** |
The Aggregate Equipment Price prior to this Change Order was | $ | *** |
The Aggregate Equipment Price will be changed by this Change Order in the amount of | $ | *** |
The new Aggregate Equipment Price including this Change Order will be | $ | *** |
The original Aggregate Labor and Skills Price was | $ | *** |
Net change by previously authorized Change Orders (0001-00014) | $ | *** |
The Aggregate Labor and Skills Price prior to this Change Order was | $ | *** |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of | $ | *** |
The new Aggregate Labor and Skills Price including this Change Order will be | $ | *** |
The original Aggregate Provisional Sum was | $ | *** |
Net change by previously authorized Change Orders (0001-00014) | $ | *** |
The Aggregate Provisional Sum prior to this Change Order was | $ | *** |
The Aggregate Provisional Sum will be changed by this Change Order in the amount of | $ | *** |
The new Aggregate Provisional Sum including this Change Order will be | $ | *** |
/s/ Ed Lehotsky | /s/ Walker Kimball | |
Owner | Contractor | |
Ed Lehotsky | Walker Kimball | |
Name | Name | |
VP LNG Projects | Senior Project Manager, SVP | |
Title | Title | |
March 2, 2016 | January 20, 2016 | |
Date of Signing | Date of Signing |
PROJECT NAME: Corpus Christi Stage 1 Liquefaction Facility OWNER: Corpus Christi Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 6, 2013 | CHANGE ORDER NUMBER: CO-00016 DATE OF CHANGE ORDER: January 20, 2016 |
1. | Per Article 6.1.B of the Agreement, Parties agree Contractor will make design changes to the O&M, Warehouse, Maintenance, and Auxiliary Material Storage buildings and add two new buildings - Security Operations Building and Laboratory Building. This Change Order includes changes to permanent buildings subcontract and related changes to piping, electrical and sitework for Contractor direct hire work as well as acceleration costs to mitigate schedule impact. |
2. | Exhibit A depicts the changes to the O&M and Control building. |
3. | Exhibit B depicts the changes to the Maintenance building. |
4. | Exhibit C depicts the changes to the Warehouse building. |
5. | Exhibit D depicts the location of the Laboratory building. |
6. | Exhibit E depicts the location of the Security Operations building. |
7. | The Auxiliary Material Storage building will be approximately 22,000 square feet. |
8. | The cost breakdowns for the scopes of work noted above in this Change Order are detailed in Exhibit F. |
9. | Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the Milestone(s) listed in Exhibit G of this Change Order. |
The original Contract Price was | $ | 7,080,830,000 | |
Net change by previously authorized Change Orders (0001-00015) | $ | 515,058,065 | |
The Contract Price prior to this Change Order was | $ | 7,595,888,065 | |
The Aggregate Equipment Price will be changed by this Change Order in the amount of | $ | *** | |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of | $ | *** | |
The new Contract Price including this Change Order will be | $ | 7,624,287,362 |
The original Aggregate Equipment Price was | $ | *** |
Net change by previously authorized Change Orders (0001-00015) | $ | *** |
The Aggregate Equipment Price prior to this Change Order was | $ | *** |
The Aggregate Equipment Price will be changed by this Change Order in the amount of | $ | *** |
The new Aggregate Equipment Price including this Change Order will be | $ | *** |
The original Aggregate Labor and Skills Price was | $ | *** |
Net change by previously authorized Change Orders (0001-00015) | $ | *** |
The Aggregate Labor and Skills Price prior to this Change Order was | $ | *** |
The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of | $ | *** |
The new Aggregate Labor and Skills Price including this Change Order will be | $ | *** |
The original Aggregate Provisional Sum was | $ | *** |
Net change by previously authorized Change Orders (0001-00015) | $ | *** |
The Aggregate Provisional Sum prior to this Change Order was | $ | *** |
The Aggregate Provisional Sum will be changed by this Change Order in the amount of | $ | *** |
The new Aggregate Provisional Sum including this Change Order will be | $ | *** |
/s/ Ed Lehotsky | /s/ Walker Kimball | |
Owner | Contractor | |
Ed Lehotsky | Walker Kimball | |
Name | Name | |
VP LNG Projects | Senior Project Manager, SVP | |
Title | Title | |
February 3, 2016 | January 20, 2016 | |
Date of Signing | Date of Signing |