• | In May 2015, we made a positive final investment decision (“FID”) and issued a notice to proceed (“NTP”) with construction to Bechtel Oil, Gas and Chemicals, Inc. (“Bechtel”) for the first two natural gas liquefaction trains (“Trains”) and the related new facilities (“Stage 1”) of the CCL Project. |
• | In connection with the commencement of construction of Stage 1 of the CCL Project, Cheniere Corpus Christi Holdings, LLC entered into an $8.4 billion credit facility to be used for costs associated with the development, construction, operation and maintenance of Stage 1 of the CCL Project and a 23-mile, 48” natural gas supply pipeline that will interconnect the CCL Project with several interstate and intrastate natural gas pipelines (the “Corpus Christi Pipeline”). |
• | Cheniere CCH Holdco II, LLC, our wholly owned subsidiary, issued $1.0 billion aggregate principal amount of 11% Senior Secured Notes due 2025, which will be used to pay a portion of the capital costs associated with Stage 1 of the CCL Project and the Corpus Christi Pipeline. |
• | In June 2015, SPL made a positive FID and issued an NTP with construction to Bechtel for Train 5 of the Sabine Pass Liquefaction Project (defined below). |
• | In connection with the commencement of construction of Train 5 of the Sabine Pass Liquefaction Project, SPL entered into four credit facilities totaling $4.6 billion, which replaced its existing credit facilities, to fund a portion of the costs of developing, constructing, and placing into operation Trains 1 through 5 of the Sabine Pass Liquefaction Project. |
• | In June 2015, we announced the development of an additional two Trains at the CCL Project, bringing the total number of Trains under development at the CCL Project to up to five, each with expected nominal |
• | In June 2015, we announced an agreement in principle to partner with Parallax Enterprises, LLC for the development of two mid-scale natural gas liquefaction projects in Louisiana, each with expected nominal production capacity of approximately 5.2 mtpa of LNG. |
▪ | Construction on Trains 1 and 2 began in August 2012, and as of June 30, 2015, the overall project completion percentage for Trains 1 and 2 was approximately 92.2%, which is ahead of the contractual schedule. Based on our current construction schedule, we anticipate that Train 1 will produce LNG as early as late 2015. |
▪ | Construction on Trains 3 and 4 began in May 2013, and as of June 30, 2015, the overall project completion percentage for Trains 3 and 4 was approximately 69.2%, which is ahead of the contractual schedule. We expect Trains 3 and 4 to become operational in late 2016 and 2017, respectively. |
▪ | The permitting process for Trains 5 and 6 has been completed. In April 2015, Cheniere Partners received FERC authorization to site, construct, and operate Trains 5 and 6. In June 2015, Cheniere Partners received authorization from the DOE to export LNG to non-FTA countries. |
▪ | Construction on Train 5 began on June 30, 2015, and Train 6 is under development. We expect Train 5 to commence operations as early as 2018. We expect to commence construction on Train 6 upon entering into acceptable commercial arrangements and obtaining adequate financing. |
▪ | Construction on Trains 1 and 2 began in May 2015. Train 3 is under development. We have entered into a Sale and Purchase Agreement (“SPA”) for approximately 0.8 mtpa of LNG volumes that commence with Train 3 and will contemplate making an FID to commence construction upon entering into additional SPAs. To date, we have obtained sufficient financing commitments and all necessary regulatory permits required to support the development of three Trains. |
▪ | Trains 4 and 5 are under development. We have initiated the regulatory process by filing the NEPA pre-filing request with the FERC, and requesting authorization from the DOE to export LNG to both FTA and non-FTA countries. |
Target Date | ||||||||
SPL | CCL | |||||||
Milestone | Trains 1 - 4 | Trains 5 & 6 | Trains 1 - 3 | Trains 4 & 5 | ||||
DOE export authorization | Received | Received | Received | 2017 | ||||
Definitive commercial agreements | Completed 16.0 mtpa | T5: Completed T6: 2015 | T1-T2: Completed T3: 2015 | |||||
- BG Gulf Coast LNG, LLC | 5.5 mtpa | |||||||
- Gas Natural Fenosa | 3.5 mtpa | |||||||
- KOGAS | 3.5 mtpa | |||||||
- GAIL (India) Ltd. | 3.5 mtpa | |||||||
- Total Gas & Power N.A. | 2.0 mtpa | |||||||
- Centrica plc | 1.75 mtpa | |||||||
- PT Pertamina (Persero) | 1.52 mtpa | |||||||
- Endesa, S.A. | 2.25 mtpa | |||||||
- Iberdrola, S.A. | 0.76 mtpa | |||||||
- Gas Natural Fenosa LNG SL | 1.50 mtpa | |||||||
- Woodside Energy Trading Singapore | 0.85 mtpa | |||||||
- Électricité de France, S.A. | 0.77 mtpa | |||||||
- EDP Energias de Portugal S.A. | 0.77 mtpa | |||||||
EPC contracts | Completed | T5: Completed T6: 2015 | Completed | |||||
Financing | Completed | T5: Completed T6: 2015 | Completed | |||||
FERC authorization | Completed | Completed | Completed | 2017 | ||||
Issue Notice to Proceed | Completed | T5: Completed T6: 2015 | T1-T2: Completed T3: 2015 | 2017 | ||||
Commence operations | 2015 - 2017 | 2018/2019 | 2018/2019 | 2021 |
Three Months Ended | Six Months Ended | ||||||||||||||
June 30, | June 30, | ||||||||||||||
2015 | 2014 | 2015 | 2014 | ||||||||||||
Revenues | |||||||||||||||
LNG terminal revenues | $ | 67,905 | $ | 66,841 | $ | 135,486 | $ | 133,260 | |||||||
Marketing and trading revenues (losses) | (706 | ) | 324 | (44 | ) | 981 | |||||||||
Other | 826 | 480 | 952 | 954 | |||||||||||
Total revenues | 68,025 | 67,645 | 136,394 | 135,195 | |||||||||||
Operating costs and expenses | |||||||||||||||
General and administrative expense | 107,856 | 67,720 | 165,873 | 141,528 | |||||||||||
Operating and maintenance expense | 18,877 | 29,409 | 56,030 | 43,096 | |||||||||||
Depreciation expense | 20,154 | 17,298 | 37,923 | 32,773 | |||||||||||
Development expense | 16,609 | 15,263 | 32,705 | 27,375 | |||||||||||
Other | 109 | 90 | 441 | 170 | |||||||||||
Total operating costs and expenses | 163,605 | 129,780 | 292,972 | 244,942 | |||||||||||
Loss from operations | (95,580 | ) | (62,135 | ) | (156,578 | ) | (109,747 | ) | |||||||
Other income (expense) | |||||||||||||||
Interest expense, net | (85,486 | ) | (43,789 | ) | (145,098 | ) | (84,059 | ) | |||||||
Loss on early extinguishment of debt | (7,281 | ) | (114,335 | ) | (96,273 | ) | (114,335 | ) | |||||||
Derivative gain (loss), net | 45,755 | (60,178 | ) | (80,181 | ) | (94,859 | ) | ||||||||
Other income (expense) | 283 | (189 | ) | 655 | 121 | ||||||||||
Total other expense | (46,729 | ) | (218,491 | ) | (320,897 | ) | (293,132 | ) | |||||||
Loss before income taxes and non-controlling interest | (142,309 | ) | (280,626 | ) | (477,475 | ) | (402,879 | ) | |||||||
Income tax benefit (provision) | 507 | (84 | ) | (171 | ) | (176 | ) | ||||||||
Net loss | (141,802 | ) | (280,710 | ) | (477,646 | ) | (403,055 | ) | |||||||
Less: net loss attributable to non-controlling interest | (23,307 | ) | (78,782 | ) | (91,442 | ) | (103,317 | ) | |||||||
Net loss attributable to common stockholders | $ | (118,495 | ) | $ | (201,928 | ) | $ | (386,204 | ) | $ | (299,738 | ) | |||
Net loss per share attributable to common stockholders—basic and diluted | $ | (0.52 | ) | $ | (0.90 | ) | $ | (1.71 | ) | $ | (1.34 | ) | |||
Weighted average number of common shares outstanding—basic and diluted | 226,481 | 223,602 | 226,405 | 223,406 |
(1) | Please refer to the Cheniere Energy, Inc. Quarterly Report on Form 10-Q for the quarter ended June 30, 2015, filed with the Securities and Exchange Commission. |
June 30, | December 31, | ||||||
2015 | 2014 | ||||||
ASSETS | (unaudited) | ||||||
Current assets | |||||||
Cash and cash equivalents | $ | 1,470,207 | $ | 1,747,583 | |||
Restricted cash | 684,073 | 481,737 | |||||
Accounts and interest receivable | 6,746 | 4,419 | |||||
LNG inventory | 13,954 | 4,294 | |||||
Other current assets | 88,382 | 20,844 | |||||
Total current assets | 2,263,362 | 2,258,877 | |||||
Non-current restricted cash | 739,145 | 550,811 | |||||
Property, plant and equipment, net | 13,799,113 | 9,246,753 | |||||
Debt issuance costs, net | 637,301 | 242,323 | |||||
Non-current derivative assets | 21,363 | 11,744 | |||||
Goodwill | 76,819 | 76,819 | |||||
Other non-current assets | 222,399 | 186,356 | |||||
Total assets | $ | 17,759,502 | $ | 12,573,683 | |||
LIABILITIES AND STOCKHOLDERS’ EQUITY | |||||||
Current liabilities | |||||||
Accounts payable | $ | 23,799 | $ | 13,426 | |||
Accrued liabilities | 565,832 | 169,129 | |||||
Deferred revenue | 26,671 | 26,655 | |||||
Derivative liabilities | 23,937 | 23,247 | |||||
Other current liabilities | 600 | 18 | |||||
Total current liabilities | 640,839 | 232,475 | |||||
Long-term debt, net | 14,854,794 | 9,806,084 | |||||
Non-current deferred revenue | 11,500 | 13,500 | |||||
Other non-current liabilities | 37,013 | 20,107 | |||||
Commitments and contingencies | |||||||
Stockholders’ equity | |||||||
Preferred stock, $0.0001 par value, 5.0 million shares authorized, none issued | — | — | |||||
Common stock, $0.003 par value | |||||||
Authorized: 480.0 million shares at June 30, 2015 and December 31, 2014 | |||||||
Issued and outstanding: 236.6 million shares and 236.7 million shares at June 30, 2015 and December 31, 2014, respectively | 711 | 712 | |||||
Treasury stock: 10.7 million shares and 10.6 million shares at June 30, 2015 and December 31, 2014, respectively, at cost | (298,926 | ) | (292,752 | ) | |||
Additional paid-in-capital | 3,014,483 | 2,776,702 | |||||
Accumulated deficit | (3,035,043 | ) | (2,648,839 | ) | |||
Total stockholders’ deficit | (318,775 | ) | (164,177 | ) | |||
Non-controlling interest | 2,534,131 | 2,665,694 | |||||
Total equity | 2,215,356 | 2,501,517 | |||||
Total liabilities and equity | $ | 17,759,502 | $ | 12,573,683 |
(1) | Please refer to the Cheniere Energy, Inc. Quarterly Report on Form 10-Q for the quarter ended June 30, 2015, filed with the Securities and Exchange Commission. |