PROJECT
NAME: Sabine Pass LNG Receiving, Storage and
Regasification Terminal
OWNER: Sabine
Pass LNG, L.P.
CONTRACTOR: Bechtel
Corporation
DATE OF AGREEMENT:
December 18, 2004
|
CHANGE ORDER NUMBER:
SP/BE-061
DATE OF CHANGE ORDER:
July 27, 2009
Insurance
and Sales & Use Tax Allowance
Amount Reconciliations
|
Adjustment
to Contract Price
|
|
The
original Contract Price was
|
$646,936,000
|
Net
change by previously authorized Change Orders (#SP/BE-002 to 028, 031, 033
thru 035; 037 thru 060)
|
$182,442,446
|
The
Contract Price prior to this Change Order was
|
$829,378,446
|
The
Contract Price will be increased/decreased by this Change Order in the
amount of
|
$
(4,224,479)
|
The
new Contract Price including this Change Order will be
|
$825,153,967
|
/s/ CHARIF
SOUKI
|
/s/ MITCH
CLAYMAN
|
|
*Charif
Souki
|
Contractor
|
|
Chairman
|
Mitch
Clayman
|
|
August 11, 2009 |
Name
|
|
Date of Signing |
Project
Manager
|
|
Title
|
||
August
17, 2009
|
||
/s/ KEITH
TEAGUE
|
Date
of Signing
|
|
*Keith
Teague
|
||
Senior
Vice President
|
||
August 11, 2009 | ||
Date of Signing
|
||
/s/ ED
LEHOTSKY
|
||
*Ed
Lehotsky
|
||
Owner
Representative
|
||
August 4, 2009 | ||
Date
of Signing
|