| 
 May 27, 2009  | ||
| 
 Response Required:  No  x  | 
 | |
| 
 Correspondence   No.     SP2-BE-C-045  | 
| 
 Subject:  | 
 Change Order SP2/BE-011 – Adjustment to Contractor’s Fixed Fee  | 
| 
 Regards,  | ||
| /s/ Carlos Macias | ||
| 
 Carlos Macias  | ||
| 
 Director, Project Management  | ||
| 
 cc:  | 
 Ed Lehotsky  | 
| 
 David Mitchell  | |
| 
 Graham McArthur  | |
| 
 File  | 
| 
 CHANGE ORDER FORM  | 
| 
 PROJECT NAME:  Sabine Pass LNG Phase 2  
Receiving, Storage and Re-Gasification  
Terminal Expansion (“Phase 2 Project”)  | 
 CHANGE ORDER NUMBER: SP2BE-011 
DATE OF CHANGE ORDER: May 5, 2009  | |
| 
 COMPANY: Sabine Pass LNG, L.P.  | 
 ADJUSTMENT TO CONTRACTOR’S FIXED FEE NO#011  | |
| 
 CONTRACTOR: Bechtel Corporation  | 
 | |
| 
 DATE OF AGREEMENT: July 21, 2006  | 
||
| 
 I.  | 
 Increase in the Fixed Fee associated with the implementation of the following agreed Scope Changes:  | 
| 
 1.  | 
 Misc Client Work Orders (Trend F-2010) 
Work Order Request WR-00011 through WR-00024 from January 2008 through June 2008 covering various requests including Cheniere's Sign & Billboard, the Noble Road Repairs and the Water Supply to the Hydrant Pond.  | 
$ | 71,828 | ||||
| 
 2.  | 
 Firewater Monitor Modifications (Trend F-2025) 
Modify firewater design to isolate firewater spray zone actuators to 18 existing valves for both Phase 1 &2. Also valves, including field service to install 6 pneumatic hand actuation of the firewater system for both phases. for each tank by adding add 6" firewater butterfly switches to allow manual  | 
$ | 696,505 | ||||
| 
 3.  | 
 FERC Requested LNG Spill Containment (Trend F-2061) 
FERC required LNG spill containment including concrete curbing and earthen dikes around the AAV and SCV areas.  | 
$ | 62,534 | ||||
| 
 4.  | 
 Bypass for Cool Down of Tanks S-104 and S105 (Trend F-2076) 
Bypasses added to the stop valves to allow a controlled initial cool down to the downstream lines for tanks S-104 and S-105.  | 
$ | 30,961 | ||||
| 
 5.  | 
 Additional Alarms to the UPS from the Metering Station (Trend F-3003) 
Alarms from the metering station routed to the UPS system to allow automatic acknowledgement and mitigation.  | 
$ | 28,340 | ||||
| 
 6.  | 
 Additional Earthen Ramns at Tanks S-104 and S-105 (Trend F-3011) 
New earthen ramps for Perlite truck access to the LNG tanks spill protection area.  | 
$ | 25,928 | ||||
| 
 7.  | 
 2"d N2 Skid Piling and Foundation (Trend F-3021) 
Drive piles and pour the foundation for a 2nd N2 Skid. 1  | 
$ | 38, 980 | ||||
| 
 8.  | 
 Ike Recovery Assistance to SPLNG in the Phase I Area (Trend F-3018) 
Post Hurricane Ike work in the Phase I area to assist SPLNG with their recovery effort. This work scope is in addition to the contractual scope of Phase II.  | 
$ | 121,272 | ||||
| 
 9.  | 
 Use of Rigid Conduit for all Light Stations (Trend F-3019) 
Replace existing %2" aluminum conduit with 3/8" rigid conduit for all light stations per the client's request.  | 
$ | 662,542 | ||||
| 
 10.  | 
 Stage 2A Additional AAVs Engineering (Trend F-3014) 
FEED design of: 4 additional trains of 18 AAVs; a 12" recondenser line from the Phase 1 recondenser to the 22R piperack; and sitework engineering for 7 additional AAV trains.  | 
$ | 1,999,000 | 
| 
 PROJECT NAME:  Sabine Pass LNG Phase 2  
Receiving, Storage and Re-Gasification  
Terminal Expansion (“Phase 2 Project”)  | 
 CHANGE ORDER NUMBER: MBE-011 
DATE OF CHANGE ORDER: May 5, 2009  | |
| 
 COMPANY: Sabine Pass LNG, L.P.  | 
 ADJUSTMENT TO CONTRACTOR’S FIXED FEE NO#011  | |
| 
 CONTRACTOR: Bechtel Corporation  | 
 | |
| 
 DATE OF AGREEMENT: July 21, 2006  | 
| 
 11.  | 
 AAV Train S Crossover Line (Trend F-3034) 
Procure materials and construct a crossover line between the SCVs and AAV Train S.  | 
$ | 591,330 | ||||
| 
 12.  | 
 Vendor Packaged Systems Test & Documentation (Trend F-3036) 
Provide function loop tests for vendor packaged systems and prepare loop documentation packages & signoffs.  | 
$ | 80,000 | ||||
| 
 Total Amount of agreed Scope Changes:  | 
$ | 4,409,220 | |||||
| 
 (Items 1-12 above)  | 
|||||||
| 
 13.  | 
 Change Order SP2BE-010 Carry-Over 
This line item represents the remainder difference of $740,047 not previously included in the Fixed Fee adjustment calculation.  | 
$ | 740,047 | ||||
| 
 Amount Eligible for Fixed Fee Calculation:  | 
$ | 5,149,267 | |||||
| 
 (Items 1-13 above)  | 
|||||||
| 
 14.  | 
 Change Order SP2BE-011 Fixed Fee 
Fixed Fee increases are based on increments of $5,000,000. Consequently, the Fixed Fee increase associated with this Change Order is calculated based on $5,000,000 (4% x $5,000,000) for a total Fixed Fee Adjustment of $200,000. The remaining balance of $149,267 will be added to a future Change Order when the next US$5,000,000 threshold is
achieved.  | 
||||||
| 
 Total Fixed Fee Adjustment Amount:  | 
$ | 200,000 | 
| 
 PROJECT NAME:  Sabine Pass LNG Phase 2  
Receiving, Storage and Re-Gasification  
Terminal Expansion (“Phase 2 Project”)  | 
 CHANGE ORDER NUMBER: SP2BE-011 
DATE OF CHANGE ORDER: May 5, 2009  | |
| 
 COMPANY: Sabine Pass LNG, L.P.  | 
 ADJUSTMENT TO CONTRACTOR’S FIXED FEE NO#011  | |
| 
 CONTRACTOR: Bechtel Corporation  | 
 | |
| 
 DATE OF AGREEMENT: July 21, 2006  | 
||
| 
 ATTACHMENTS:  | 
||
| 
 Attachment A -  | 
 Trend Estimate (F-2010)  | |
| 
 Attachment B -  | 
 Trend Estimate (F-2025)  | |
| 
 Attachment C -  | 
 Trend Estimate (F-2061)  | |
| 
 Attachment D -  | 
 Trend Estimate (F-2076)  | |
| 
 Attachment E -  | 
 Trend Estimate (F-3003)  | |
| 
 Attachment F -  | 
 Trend Estimate (F-3011)  | |
| 
 Attachment G -  | 
 Trend Estimate (F-3019)  | |
| 
 Attachment H -  | 
 Trend Estimate (F-3021)  | |
| 
 Attachment I -  | 
 Trend Estimate (F-3018)  | |
| 
 Attachment J -  | 
 Trend Estimate (F-3014)  | |
| 
 Attachment K -  | 
 Trend Estimate (F-3034)  | |
| 
 Attachment K -  | 
 Trend Estimate (F-3036)  | |
| 
 Attachment L -  | 
 Adjusted Fixed Fee Table  | |
| 
 REFERENCES:  | 
||
| 
 Project Instruction Form SP2-023  | ||
| 
 Project Instruction Form SP2-027  | ||
| 
 SPLNG Correspondence SP-BE-C-269 dated June 19, 2007  | ||
| 
 Adjustment to Contractor's Fixed Fee  | 
||||
| 
 The original Fixed Fee was  | 
$ | 18,500,000 | ||
| 
 Change in Fixed Fee by previously authorized Change Orders  | 
$ | 2,200,000 | ||
| 
 The Fixed Fee prior to this Change Order was  | 
$ | 20,700,000 | ||
| 
 The Fixed Fee will be increased by this Change Order in the amount of  | 
$ | 200,000 | ||
| 
 The new Fixed Fee including this Change Order will be  | 
$ | 20,900,000 | ||
| 
 PROJECT NAME:  Sabine Pass LNG Phase 2  
Receiving, Storage and Re-Gasification  
Terminal Expansion (“Phase 2 Project”)  | 
 CHANGE ORDER NUMBER: SP2BE-011 
DATE OF CHANGE ORDER: May 5, 2009  | |
| 
 COMPANY: Sabine Pass LNG, L.P.  | 
 ADJUSTMENT TO CONTRACTOR’S FIXED FEE NO#011  | |
| 
 CONTRACTOR: Bechtel Corporation  | 
 | |
| 
 DATE OF AGREEMENT: July 21, 2006  | 
||
| 
 /s/ Charif Souki  | 
 /s/ Patrick J. McCormack  | |
| 
 *Charif Souki  | 
 Contractor  | |
| 
 Chairman  | 
 Patrick J. McCormack  | |
| 
 Name  | ||
| 
 May / 20 / 2009  | 
 Project Director  | |
| 
 Date of Signing  | 
 Title  | |
| 
 5/14/09  | ||
| Date of Signing | ||
| 
 /s/ Ed Lehotsky  | 
||
| 
 *Ed Lehotsky  | 
||
| 
 Owner Representative  | 
| May 20, 2009 | ||
| 
 Date of Signing     | 
||
| 
 * Required Owner signature  |