PROJECT NAME: |
Sabine Pass LNG Project (Phase 2) |
CHANGE ORDER NUMBER: |
009 |
DATE OF CHANGE ORDER: |
March 26,2009 |
PURCHASER: |
Sabine Pass LNG, L.P. |
SOIL CONTRACTOR: |
Remedial Construction Services, L.P. |
CONTRACT NO. |
25279-004-OC2-C000-00001 |
DATE OF AGREEMENT: |
July 21, 2006 |
The Agreement between the Parties listed above is charged as follows: (attach additional documentation if necessary) |
1) |
Contract Exhibit “C”, Quantities, Pricing and Data, dated March 26, 2009 that supersedes and replaces Exhibit “C”, Quantities, Pricing and Data, dated November 26, 2007 in its entirety. |
2) |
Contract Exhibit “D”, Scope of Work, Revision 2, dated March 26, 2009 that supersedes and replaces Exhibit “D”, Scope of Work, dated September 11, 2007 in its entirety. |
3) |
Contract Exhibit “E-3” Drawings, dated March 26, 2009 which incorporates drawing 25279-001-CS-000-00009 Revision 3 titled Civil Site Development Finished Grade Plan. |
The original contract price was |
$ | 28,526,962.28 | |||
Net Change by previously authorized Change Orders |
$ | -1,744,631.63 | |||
The Contract Price prior to this Change Order |
$ | 26,782,330.65 | |||
The Contract Price will be increased by this Change Order amount of |
$ | 181,100.00 | |||
The New Contract Price including this Change Order will be |
$ | 26,963,430.65 |
Purchaser: |
Soil Contractor: | |
Sabine Pass LNG, L.P. |
Remedial Construction Services, L.P. |
By: |
Sabine Pass LNG-GP, Inc., |
|
Its general partner |
Authorized Signature: |
/s/ Ed Lehotsky |
Authorized Signature: |
/s/ Steven R. Birdwell | |||
Name: |
Ed Lehotsky |
Name: |
Steven R. Birdwell | |||
Title: |
VP LNG Proj Mgt |
Title: |
President | |||
Date of Signing: |
April 3, 2009 |
Date of Signing: |
4-7-2009 |
PROJECT NAME: |
Sabine Pass LNG Project (Phase 2) |
CHANGE ORDER NUMBER: |
010 |
DATE OF CHANGE ORDER: |
March 27, 2009 |
PURCHASER: |
Sabine Pass LNG, L.P. |
SOIL CONTRACTOR: |
Remedial Construction Services, L.P. |
CONTRACT NO. |
25279-004-OC2-C000-00001 |
DATE OF AGREEMENT: |
July 21, 2006 |
The Agreement between the Parties listed above is charged as follows: (attach additional documentation if necessary) |
1) |
Contract Exhibit “B”, Special Conditions, dated March 27, 2009 that supersedes and replaces Exhibit “B”, Special Conditions, dated January 3, 2007 in its entirety. |
2) |
Contract Exhibit “C”, Quantities, Pricing and Data, dated March 27, 2009 that supersedes and replaces Exhibit “C”, Quantities, Pricing and Data, dated March 26, 2009 in its entirety. |
3) |
Contract Exhibit “D-2”, Scope of Work, dated January 14, 2009 which incorporates the scope of work for the LNG Tanks Area Slope Protection and Finished Grade. |
4) |
Contract Exhibit “E-4” Drawings, dated January 14, 2009 which incorporates drawings for the LNG Tanks Area Slope Protection and Finished Grade. |
The original contract price was |
$ | 28,526,962.28 | |||
Net Change by previously authorized Change Orders |
$ | -1,563,531.63 | |||
The Contract Price prior to this Change Order |
$ | 26,963,430.65 | |||
The Contract Price will be increased by this Change Order amount of |
$ | 605,156.85 | |||
The New Contract Price including this Change Order will be |
$ | 27,568,587.50 |
Purchaser: |
Soil Contractor: |
Sabine Pass LNG, L.P. |
Remedial Construction Services, L.P. |
By: |
Sabine Pass LNG-GP, Inc., |
|
Its general partner |
Authorized Signature: |
/s/ Ed Lehotsky |
Authorized Signature: |
/s/ Steven R. Birdwell | |||
Name: |
Ed Lehotsky |
Name: |
Steven R. Birdwell | |||
Title: |
VP LNG Proj Mgt |
Title: |
President | |||
Date of Signing: |
April 3, 2009 |
Date of Signing: |
4-7-2009 |
PROJECT NAME: |
Sabine Pass LNG Project (Phase 2) |
CHANGE ORDER NUMBER: |
011 |
DATE OF CHANGE ORDER: |
March 28, 2009 |
PURCHASER: |
Sabine Pass LNG, L.P. |
SOIL CONTRACTOR: |
Remedial Construction Services, L.P. |
CONTRACT NO. |
25279-004-OC2-C000-00001 |
DATE OF AGREEMENT: |
July 21, 2006 |
The Agreement between the Parties listed above is charged as follows: (attach additional documentation if necessary) |
1) |
Contract Exhibit “C”, Quantities, Pricing and Data, dated March 28, 2009 that supersedes and replaces Exhibit “C”, Quantities, Pricing and Data, dated March 27, 2009 in its entirety. |
2) |
Contract Exhibit “D-3”, Scope of Work, dated December 9, 2008 that incorporates the scope of work for the Asphalt Paving and Asphalt Sealer work. |
3) |
Contract Exhibit “E-5”, Drawings, dated November 8, 2008 that incorporates drawings for the Asphalt Paving and Asphalt Sealer work. |
The original contract price was |
$ | 28,526,962.28 | |||
Net Change by previously authorized Change Orders |
$ | -958,374.78 | |||
The Contract Price prior to this Change Order |
$ | 27,568,587.50 | |||
The Contract Price will be increased by this Change Order amount of |
$ | 590,834.04 | |||
The New Contract Price including this Change Order will be |
$ | 28,159,421.54 |
Purchaser: |
Soil Contractor: | |
Sabine Pass LNG, L.P. |
Remedial Construction Services, L.P. |
By: |
Sabine Pass LNG-GP, Inc., |
|
Its general partner |
Authorized Signature: |
/s/ Ed Lehotsky |
Authorized Signature: |
/s/ Steven R. Birdwell | |||
Name: |
Ed Lehotsky |
Name: |
Steven R. Birdwell | |||
Title: |
VP LNG Proj Mgt |
Title: |
President | |||
Date of Signing: |
April 3, 2009 |
Date of Signing: |
4/7/2009 |
PROJECT NAME: |
Sabine Pass LNG Project (Phase 2) |
CHANGE ORDER NUMBER: |
012 |
DATE OF CHANGE ORDER: |
June 18, 2009 |
PURCHASER: |
Sabine Pass LNG, L.P. |
SOIL CONTRACTOR: |
Remedial Construction Services, L.P. |
CONTRACT NO. |
25279-004-OC2-C000-00001 |
DATE OF AGREEMENT: |
July 21, 2006 |
The Agreement between the Parties listed above is charged as follows: (attach additional documentation if necessary) |
|
● |
Drilling holes on Dike 1 and the North Dike for Tank Dike Access Road Light Poles (CN-027). |
|
● |
Installation of Envirogrid material on Tank S-104 and S-105 Impound Sump slopes (CN-028). |
|
● |
Construction of the corners of each Tank S-104 and S-105 Sump Aprons as described in CN-029. |
|
● |
Construction of the Temporary Containment Berm in Tank S-105 Impoundment Area (CN-030) |
1) |
Contract Exhibit “C”, Quantities, Pricing and Data, dated June 18, 2009 that supersedes and replaces Exhibit “C”, Quantities, Pricing and Data, dated March 28, 2009 in its entirety. |
The original contract price was |
$ | 28,526,962.28 | |||
Net Change by previously authorized Change Orders |
$ | -958,374.78 | |||
The Contract Price prior to this Change Order |
$ | 28,159,421.54 | |||
The Contract Price will be increased by this Change Order amount of |
$ | 39,173.00 | |||
The New Contract Price including this Change Order will be |
$ | 28,198,594.54 |
Purchaser: |
Soil Contractor: | |
Sabine Pass LNG, L.P. |
Remedial Construction Services, L.P. |
By: |
Sabine Pass LNG-GP, Inc., |
|
Its general partner |
Authorized Signature: |
/s/ Ed Lehotsky |
Authorized Signature: |
/s/ Tommy Breaux | |||
Name: |
Ed Lehotsky |
Name: |
Tommy Breaux | |||
Title: |
VP LNG Proj Mgt |
Title: |
Program Manager | |||
Date of Signing: |
23, Jine 2009 |
Date of Signing: |
24 June 2009 |