PROJECT
NAME: Sabine Pass LNG Receiving, Storage and
Regasification Terminal
OWNER: Sabine
Pass LNG, L.P.
CONTRACTOR: Bechtel
Corporation
DATE OF AGREEMENT:
December 18, 2004
|
CHANGE ORDER NUMBER:
SP/BE-062
DATE OF CHANGE ORDER:
July 27, 2009
Resolution
of Claims for Final Completion
|
Adjustment
to Contract Price
|
|
The
original Contract Price was
|
$646,936,000
|
Net
change by previously authorized Change Orders (#SP/BE-002 to 028, 031, 033
thru 035; 037 thru 061)
|
$178,217,967
|
The
Contract Price prior to this Change Order was
|
$825,153,967
|
The
Contract Price will be increased by this Change Order in the amount
of
|
$ 727,680
|
The
new Contract Price including this Change Order will be
|
$825,881,647
|
/s/ CHARIF
SOUKI
|
/s/ MITCH
CLAYMAN
|
|
*Charif
Souki
|
Contractor
|
|
Chairman
|
Mitch
Clayman
|
|
August 11, 2009 |
Name
|
|
Date
of Signing
|
Project
Manager
|
|
Title
|
||
August
17, 2009
|
||
/s/ KEITH
TEAGUE
|
Date
of Signing
|
|
*Keith
Teague
|
||
Senior
Vice President
|
||
August 11, 2009 | ||
Date
of Signing
|
||
/s/ ED
LEHOTSKY
|
||
*Ed
Lehotsky
|
||
Owner
Representative
|
||
August 4, 2009 | ||
Date
of Signing
|
T-5007
|
Hexavalent
Chromium
|
T-7021
|
Fence
changes
|
T-7033A
|
LNG
Tank Dike Radar Array
|
T-7044
|
Additional
compensation for craft labor wage increases (over and above CO SP/BE-044,
Trend T-5017) – Based on new forecast
|
T-7045
|
Metering
station Tie-in rework
|
T-7047
|
Additional
Fence Changes
|
T-7050
|
Light
Weight Concrete added to LNG Spill Trench
|
T-7053
|
Concrete
paving around LNG Tank impoundment sumps
|
T-7054
|
Relocate
JB 158 to PL00023 (Tug Berth Parking)
|
T-7056
|
Rework
Culverts at Operations Trailer Road
|
T-7058
|
Added
Curbs and Speed Bumps for LNG Spill Control
|
T-7062
|
Added
Walkways over 2R1 LNG Spill Trench
|
T-7064
|
Red
Concrete Placement over Area Lighting U/G Cables
|
T-7065
|
Wilbros
Costs (Light Pole & Roadwork)
|
T-7072
|
Seismic
Monitoring
|
T-7075
|
Provide
Site Security (4/17/08-6/30/08)
|
N/A
|
Credit
for converting drawings to AutoCADD
|
T-7025
|
Document
turnover – additional Asbuilt drawings
|
T-7063
|
Water
Purchase and Temporary Piping to FW Pond (Lack of JB
Water)
|
T-7066
|
Wetland
Restoration
|
T-7068
|
Nitrogen
Supply – True up of actual costs
|
T-7061
|
Start-up
Group Delay Costs
|
T-7084
|
Additional
Cheniere Emissions Test (Load Bank Rental for three
days)
|
T-7086
|
Credit
for gravel on North Dike @ 4-5 tank N-S dike
intersection
|
T-7087
|
Finish
Grade South of SE corner Tank 1 after the last PI road is
completed
|
T-7089
|
Valtronics
Heat Trace
|
T-7033B
|
LNG
Tank Dike Lighting
|
T-7046
|
Drill
holes in Cryo Check Valves
|
T-7071
|
Water
System Air Gap Skid
|
T-7073
|
Road
Ditches / Drainage
|
N/A
|
Credit
for LNG Tank Gaskets
|
N/A
|
Wind
Damage to Light Poles
|
N/A
|
Vented
Gas from 1st
Cargo through 9/30/2008
|
N/A
|
Noise
at SIS cabinets
|
N/A
|
SVT
Service Rep visit during 4th
Cargo
|