PROJECT NAME: Corpus Christi Stage 1 Liquefaction Facility OWNER: Corpus Christi Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 6, 2013 | CHANGE ORDER NUMBER: CO-00001 DATE OF CHANGE ORDER: March 9, 2015 |
1. | Per Article 6.2.A.11 of the Agreement, Parties agree to increase the Contract Price for Contractor’s increased costs to perform Work by $233,800,000 due to delay in issuance of NTP from July 1, 2014 to April 1, 2015. Pricing validity for contractual purposes is May 1, 2015. |
2. | The overall cost breakdown for this Change Order is detailed in Exhibit A and described as follows: |
a. | The previous Aggregate Equipment Price prior to this Change Order was *** U.S. Dollars (U.S. $***). This Change Order will amend that value and the new value shall be *** U.S. Dollars (U.S. $***). |
b. | The previous Aggregate Labor and Skills Price prior to this Change Order was *** U.S. Dollars (U.S.$***). This Change Order will amend that value and the new value shall be *** U.S. Dollars (U.S. $***). |
3. | Schedules C-1 and C-3 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit B of this Change Order. |
The original Contract Price was | $ | 7,080,830,000 | |
Net change by previously authorized Change Orders | $ | — | |
The Contract Price prior to this Change Order was | $ | 7,080,830,000 | |
The Aggregate Equipment Price will be increased by this Change Order in the amount of | $ | *** | |
The Aggregate Labor and Skills Price will be increased by this Change Order in the amount of | $ | *** | |
The Aggregate Provisional Sum will be unchanged by this Change Order in the amount of | $ | — | |
The new Contract Price including this Change Order will be | $ | 7,314,630,000 |
/s/ Ed Lehotsky | /s/ Maria K. Brady | |
Owner | Contractor | |
Ed Lehotsky | Maria K. Brady | |
Name | Name | |
VP LNG Projects | Senior Vice President | |
Title | Title | |
March 31, 2015 | March 9, 2015 | |
Date of Signing | Date of Signing |
PROJECT NAME: Corpus Christi Stage 1 Liquefaction Facility OWNER: Corpus Christi Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 6, 2013 | CHANGE ORDER NUMBER: CO-00002 DATE OF CHANGE ORDER: March 25, 2015 |
1. | Per Article 6.2.A.11 of the Agreement, Parties agree Bechtel will change from SAC to DLE Compressor Turbine Drivers, include the Inlet Air Chilling (IAC) while removing the Inlet Air Humidification, and resize and relocate water treatment facilities. |
2. | The following scope changes will be incorporated from this Change Order: |
a. | Inlet air chilling (Stellar Chiller Package) will be added and utilized in the Nuovo Pignone PGT 2500 + G4 aero-derivative gas turbine engines for both Subproject 1 and Subproject 2. |
b. | Change to DLE compressor turbine drivers (GE Compressor/Turbine Package) for installed and capital spares. |
c. | Removal of the Inlet Air Humidification (GE Compressor/Turbine Package). |
d. | Resize/relocate the Water Treatment Facility from 102F01 to 105A01 (Aquatech Package). |
e. | Add 30” welding pipe caps on Methane Cold Boxes (Linde Package). |
f. | Add 30” HDPE water lines from chiller package to ISBL chiller coils. |
g. | Revise electrical design from 13.8kV to 34.5kV transformers. |
3. | Exhibit A of this Change Order depicts the changes associated with the details in Item 2 of this Change Order. |
4. | Article 2.5 of Attachment EE, Schedule EE-2 will be added and shall state the following: |
5. | Bechtel and CCL agree Attachment S - “Performance Tests and Commissioning Tests” and Attachment T - “Performance Guarantee, Performance Liquidated Damages, Minimum Acceptance Criteria, and Delay Liquidated Damages” of the EPC Agreement shall be replaced with the revised versions in Exhibit B of this Change Order. |
6. | The overall cost breakdown for this Change Order is detailed in Exhibit C and described as follows: |
a. | The previous Aggregate Equipment Price prior to this Change Order was *** U.S. Dollars (U.S. $***). This Change Order will amend that value and the new value shall be *** U.S. Dollars (U.S. $***). |
b. | The previous Aggregate Labor and Skills Price prior to this Change Order was *** U.S. Dollars (U.S. $***). This Change Order will amend that value and the new value shall be *** U.S. Dollars (U.S. $***). |
7. | The previous Aggregate Provisional Sum prior to this Change Order was Nine Hundred Fifty Million Five Hundred Sixty One Thousand Three Hundred Fifty One U.S. Dollars (U.S. $950,561,351). This Change Order will amend that value and the new value shall be One Billion, One Hundred Fifteen Million, Six Hundred eighty Seven Thousand, One Hundred Fifty One U.S. Dollars (U.S. $1,115,687,151). |
8. | Schedules C-1 and C-3 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit D of this Change Order. |
The original Contract Price was | $ | 7,080,830,000 | |
Net change by previously authorized Change Orders (0001) | $ | 233,800,000 | |
The Contract Price prior to this Change Order was | $ | 7,314,630,000 | |
The Aggregate Equipment Price will be increased by this Change Order in the amount of | $ | *** | |
The Aggregate Labor and Skills Price will be increased by this Change Order in the amount of | $ | *** | |
The Aggregate Provisional Sum will be unchanged by this Change Order in the amount of | $ | *** | |
The new Contract Price including this Change Order will be | $ | 7,573,977,398 |
/s/ Ed Lehotsky | /s/ Marcello Donati | |
Owner | Contractor | |
Ed Lehotsky | Marcello Donati | |
Name | Name | |
VP LNG Projects | Project Manager | |
Title | Title | |
April 7, 2015 | March 25, 2015 | |
Date of Signing | Date of Signing |
PROJECT NAME: Corpus Christi Stage 1 Liquefaction Facility OWNER: Corpus Christi Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 6, 2013 | CHANGE ORDER NUMBER: CO-00003 DATE OF CHANGE ORDER: May 13, 2015 |
1. | The Currency Provisional Sum in Article 1.1 of Attachment EE, Schedule EE-1 of the Agreement prior to this Change Order was *** U.S Dollars (U.S. $***). The Provisional Sum is hereby decreased by $*** and the new value as amended by this Change Order shall be $*** |
2. | Pursuant to instructions in Article 1.1 of Attachment EE, Schedule EE-1 of the Agreement, Exhibit A to this Change Order illustrates the calculation of the final currency costs in the Agreement. |
3. | The Fuel Provisional Sum in Article 1.2 of Attachment EE, Schedule EE-1 of the Agreement prior to this Change Order was *** U.S Dollars (U.S. $***). The Provisional Sum is hereby decreased by $*** and the new value as amended by this Change Order shall be $***. |
4. | Pursuant to instructions in Article 1.2 of Attachment EE, Schedule EE-1 of the Agreement, Exhibit B to this Change Order illustrates the calculation of the final fuel costs in the Agreement. |
5. | The Aggregate Provisional Sum specified in Article 7.1 of the Agreement prior to this Change Order was $950,561,351. The Aggregate Provisional Sum is decreased by $551,704,129 and the new value of the Aggregate Provisional Sum is $398,857,222. |
6. | The previous Aggregate Equipment Price prior to this Change Order was *** U.S. Dollars (U.S. $***). This Change Order will amend that value and the new value shall be *** U.S. Dollars (U.S. $***). |
7. | The previous Aggregate Labor and Skills Price prior to this Change Order was *** U.S. Dollars (U.S. $***). This Change Order will amend that value and the new value shall be *** U.S. Dollars (U.S. $***) |
8. | Schedules C-1 and C-3 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestones listed in Exhibit C of this Change Order. |
The original Contract Price was | $ | 7,080,830,000 | |
Net change by previously authorized Change Orders (0001, 0002, and 0004) | $ | 493,147,398 | |
The Contract Price prior to this Change Order was | $ | 7,573,977,398 | |
The Aggregate Equipment Price will be increased by this Change Order in the amount of | $ | *** | |
The Aggregate Labor and Skills Price will be increased by this Change Order in the amount of | $ | *** | |
The Aggregate Provisional Sum will be unchanged by this Change Order in the amount of | $ | *** | |
The new Contract Price including this Change Order will be | $ | 7,479,143,655 |
/s/ Ed Lehotsky | /s/ Maria K. Brady | |
Owner | Contractor | |
Ed Lehotsky | Maria K. Brady | |
Name | Name | |
VP LNG Projects | Senior Vice President | |
Title | Title | |
May 13, 2015 | May 13, 2015 | |
Date of Signing | Date of Signing |
PROJECT NAME: Corpus Christi Stage 1 Liquefaction Facility OWNER: Corpus Christi Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 6, 2013 | CHANGE ORDER NUMBER: CO-00004 DATE OF CHANGE ORDER: May 12, 2015 |
1. | The last sentence of paragraph 1 of Change Order CO-00001 is amended and restated to read as follows: “Pricing validity for contractual purposes is May 17, 2015.” |
2. | If NTP of Corpus Christi Liquefaction Stage 1 is delayed beyond May 17, 2015, the cost impact for Stage 1 will be increased by $1,000,000 (one million USD) per Day. |
The original Contract Price was | $ | 7,080,830,000 | |
Net change by previously authorized Change Orders (0001-0002) | $ | 493,147,398 | |
The Contract Price prior to this Change Order was | $ | 7,573,977,398 | |
The Aggregate Equipment Price will be increased by this Change Order in the amount of | $ | — | |
The Aggregate Labor and Skills Price will be increased by this Change Order in the amount of | $ | — | |
The Aggregate Provisional Sum will be unchanged by this Change Order in the amount of | $ | — | |
The new Contract Price including this Change Order will be | $ | 7,573,977,398 |
/s/ Ed Lehotsky | /s/ Maria K. Brady | |
Owner | Contractor | |
Ed Lehotsky | Maria K. Brady | |
Name | Name | |
VP LNG Projects | Senior Vice President | |
Title | Title | |
May 12, 2015 | May 12, 2015 | |
Date of Signing | Date of Signing |